← Back
Banking facility, with or without parking
146-19 JAMAICA AVENUE
QUEENS · Jamaica · BIN 4206758
💬 Discuss this project
1939Year Built
1Stories
K7Building Class
C6-3Zoning
—Gross Floor Area
1Units
6 Open Violations ▸FDNY Report ↗
Banking facility, with or without parking · Owner of record: NORTH FORK BANK · 1.68 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbing
Roof2p · 1 filing · 8 docs
Cellar2p · 1 filing · 13 docs
Sub-Basement1p · 1 filing · 8 docs
Site & exterior3p · 1 filing · 3 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
CAPITAL ONE BANK1803/22/2026
CAPITAL ONE907/08/2026
NORTH FORK BANK403/22/2026
CAPITAL ONE, N.A.203/22/2026
CAPITAL ONE FINANCIAL203/21/2026
JAMAICA SAVINGS BANK103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
NEWTEC ENGINEERING210/28/2024
VINCENT J. LIOTTA P.E.110/04/2022
KZ ENGINEERING, P.C109/18/2020
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SYNERGY BUILDING CONSULTANTS103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
VIVIANO, PAULElectrical203/21/2026
FEDER, IRVINGElectrical203/21/2026
MCPHEE&SON PL-HT-CL CORPPlumbing107/08/2026
CHAPARRO, ANTHONYElectrical103/21/2026
ARSENAL SCAFFOLD INCGeneral Contractor107/08/2026
INTEGRATED HVAC SYS & SVCGeneral Contractor107/08/2026
DECKERT, WILLIAMElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
OBAID MIAN849210/28/2024
VINCENT J. LIOTTA P. E.1974110/04/2022
Building Lifecycle
All (33)Filed (4)Permit Issued (3)Signed Off (2)Violation (11)Inspection (1)Special Inspection (12)
11/07/2024
Inspection — Pass-Final Boiler Equipment Inspection
Pass
View inspection ↗
10/28/2024
Filed — Alteration
This boiler replacement job is being re-filed since the existing BIS filing Job#421643403 can not be reinstated by DOB. There is no new work to be done.
Q00985370-P1
10/28/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
Obaid Mian
10/28/2024
Special inspection requirement — Heating Systems
Obaid Mian
10/28/2024
Special inspection requirement — HVAC-R and service water heating equipment
Obaid Mian
10/28/2024
Special inspection requirement — HVAC-R and service water heating system controls
Obaid Mian
10/28/2024
Special inspection requirement — Maintenance information
Obaid Mian
01/24/2024
Permit issued — Boiler Equipment
Q00985370-I1-BE
01/22/2024
Filed — Alteration
This boiler replacement job is being re-filed since the existing BIS filing Job#421643403 can not be reinstated by DOB. There is no new work to be done.
Q00985370-I1
05/16/2023
Signed off — Alteration
INSTALLATION OF 1.5 TON SPLIT SYSTEM ON THE ROOF AND BASEMENT IT ROOM. NO CHANGE TO EGRESS, USE, OR OCCUPANCY.
Q00713653-I1
01/23/2023
Permit issued — Mechanical Systems
Q00713653-I1-MS
10/04/2022
Filed — Alteration
INSTALLATION OF 1.5 TON SPLIT SYSTEM ON THE ROOF AND BASEMENT IT ROOM. NO CHANGE TO EGRESS, USE, OR OCCUPANCY.
Q00713653-I1
04/06/2022
Special inspection requirement — Maintenance information
Vincent Liotta
04/06/2022
Special inspection requirement — Mechanical Systems
Vincent Liotta
04/06/2022
Special inspection requirement — Final
Vincent Liotta
04/06/2022
Special inspection requirement — HVAC-R and service water heating system controls
Vincent Liotta
04/06/2022
Special inspection requirement — HVAC-R and service water piping design and insulation
Vincent Liotta
04/06/2022
Special inspection requirement — HVAC-R and service water heating equipment
Vincent Liotta
03/10/2021
Violation issued (FDNY_NOV, closed)
10/15/2020
Signed off — Alteration
Installation of temporary construction fence per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.
Q00397869-I1
09/21/2020
Permit issued — Construction Fence
Q00397869-I1-FN
09/18/2020
Filed — Alteration
Installation of temporary construction fence per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.
Q00397869-I1
09/11/2020
Special inspection requirement — Final
Karol Zdancewicz
08/15/2016
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/25/2014
Violation issued (FDNY_NOV, closed)
01/01/2009
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
01/03/2008
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/07/1994
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/28/1993
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
04/07/1992
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
04/25/1991
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
06/29/1990
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
10/12/1989
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWBoiler EquipmentSigned-offBRATERLYN ENTERPRISES DBA01/24/2024
DOB NOWMechanical SystemsSigned-offINTEGRATED HVAC SYS SVC01/23/2023
DOB NOWConstruction FenceSigned-offARSENAL SCAFFOLD INC09/21/2020
BISMHISSUEDGREGOR INDUSTRIES INC02/24/2020
BISOTISSUEDGREGOR INDUSTRIES INC02/24/2020
BISOTISSUEDGREGOR INDUSTRIES INC02/24/2020
BISPLISSUEDM&T PLBG AND HTG CO., INC01/07/2020
BISBLISSUEDMCPHEE&SON PL-HT-CL CORP11/21/2019
BISPLISSUEDMCPHEE&SON PL-HT-CL CORP11/21/2019
BISOTISSUEDGREGOR INDUSTRIES INC06/13/2019
BISOTISSUEDGREGOR INDUSTRIES INC06/13/2019
BISMHISSUEDGREGOR INDUSTRIES INC06/13/2019
BISMHISSUEDPERRY MECHANICAL CONTRACT02/05/2016
BISOTISSUEDGREGOR INDUSTRIES INC07/28/2015
BISMHISSUEDMASTER MECHANICAL CORP07/28/2015
BISOTISSUEDGREGOR INDUSTRIES INC07/28/2015
BIS—ISSUEDAMERICAN SIGN & ELECL CON11/28/2007
BIS—ISSUEDAMERICAN SIGN & ELECL CON11/28/2007
BISMHISSUEDSJS CONSTRUCTION CO., INC.08/21/2002
BISOTISSUEDSJS CONSTRUCTION CO., INC.08/19/2002
BIS—ISSUEDAMERICAN SIGN & ELECL CON05/18/2000
BIS—ISSUEDAMERICAN SIGN & ELECL CON05/18/2000
BISOTISSUEDEGG CONTRACTING INC.03/07/1997
BISMHISSUEDDUAL PURPOSE CORP05/17/1990
BISBLISSUEDMCCREADY & RICE PLUMBING10/06/1989
BISPLISSUEDMCCREADY & RICE PLUMBING10/06/1989
2 projects · most recent 12/13/2019
General Wiring
FiledStatusContractorScope
12/13/2019Permit IssuedA & R ELECTRIC AND CONTRLGeneral Wiring
08/06/2019CompleteA & R ELECTRIC AND CONTRLGeneral Wiring
▾Field Inspections (DOB CAP) — 1
DateTypeResultReport
11/07/2024Pass-Final Boiler Equipment InspectionPassView ↗
▾Special Inspection Requirements (DOB NOW) — 12
DateRequirementInspectorRole
10/28/2024HVAC-R and service water piping design and insulationObaid Mianenergy_progress
10/28/2024Heating SystemsObaid Mianspecial
10/28/2024HVAC-R and service water heating equipmentObaid Mianenergy_progress
10/28/2024HVAC-R and service water heating system controlsObaid Mianenergy_progress
10/28/2024Maintenance informationObaid Mianenergy_progress
04/06/2022Maintenance informationVincent Liottaenergy_progress
04/06/2022Mechanical SystemsVincent Liottaspecial
04/06/2022FinalVincent Liottaprogress
04/06/2022HVAC-R and service water heating system controlsVincent Liottaenergy_progress
04/06/2022HVAC-R and service water piping design and insulationVincent Liottaenergy_progress
04/06/2022HVAC-R and service water heating equipmentVincent Liottaenergy_progress
09/11/2020FinalKarol Zdancewiczprogress
▾Documents — 186 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch3
08/25/2026Q00713653-I1Request digital key ↗
08/23/2026Q00985370-I1Request digital key ↗
08/23/2026Q00985370-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Construction Fence1
08/28/2026Q00397869-I1Request digital key ↗
▸Applications & Permits39
▸BISPLAN / WORK APPROVAL APPLICATION23
04/29/2025402617021Open ↗
02/21/2024402617021Open ↗
01/08/2024402617021Open ↗
Showing 3 of 23 on file for this type
▸BISWORK PERMIT APPLICATION13
02/25/2020421932323Open ↗
02/25/2020421932323Open ↗
02/25/2020421932323Open ↗
Showing 3 of 13 on file for this type
▸DOB NOWLPC Approval/Permit3
08/23/2026Q00985370-I1Open ↗
08/13/2026Q00985370-P1Open ↗
08/13/2026Q00713653-I1Open ↗
▸Seals & Professional Certifications45
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION22
06/24/2019421932323Open ↗
06/24/2019421932323Open ↗
06/24/2019421932323Open ↗
Showing 3 of 22 on file for this type
▸DOB NOWProgress Inspector Seal & Signature7
09/23/2026Q00985370-I1Open ↗
09/23/2026Q00985370-I1Open ↗
09/23/2026Q00985370-I1Open ↗
Showing 3 of 7 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT5
06/24/2019421932323Open ↗
06/24/2019421932323Open ↗
06/24/2019421932323Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/28/2026Q00397869-I1Open ↗
08/23/2026Q00985370-I1Open ↗
08/13/2026Q00985370-P1Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST3
06/24/2019421932323Open ↗
11/27/2018421643403Open ↗
05/08/2017440285763Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
09/23/2026Q00985370-I1Open ↗
09/01/2026Q00713653-I1Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
02/02/2016440285763Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
02/02/2016440285763Open ↗
▸Trade Schedules & Equipment17
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE7
01/06/2020421932323Open ↗
12/20/2019421932323Open ↗
12/05/2019421932323Open ↗
Showing 3 of 7 on file for this type
▸BISEQUIPMENT USE PERMITS4
10/22/2017440285763Open ↗
10/22/2017440285763Open ↗
10/22/2017440285763Open ↗
Showing 3 of 4 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT2
10/19/2017440285763Open ↗
10/19/2016421046745Open ↗
▸BISJAMAICA: DEP SEWER CONNECTION APPROVAL1
02/02/2016440285763Open ↗
▸BISFA - FDNY APPROVAL : FD-FAA1
07/18/2020421219880Open ↗
▸BISWPC-8 - Application for Permit to Install Single/Multiple Premise(s) Sewer House Connection1
08/04/2015421046745Open ↗
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT1
11/27/2018421643403Open ↗
▸Environmental & Asbestos8
▸BISASBESTOS: CERTIFICATION (DEP ACP5)5
06/24/2019421932323Open ↗
11/27/2018421643403Open ↗
02/02/2016440285763Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/23/2026Q00985370-I1Open ↗
08/13/2026Q00985370-P1Open ↗
08/13/2026Q00713653-I1Open ↗
▸Energy Compliance13
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS9
06/24/2019421932323Open ↗
06/24/2019421932323Open ↗
11/27/2018421643403Open ↗
Showing 3 of 9 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
02/02/2016440285763Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
02/02/2016440285763Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
07/03/2017440285763Open ↗
▸DOB NOWPreliminary Commissioning Report Certification1
08/13/2026Q00713653-I1Open ↗
▸Inspections & Test Reports3
▸BISTECHNICAL REPORT: RESPONSIBILITY2
02/17/2024402617021Open ↗
02/02/2016440285763Open ↗
▸BIS* FINAL INSPECTION DIRECTIVE 14 OF 19751
02/22/2024402617021Open ↗
▸Approvals, Objections & Sign-offs15
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST6
02/23/2024402617021Open ↗
10/19/2017440285763Open ↗
07/19/2017440285763Open ↗
Showing 3 of 6 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION5
11/15/2019421932323Open ↗
06/24/2019421932323Open ↗
11/27/2018421643403Open ↗
Showing 3 of 5 on file for this type
▸BISLANDMARKS APPROVAL3
07/22/2016421046745Open ↗
02/02/2016440285763Open ↗
06/11/2015421046745Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
04/17/2015421046745Open ↗
▸Cost, Insurance & Ownership21
▸BISCOST AFFIDAVIT19
02/17/2024402617021Open ↗
11/08/2019421932323Open ↗
10/25/2019421932323Open ↗
Showing 3 of 19 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW32
02/22/2024402617021Open ↗
12/06/2022421219880Open ↗
▸Filing & Intake Forms21
▸BISADDITIONAL INFORMATION10
02/21/2024402617021Open ↗
10/23/2020421932323Open ↗
09/24/2020421932323Open ↗
Showing 3 of 10 on file for this type
▸BISEFILING COVER SHEET8
06/24/2019421932323Open ↗
06/24/2019421932323Open ↗
06/24/2019421932323Open ↗
Showing 3 of 8 on file for this type
▸BISBOROUGH INTAKE FORM2
10/25/2019421932323Open ↗
10/19/2017440285763Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
02/02/2016440285763Open ↗