Two family converted from one family
146-16 120 AVENUE
QUEENS · Baisley Park · BIN 4261516
💬 Discuss this project
1899Year Built
1.67Stories
B3Building Class
R3AZoning
1,282 sfGross Floor Area
2Units
1 Open Violation ▸FDNY Report ↗
Two family converted from one family · 3,607 sf lot · 0.36 FAR built · Flood zone X
Locations of Work
Architecture
Attic2p · 1 filing · 7 docs
Floor 12p · 1 filing · 7 docs
Cellar2p · 1 filing · 7 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
SOTIR ASSOCIATES106/01/2023
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
FLAG-CLEAN ISLAND LTDGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SOTIR ASSOCIATES7473106/01/2023
Building Lifecycle
All (9)Filed (1)Permit Issued (1)Signed Off (1)Violation (1)Special Inspection (5)
06/21/2023
Signed off — Alteration
Q00862203-I1
06/14/2023
Permit issued — General Construction
Q00862203-I1-GC
06/01/2023
Filed — Alteration
Q00862203-I1
05/10/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Hany Demetry
05/10/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
Hany Demetry
05/10/2023
Special inspection requirement — Energy Code Compliance Inspections
Hany Demetry
05/10/2023
Special inspection requirement — Lighting in dwelling units
Hany Demetry
04/19/2023
Special inspection requirement — Final
Hany Demetry
05/16/2022
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offFLAG-CLEAN ISLAND LTD06/14/2023
BISOTISSUED1ST LIGHT ENERGY INC07/17/2017
Nothing on file for this building.
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
05/10/2023Fire-Resistant Penetrations and JointsHany Demetryspecial
05/10/2023Structural Stability – Alterations of existing buildingsHany Demetryspecial
05/10/2023Energy Code Compliance InspectionsHany Demetryprogress
05/10/2023Lighting in dwelling unitsHany Demetryenergy_progress
04/19/2023FinalHany Demetryprogress
▾Documents — 20 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/24/2026Q00862203-I1Request digital key ↗
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION1
07/15/2017440419183Open ↗
▸BISWORK PERMIT APPLICATION1
07/15/2017440419183Open ↗
▸Seals & Professional Certifications8
▸DOB NOWProgress Inspector Seal & Signature3
08/26/2026Q00862203-I1Open ↗
08/26/2026Q00862203-I1Open ↗
08/26/2026Q00862203-I1Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
07/15/2017440419183Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
07/15/2017440419183Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
07/15/2017440419183Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026Q00862203-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/26/2026Q00862203-I1Open ↗
▸Safety & Tenant Protection1
▸BISTENANT PROTECTION PLAN AND NOTES1
07/15/2017440419183Open ↗
▸Environmental & Asbestos2
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
07/15/2017440419183Open ↗
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form1
08/13/2026Q00862203-I1Open ↗
▸Energy Compliance3
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
07/15/2017440419183Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
07/15/2017440419183Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
07/15/2017440419183Open ↗
▸Inspections & Test Reports1
▸BISTECHNICAL REPORT: RESPONSIBILITY1
07/15/2017440419183Open ↗
▸Cost, Insurance & Ownership1
▸BISCOST AFFIDAVIT1
07/15/2017440419183Open ↗
▸Filing & Intake Forms1
▸BISEFILING JOB APPLICATION COVER SHEET1
07/15/2017440419183Open ↗