| Owner | Filings | Most Recent |
|---|---|---|
| PRESIDENT ST DEVELOPMENT PARTNER | 21 | 03/21/2026 |
| PSDP LLC | 19 | 07/08/2026 |
| AVERY HALL INVESTMENTS | 5 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| SAG ENGINEERING & CONSULTING, PC | 1 | 09/03/2019 |
| PCS ENGINEERING | 2 | 02/06/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| MANNYRZ | 1 | 03/21/2026 |
| PCS ENGINEERING | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| JEM CONTRACTING CORP | General Contractor | 9 | 07/08/2026 |
| HEADQUARTERS MECH INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SAG ENGINEERING & CONSULT | 608 | 1 | 09/03/2019 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | HEADQUARTERS MECH INC | 09/09/2019 |
| DOB NOW | Supported Scaffold | Signed-off | JEM CONTRACTING CORP | 11/07/2018 |
| DOB NOW | Supported Scaffold | Signed-off | JEM CONTRACTING CORP | 08/07/2018 |
| DOB NOW | Supported Scaffold | Signed-off | JEM CONTRACTING CORP | 05/01/2018 |
| DOB NOW | Supported Scaffold | Signed-off | JEM CONTRACTING CORP | 01/19/2018 |
| DOB NOW | Supported Scaffold | Signed-off | JEM CONTRACTING CORP | 11/29/2017 |
| BIS | OT | ISSUED | NOBLE CONSTRUCTION GR LLC | 10/15/2020 |
| BIS | EQ | ISSUED | CONSOLIDATED SCAFFOLDING | 06/06/2019 |
| BIS | — | RE-ISSUED | NOBLE CONSTRUCTION GR LLC | 05/17/2019 |
| BIS | EQ | ISSUED | CONSOLIDATED SCAFFOLDING | 03/26/2019 |
| BIS | EQ | ISSUED | NOBLE CONSTRUCTION GR LLC | 01/18/2019 |
| BIS | — | ISSUED | NOBLE CONSTRUCTION GR LLC | 12/21/2018 |
| BIS | SD | ISSUED | TRISTATE FIRE SPRINK INC | 10/24/2018 |
| BIS | SD | ISSUED | HEADQUARTERS MECH INC | 07/30/2018 |
| BIS | PL | ISSUED | HEADQUARTERS MECH INC | 07/20/2018 |
| BIS | EQ | ISSUED | CONSOLIDATED SCAFFOLD & BRIDGE | 06/11/2018 |
| BIS | EQ | ISSUED | CONSOLIDATED SCAFFOLD & BRIDGE | 04/10/2018 |
| BIS | EQ | ISSUED | CONSOLIDATED SCAFFOLD & BRIDGE | 04/02/2018 |
| BIS | EQ | ISSUED | JEM CONTRACTING CORP | 02/23/2018 |
| BIS | EQ | ISSUED | NOBLE CONSTRUCTION GR LLC | 02/09/2018 |
| BIS | — | ISSUED | NOBLE CONSTRUCTION GR LLC | 02/02/2018 |
| BIS | EQ | ISSUED | JEM CONTRACTING CORP | 11/28/2017 |
| BIS | EQ | ISSUED | CONSOLIDATED SCAFFOLD & BRIDGE | 10/11/2017 |
| BIS | — | RE-ISSUED | NOBLE CONSTRUCTION GR LLC | 09/21/2017 |
| BIS | — | RE-ISSUED | NOBLE CONSTRUCTION GR LLC | 09/21/2017 |
| BIS | — | RE-ISSUED | NOBLE CONSTRUCTION GR LLC | 08/30/2017 |
| BIS | — | RE-ISSUED | NOBLE CONSTRUCTION GR LLC | 08/30/2017 |
| BIS | SD | ISSUED | HEADQUARTERS MECH INC | 07/27/2017 |
| BIS | PL | ISSUED | HEADQUARTERS MECH INC | 07/19/2017 |
| BIS | EQ | ISSUED | CONSOLIDATED SCAFFOLD & BRIDGE | 06/19/2017 |
| BIS | EQ | ISSUED | CONSOLIDATED SCAFFOLD & BRIDGE | 04/10/2017 |
| BIS | EQ | ISSUED | CONSOLIDATED SCAFFOLD & BRIDGE | 04/03/2017 |
| BIS | EQ | ISSUED | NOBLE CONSTRUCTION GR LLC | 03/03/2017 |
| BIS | — | ISSUED | NOBLE CONSTRUCTION GR LLC | 03/03/2017 |
| BIS | — | ISSUED | NOBLE CONSTRUCTION GR LLC | 03/03/2017 |
| BIS | EQ | ISSUED | ARSENAL SCAFFOLD INC | 09/20/2016 |
| BIS | EQ | ISSUED | ARSENAL SCAFFOLD INC | 09/20/2016 |
| BIS | EQ | ISSUED | ARSENAL SCAFFOLD INC | 09/20/2016 |
| BIS | EQ | ISSUED | ARSENAL SCAFFOLD INC | 09/20/2016 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/24/2018 | Complete | LIPPOLIS ELECTRIC, INC. | 1 meters, 1 new_meters |
| 08/07/2018 | Complete | LIPPOLIS ELECTRIC, INC. | 21 meters, 21 new_meters |
| 01/03/2018 | Complete | LIPPOLIS ELECTRIC, INC. | — |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 02/06/2018 | Final | SILVIAN MARCUS | progress |