Locations of Work
Electrical
Roof1 filing · 7 docs
Electrical
Issued Permit Scope
Solar
Installation of solar panels, rooftop, railed, grid-tied, 10 modules, 4.1 KW
On file for this project
7 documents
▾Design Consultants (Architect / Engineer of Record)
▾Contractors (License-Anchored)
▾Special Inspection Agencies
| Agency | License # | Filings | Most Recent |
|---|
| MXV SIA LLC | 9281 | 1 | 02/07/2025 |
Nothing on file for this building.
Nothing on file for this building.
Nothing on file for this building.
▾Special Inspection Requirements (DOB NOW) — 5
| Date | Requirement | Inspector | Role |
|---|
| 02/07/2025 | Fire-Resistant Penetrations and Joints | Mina Makar | special |
| 02/07/2025 | Structural Stability – Alterations of existing buildings | Mina Makar | special |
| 02/07/2025 | Energy Code Compliance Inspections | Mina Makar | progress |
| 02/07/2025 | Final | Mina Makar | progress |
| 02/07/2025 | Air barrier - visual inspection | Mina Makar | energy_progress |