RoofUnder Construction64p · 1 filing · 20 docs
ArchitectureMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing
NEW SANITARY PIPING FOR RPZ DRAINAGE, NEW VENT PIPING FOR RPZ DRAIN TRAP, NEW NATURAL GAS PIPING FOR BOILER AND DOMESTIC HOT WATER HEATERS, AND NEW DOMESTIC WATER PIPING FOR WATER SERVICE AND DOMESTIC HOT WATER HEATER INSTALLATION.
On file for this project
70 documents · 5 drawing sheets
Floor 5Under Construction60p · 1 filing · 20 docs
ArchitectureMechanicalPlumbing
Issued Permit Scope
Boiler Equipment · General Construction · Mechanical Systems · Plumbing
NEW SANITARY PIPING FOR RPZ DRAINAGE, NEW VENT PIPING FOR RPZ DRAIN TRAP, NEW NATURAL GAS PIPING FOR BOILER AND DOMESTIC HOT WATER HEATERS, AND NEW DOMESTIC WATER PIPING FOR WATER SERVICE AND DOMESTIC HOT WATER HEATER INSTALLATION.
On file for this project
70 documents · 1 drawing sheet
Floor 4Under Construction59p · 1 filing · 20 docs
ArchitectureMechanicalPlumbing
Issued Permit Scope
Boiler Equipment · General Construction · Mechanical Systems · Plumbing
NEW SANITARY PIPING FOR RPZ DRAINAGE, NEW VENT PIPING FOR RPZ DRAIN TRAP, NEW NATURAL GAS PIPING FOR BOILER AND DOMESTIC HOT WATER HEATERS, AND NEW DOMESTIC WATER PIPING FOR WATER SERVICE AND DOMESTIC HOT WATER HEATER INSTALLATION.
On file for this project
70 documents
Floor 3Under Construction61p · 1 filing · 20 docs
ArchitectureMechanicalPlumbing
Issued Permit Scope
Boiler Equipment · General Construction · Mechanical Systems · Plumbing
NEW SANITARY PIPING FOR RPZ DRAINAGE, NEW VENT PIPING FOR RPZ DRAIN TRAP, NEW NATURAL GAS PIPING FOR BOILER AND DOMESTIC HOT WATER HEATERS, AND NEW DOMESTIC WATER PIPING FOR WATER SERVICE AND DOMESTIC HOT WATER HEATER INSTALLATION.
On file for this project
70 documents · 2 drawing sheets
Floor 2Under Construction60p · 1 filing · 20 docs
ArchitectureMechanicalPlumbing
Issued Permit Scope
Boiler Equipment · General Construction · Mechanical Systems · Plumbing
NEW SANITARY PIPING FOR RPZ DRAINAGE, NEW VENT PIPING FOR RPZ DRAIN TRAP, NEW NATURAL GAS PIPING FOR BOILER AND DOMESTIC HOT WATER HEATERS, AND NEW DOMESTIC WATER PIPING FOR WATER SERVICE AND DOMESTIC HOT WATER HEATER INSTALLATION.
On file for this project
70 documents · 1 drawing sheet
Floor 1Under Construction61p · 1 filing · 20 docs
ArchitectureMechanicalPlumbing
Issued Permit Scope
Boiler Equipment · General Construction · Mechanical Systems · Plumbing
NEW SANITARY PIPING FOR RPZ DRAINAGE, NEW VENT PIPING FOR RPZ DRAIN TRAP, NEW NATURAL GAS PIPING FOR BOILER AND DOMESTIC HOT WATER HEATERS, AND NEW DOMESTIC WATER PIPING FOR WATER SERVICE AND DOMESTIC HOT WATER HEATER INSTALLATION.
On file for this project
70 documents · 2 drawing sheets
CellarUnder Construction65p · 1 filing · 20 docs
ArchitectureDMMechanicalPlumbingStructural
Issued Permit Scope
Boiler Equipment · General Construction · Mechanical Systems · Plumbing
NEW SANITARY PIPING FOR RPZ DRAINAGE, NEW VENT PIPING FOR RPZ DRAIN TRAP, NEW NATURAL GAS PIPING FOR BOILER AND DOMESTIC HOT WATER HEATERS, AND NEW DOMESTIC WATER PIPING FOR WATER SERVICE AND DOMESTIC HOT WATER HEATER INSTALLATION.
On file for this project
70 documents · 6 drawing sheets
Site & exteriorUnder Construction31p · 2 filings · 20 docs
ArchitectureGeneralMechanical
Issued Permit Scope
General Construction · Sidewalk Shed
NEW SANITARY PIPING FOR RPZ DRAINAGE, NEW VENT PIPING FOR RPZ DRAIN TRAP, NEW NATURAL GAS PIPING FOR BOILER AND DOMESTIC HOT WATER HEATERS, AND NEW DOMESTIC WATER PIPING FOR WATER SERVICE AND DOMESTIC HOT WATER HEATER INSTALLATION.
On file for this project
70 documents · 12 drawing sheets
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLAN. NO CHANGE IN USE, EGRESS OR OCCUPANCY. THE SIDEWALK SHED IS AT THE BUILDING FACE AT THE WEST 142ND STREET ELEVATION.
On file for this project
2 documents · 3 drawing sheets