← Back
Two stories - detached, small or mid-size
147-12 226 STREET
💬 Discuss this project
1925Year Built
2.5Stories
A1Building Class
R3-1Zoning
1,686 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · 3,600 sf lot · 0.47 FAR built · Flood zone X500
Locations of Work
ArchitectureStructuralElectricalGeneral
Permit Issued — active, not yet Signed-off
RoofUnder Construction1 filing
Floor 2Under Construction1p · 1 filing
Floor 1
Filed — no permit issued9p · 1 filing · 16 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
AYRACON ALMARAZ202/25/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ACA ASSOCIATES203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
TRINITY SOLAR LLCGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BITOPI CONSULTANTS LLC7036202/25/2026
Building Lifecycle
All (8)Filed (2)Permit Issued (1)Special Inspection (5)
02/27/2026
Permit issued — Solar
Q01363836-I1-SL
02/25/2026
Filed — Alteration
Q01363836-I1
02/06/2026
Filed — Alteration
Q01352769-I1
01/28/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
KAMRUL AHSAN
01/28/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
KAMRUL AHSAN
01/28/2026
Special inspection requirement — Energy Code Compliance Inspections
Ayracon Almaraz
01/28/2026
Special inspection requirement — Final
Ayracon Almaraz
01/28/2026
Special inspection requirement — Air barrier - visual inspection
Ayracon Almaraz
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarPermit IssuedTRINITY SOLAR LLC02/27/2026
1 project · most recent 01/27/2026
FiledStatusContractorScope
01/27/2026CancelledREDLINE ELECTRIC INC—
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
01/28/2026Fire-Resistant Penetrations and JointsKAMRUL AHSANspecial
01/28/2026Structural Stability – Alterations of existing buildingsKAMRUL AHSANspecial
01/28/2026Energy Code Compliance InspectionsAyracon Almarazprogress
01/28/2026FinalAyracon Almarazprogress
01/28/2026Air barrier - visual inspectionAyracon Almarazenergy_progress
▾Documents — 16 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/17/2026Q01352769-P2Request digital key ↗
08/17/2026Q01352769-I1Request digital key ↗
▸Seals & Professional Certifications12
▸DOB NOWProgress Inspector Seal & Signature6
08/30/2026Q01352769-I1Open ↗
08/30/2026Q01352769-I1Open ↗
08/30/2026Q01352769-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
08/30/2026Q01352769-I1Open ↗
08/30/2026Q01352769-I1Open ↗
08/23/2026Q01352769-P2Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/17/2026Q01352769-I1Open ↗
08/17/2026Q01352769-P2Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/17/2026Q01352769-I1Open ↗
08/17/2026Q01352769-P2Open ↗