← Back
One story - permanent living quarter
146-28 183 STREET
💬 Discuss this project
1925Year Built
1Stories
A2Building Class
R3-2Zoning
892 sfGross Floor Area
1Units
One story - permanent living quarter · 4,000 sf lot · 0.22 FAR built · Flood zone X500
Locations of Work
Architecture
Floor 19p · 1 filing · 17 docs
Cellar9p · 1 filing · 17 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
NMI ARCHITECTURE, PLLC203/18/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
NMI ARCHITECTURE PLLC403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
MIGLIORE RESTORATION INCGeneral Contractor207/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
NMI ARCHITECTURE, PLLC6825203/18/2022
Building Lifecycle
All (24)Filed (2)Permit Issued (2)Signed Off (1)Inspection (1)Objection (8)Special Inspection (10)
10/30/2023
Signed off — Alteration
This project is filed for an emergency fire Repair at Cellar, and 1st floor, NO CHANGE OF USE, EGRESS OR OCCUPANCY.
Q00504602-I1
02/14/2023
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
10/05/2022
Permit issued — General Construction
Q00504602-I1-GC
03/23/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
NASHAT IBRAHIM
03/23/2022
Special inspection requirement — Energy Code Compliance Inspections
NASHAT IBRAHIM
03/23/2022
Special inspection requirement — Fenestration air leakage
NASHAT IBRAHIM
03/23/2022
Special inspection requirement — Fenestration and door U-factor and product ratings
NASHAT IBRAHIM
03/23/2022
Special inspection requirement — Insulation placement and R values
NASHAT IBRAHIM
03/18/2022
Filed — Alteration
This project is filed for an emergency fire Repair at Cellar, and 1st floor, NO CHANGE OF USE, EGRESS OR OCCUPANCY.
Q00504602-P1
03/18/2022
Special inspection requirement — Fenestration and door U-factor and product ratings
NASHAT IBRAHIM
03/18/2022
Special inspection requirement — Fenestration air leakage
NASHAT IBRAHIM
03/18/2022
Special inspection requirement — Insulation placement and R values
NASHAT IBRAHIM
03/15/2022
Special inspection requirement — Energy Code Compliance Inspections
NASHAT IBRAHIM
03/15/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
NASHAT IBRAHIM
10/08/2021
Permit issued — General Construction
Q00504602-I1-GC
09/30/2021
Objection resolved — Addressed
09/30/2021
Objection resolved — Addressed
09/23/2021
Objection raised — Scope
09/17/2021
Objection resolved — Addressed
09/17/2021
Objection resolved — Addressed
09/14/2021
Objection raised — Energy
09/14/2021
Objection raised — Fire_Protection
09/14/2021
Objection raised — Fire_Protection
09/08/2021
Filed — Alteration
This project is filed for an emergency fire Repair at Cellar, and 1st floor, NO CHANGE OF USE, EGRESS OR OCCUPANCY.
Q00504602-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offMIGLIORE RESTORATION INC10/05/2022
DOB NOWGeneral ConstructionSigned-offMIGLIORE RESTORATION INC10/08/2021
BISOTISSUEDGREEN STREET POWER PARTNE01/13/2016
Nothing on file for this building.
▾Field Inspections (DOB CAP) — 1
DateTypeResultReport
02/14/2023Pass-Final General Construction Non-Directive 14PassView ↗
▾Special Inspection Requirements (DOB NOW) — 10
DateRequirementInspectorRole
03/23/2022Fire-Resistant Penetrations and JointsNASHAT IBRAHIMspecial
03/23/2022Energy Code Compliance InspectionsNASHAT IBRAHIMprogress
03/23/2022Fenestration air leakageNASHAT IBRAHIMenergy_progress
03/23/2022Fenestration and door U-factor and product ratingsNASHAT IBRAHIMenergy_progress
03/23/2022Insulation placement and R valuesNASHAT IBRAHIMenergy_progress
03/18/2022Fenestration and door U-factor and product ratingsNASHAT IBRAHIMenergy_progress
03/18/2022Fenestration air leakageNASHAT IBRAHIMenergy_progress
03/18/2022Insulation placement and R valuesNASHAT IBRAHIMenergy_progress
03/15/2022Energy Code Compliance InspectionsNASHAT IBRAHIMprogress
03/15/2022Fire-Resistant Penetrations and JointsNASHAT IBRAHIMspecial
▾Documents — 53 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/26/2026Q00504602-P1Request digital key ↗
08/14/2026Q00504602-I1Request digital key ↗
▸Applications & Permits9
▸BISPLAN / WORK APPROVAL APPLICATION8
05/10/2021440281222Open ↗
01/15/2021440281222Open ↗
01/07/2021440281222Open ↗
Showing 3 of 8 on file for this type
▸BISWORK PERMIT APPLICATION1
01/12/2016440281222Open ↗
▸Seals & Professional Certifications15
▸DOB NOWProgress Inspector Seal & Signature8
08/26/2026Q00504602-P1Open ↗
08/26/2026Q00504602-P1Open ↗
08/26/2026Q00504602-P1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/26/2026Q00504602-P1Open ↗
08/26/2026Q00504602-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/26/2026Q00504602-P1Open ↗
08/23/2026Q00504602-I1Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
01/12/2016440281222Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
01/12/2016440281222Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
01/12/2016440281222Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/26/2026Q00504602-P1Open ↗
08/14/2026Q00504602-I1Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
01/12/2016440281222Open ↗
▸Energy Compliance9
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
07/27/2017440281222Open ↗
01/12/2016440281222Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (FINAL)2
02/04/2021440281222Open ↗
07/27/2017440281222Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
07/27/2017440281222Open ↗
▸BISSOLAR TAX ABATEMENT APPLICATION1
01/12/2016440281222Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
01/12/2016440281222Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
01/12/2016440281222Open ↗
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026Q00504602-I1Open ↗
▸Inspections & Test Reports3
▸BISTECHNICAL REPORT: RESPONSIBILITY3
02/04/2021440281222Open ↗
07/27/2017440281222Open ↗
01/12/2016440281222Open ↗
▸Approvals, Objections & Sign-offs3
▸BISThird Party Electrical Signoff Compliance Report1
07/27/2017440281222Open ↗
▸BISUtility Company PV System Interconnection Acknowledgement Letter1
07/27/2017440281222Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
07/27/2017440281222Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
07/27/2017440281222Open ↗
01/12/2016440281222Open ↗
▸Filing & Intake Forms6
▸BISADDITIONAL INFORMATION3
01/22/2021440281222Open ↗
12/18/2020440281222Open ↗
11/17/2017440281222Open ↗
▸BISBOROUGH INTAKE FORM2
02/12/2019440281222Open ↗
11/17/2017440281222Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
01/12/2016440281222Open ↗
▸Other Documents1
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION1
07/27/2017440281222Open ↗