| Firm | Filings | Most Recent |
|---|---|---|
| A&A CONSULTING ENGINEERS PC | 7 | 07/09/2025 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| HAYDEN BROWN CONS CORP | General Contractor | 10 | 08/14/2026 |
| INFINITI ESC PLUMBING COR | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| A&A CONSULTING ENG. PC | 3252 | 5 | 07/09/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | HAYDEN BROWN CONS CORP | 08/12/2026 |
| DOB NOW | Construction Fence | Signed-off | HAYDEN BROWN CONS | 07/30/2025 |
| DOB NOW | Foundation | Permit Issued | HAYDEN BROWN CONS | 07/29/2025 |
| DOB NOW | Construction Fence | Signed-off | HAYDEN BROWN CONS | 08/27/2024 |
| DOB NOW | General Construction | Permit Issued | HAYDEN BROWN CONS | 08/27/2024 |
| DOB NOW | Plumbing | Signed-off | INFINITI ESC PLUMBING COR | 06/20/2024 |
| DOB NOW | Foundation | Permit Issued | HAYDEN BROWN CONS | 04/22/2024 |
| DOB NOW | Construction Fence | Permit Issued | HAYDEN BROWN CONS | 03/28/2024 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/09/2025 | Signed-off | INFINITI ESC PLUMBING COR | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/07/2024 | Complete | AYYUB ELECTRIC CORP | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/22/2025 | Permit Issued | HAYDEN BROWN CONS CORP | Wood |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/22/2025 | Permit Issued | HAYDEN BROWN CONS CORP | Earthwork |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/06/2026 | Subgrade Inspections | SAEED AINECHI | special |
| 08/06/2026 | Fenestration and door U-factor and product ratings | SAEED AINECHI | energy_progress |
| 08/06/2026 | Air barrier - visual inspection | SAEED AINECHI | energy_progress |
| 08/06/2026 | Fenestration air leakage | SAEED AINECHI | energy_progress |
| 08/06/2026 | Fenestration areas | SAEED AINECHI | energy_progress |
| 08/06/2026 | Lighting in dwelling units | SAEED AINECHI | energy_progress |
| 08/06/2026 | Insulation placement and R values | SAEED AINECHI | energy_progress |
| 08/06/2026 | Structural Wood Frame | SAEED AINECHI | progress |
| 08/06/2026 | Footing and Foundation | SAEED AINECHI | progress |
| 08/06/2026 | Final | SAEED AINECHI | progress |
| 08/06/2026 | Fire-Resistance Rated Construction | SAEED AINECHI | progress |
| 08/06/2026 | Energy Code Compliance Inspections | SAEED AINECHI | progress |
| 08/06/2026 | Concrete - Cast-In-Place | SAEED AINECHI | special |
| 08/06/2026 | Underpinning | SAEED AINECHI | special |
| 08/06/2026 | Excavations - Sheeting, Shoring, and Bracing | SAEED AINECHI | special |
| 08/06/2026 | Structural Stability – Alterations of existing buildings | SAEED AINECHI | special |
| 08/06/2026 | Fire-Resistant Penetrations and Joints | SAEED AINECHI | special |
| 07/30/2025 | Maintenance information | SAEED AINECHI | energy_progress |
| 07/30/2025 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | SAEED AINECHI | special |
| 07/30/2025 | Fire-Resistant Penetrations and Joints | SAEED AINECHI | special |
| 07/30/2025 | Energy Code Compliance Inspections | SAEED AINECHI | progress |
| 07/30/2025 | Metering | SAEED AINECHI | energy_progress |
| 07/30/2025 | Permanent certificate | SAEED AINECHI | energy_progress |
| 07/07/2025 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | SAEED AINECHI | special |
| 07/07/2025 | Energy Code Compliance Inspections | SAEED AINECHI | progress |