← Back
BuildNYC
Two stories - detached, small or mid-size
146-42 175 STREET
💬 Discuss this project
1920Year Built
1.5Stories
A1Building Class
R3-2Zoning
—Gross Floor Area
1Units
Two stories - detached, small or mid-size · 0.46 FAR built · Flood zone X500
Locations of Work
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Filed — no permit issued1 filing · 10 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Turnier Engineering109/03/2026
Building Lifecycle
All (51)Filed (1)Objection (36)Special Inspection (14)
10/06/2026
Objection resolved — Resolved
10/06/2026
Objection resolved — Open
10/06/2026
Objection resolved — Addressed
10/06/2026
Objection resolved — Addressed
10/06/2026
Objection resolved — Addressed
10/06/2026
Objection resolved — Resolved
10/06/2026
Objection resolved — Resolved
10/06/2026
Objection resolved — Addressed
10/06/2026
Objection resolved — Open
10/06/2026
Objection resolved — Addressed
10/06/2026
Objection resolved — Addressed
10/06/2026
Objection resolved — Open
10/06/2026
Objection resolved — Addressed
10/06/2026
Objection resolved — Addressed
10/06/2026
Objection resolved — Open
10/06/2026
Objection resolved — Addressed
10/06/2026
Objection resolved — Addressed
10/06/2026
Objection resolved — Addressed
09/22/2026
Objection raised — Other
09/22/2026
Objection raised — Energy
09/22/2026
Objection raised — Scope
09/22/2026
Objection raised — Other
09/22/2026
Objection raised — Other
09/22/2026
Objection raised — Other
09/22/2026
Objection raised — Other
09/22/2026
Objection raised — Structural
09/22/2026
Objection raised — Other
09/22/2026
Objection raised — Other
09/22/2026
Objection raised — Other
09/22/2026
Objection raised — Other
09/22/2026
Objection raised — Other
09/22/2026
Objection raised — Other
09/22/2026
Objection raised — Other
09/22/2026
Objection raised — Fire_Protection
09/22/2026
Objection raised — Fire_Protection
09/22/2026
Objection raised — Structural
09/03/2026
Filed — Alteration CO
1st fl lateral enlargement with no enlargement of cellar & 2nd fl lateral enlargement. Convert new enlarged structure into a 2 family dwelling. Provide new foundation for 1st fl enlargement. Obtain new certificate of occupancy.
Q01400958-I1
05/12/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
05/12/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
05/12/2026
Special inspection requirement — Final
05/12/2026
Special inspection requirement — Footing and Foundation
05/12/2026
Special inspection requirement — Fenestration areas
05/12/2026
Special inspection requirement — Fenestration air leakage
05/12/2026
Special inspection requirement — Interior lighting power
05/12/2026
Special inspection requirement — Air barrier - visual inspection
05/12/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
05/12/2026
Special inspection requirement — Insulation placement and R values
05/12/2026
Special inspection requirement — Electric vehicle service equipment requirements
05/12/2026
Special inspection requirement — Maintenance information
05/12/2026
Special inspection requirement — Metering
05/12/2026
Special inspection requirement — Permanent certificate
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
BISOTISSUEDStaten Island Renewable E02/22/2017
BISOTISSUEDStaten Island Renewable E11/03/2016
BISPLISSUEDZara Plumbing08/17/1994
BIS—ISSUEDJack F. Shelly General Contractors06/21/1994
1 project · most recent 09/03/2026
Wood
FiledStatusContractorScope
09/03/2026——Wood
▾Special Inspection Requirements (DOB NOW) — 14
DateRequirementInspectorRole
05/12/2026Fire-Resistant Penetrations and Joints—special
05/12/2026Structural Stability – Alterations of existing buildings—special
05/12/2026Final—progress
05/12/2026Footing and Foundation—progress
05/12/2026Fenestration areas—energy_progress
05/12/2026Fenestration air leakage—energy_progress
05/12/2026Interior lighting power—energy_progress
05/12/2026Air barrier - visual inspection—energy_progress
05/12/2026Fenestration and door U-factor and product ratings—energy_progress
05/12/2026Insulation placement and R values—energy_progress
05/12/2026Electric vehicle service equipment requirements—energy_progress
05/12/2026Maintenance information—energy_progress
05/12/2026Metering—energy_progress
05/12/2026Permanent certificate—energy_progress
▾Documents — 29 on file (BIS + DOB NOW)
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION1
10/25/2016440356730Open ↗
▸BISWORK PERMIT APPLICATION1
10/25/2016440356730Open ↗
▸Zoning, Tax Lot & Property Records1
▸DOB NOWZD1: DOB Zoning Diagram1
10/04/2026Q01400958-I1Open ↗
▸Seals & Professional Certifications4
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
10/25/2016440356730Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
10/25/2016440356730Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
10/25/2016440356730Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
10/04/2026Q01400958-I1Open ↗
▸Safety & Tenant Protection2
▸BISTENANT PROTECTION PLAN AND NOTES1
10/25/2016440356730Open ↗
▸DOB NOWStreet Tree Checklist1
10/04/2026Q01400958-I1Open ↗
▸Environmental & Asbestos2
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
10/25/2016440356730Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
10/04/2026Q01400958-I1Open ↗
▸Energy Compliance6
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
05/01/2017440356730Open ↗
10/25/2016440356730Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
10/25/2016440356730Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
04/27/2017440356730Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
10/25/2016440356730Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (FINAL)1
04/27/2017440356730Open ↗
▸Inspections & Test Reports3
▸BISTECHNICAL REPORT: RESPONSIBILITY2
05/03/2017440356730Open ↗
10/25/2016440356730Open ↗
▸DOB NOWGeotechnical Report (BC 1803.6)1
10/04/2026Q01400958-I1Open ↗
▸Approvals, Objections & Sign-offs2
▸BISUtility Company PV System Interconnection Acknowledgement Letter1
04/27/2017440356730Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
04/27/2017440356730Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
04/27/2017440356730Open ↗
10/25/2016440356730Open ↗
▸Filing & Intake Forms1
▸BISEFILING JOB APPLICATION COVER SHEET1
10/25/2016440356730Open ↗
▸Other Documents4
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
10/04/2026Q01400958-I1Open ↗
▸DOB NOWPlot Diagram1
10/04/2026Q01400958-I1Open ↗
▸DOB NOWProperty Ownership Certification1
10/04/2026Q01400958-I1Open ↗
▸DOB NOWSite Survey: Initial1
10/04/2026Q01400958-I1Open ↗