| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/13/2024 | — | — | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/17/2024 | Complete | A ELECTRICAL MAIN SVC INC | 3 meters, 3 new_meters |
| 12/12/2023 | Complete | A ELECTRICAL MAIN SVC INC | General Wiring |
| 03/25/2023 | Complete | YORK ELEC'L CONTR'S INC. | 1 meters |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/13/2024 | Permit Issued | GREAT ONE CONSTRUCTION LL | Steel, Wood |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 04/10/2023 | $830K | — | Private party → Private party | $453/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| ALPHA HOME DESIGN LLC | 6 | 11/01/2024 |
| FANG ARCHITECT | 4 | 09/13/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| FANG ARCHITECT | 9 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| GREAT ONE CONSTRUCTION LL | General Contractor | 5 | 07/08/2026 |
| CATMAN PLUMBING INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| YAN GAO | 6619 | 6 | 11/01/2024 |
| FANG ARCHITECT | 5513 | 3 | 09/13/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Earth Work | Permit Issued | GREAT ONE CONSTRUCTION LL | 06/27/2024 |
| DOB NOW | General Construction | Signed-off | GREAT ONE CONSTRUCTION LL | 01/08/2024 |
| DOB NOW | Plumbing | Signed-off | CATMAN PLUMBING INC | 12/05/2023 |
| DOB NOW | General Construction | Signed-off | GREAT ONE CONSTRUCTION LL | 12/05/2023 |
| Date | Type | Result | Report |
|---|---|---|---|
| 11/14/2024 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 09/09/2024 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 09/09/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 01/19/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 01/19/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/01/2024 | Fenestration air leakage | YAN GAO | energy_progress |
| 11/01/2024 | Interior lighting power | YAN GAO | energy_progress |
| 11/01/2024 | Fenestration and door U-factor and product ratings | YAN GAO | energy_progress |
| 11/01/2024 | Fenestration areas | YAN GAO | energy_progress |
| 11/01/2024 | Fire-Resistance Rated Construction | YAN GAO | progress |
| 11/01/2024 | Fire-Resistant Penetrations and Joints | YAN GAO | special |
| 11/01/2024 | Fire-Resistance Rated Construction | YAN GAO | progress |
| 11/01/2024 | Energy Code Compliance Inspections | YAN GAO | progress |
| 11/01/2024 | Insulation placement and R values | YAN GAO | energy_progress |
| 11/01/2024 | Fenestration areas | YAN GAO | energy_progress |
| 11/01/2024 | Fenestration air leakage | YAN GAO | energy_progress |
| 11/01/2024 | Interior lighting power | YAN GAO | energy_progress |
| 11/01/2024 | Fenestration and door U-factor and product ratings | YAN GAO | energy_progress |
| 11/01/2024 | Fire-Resistant Penetrations and Joints | YAN GAO | special |
| 11/01/2024 | Energy Code Compliance Inspections | YAN GAO | progress |
| 11/01/2024 | Insulation placement and R values | YAN GAO | energy_progress |
| 09/13/2024 | Structural Steel - Details | DEZHANG FANG | special |
| 09/13/2024 | Energy Code Compliance Inspections | DEZHANG FANG | progress |
| 09/13/2024 | Final | DEZHANG FANG | progress |
| 09/13/2024 | Fire-Resistance Rated Construction | DEZHANG FANG | progress |
| 09/13/2024 | Footing and Foundation | DEZHANG FANG | progress |
| 09/13/2024 | Insulation placement and R values | DEZHANG FANG | energy_progress |
| 09/13/2024 | Maintenance information | DEZHANG FANG | energy_progress |
| 09/13/2024 | Fenestration and door U-factor and product ratings | DEZHANG FANG | energy_progress |
| 09/13/2024 | Fenestration air leakage | DEZHANG FANG | energy_progress |