1 Open Violation ▸FDNY Report ↗
Two family brick · 0.43 FAR built · Flood zone X500
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
RE STAR EQUITIES303/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
PARKER AND WEST ENGINEERING, PLLC112/15/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SUNRUN103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SUNRUN INSTALLATION SVCGeneral Contractor203/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
PARKER AND WEST ENGINEERI5272112/15/2023
Building Lifecycle
All (10)Filed (1)Permit Issued (1)Signed Off (1)Violation (1)Special Inspection (6)
02/27/2024
Signed off — Alteration
FILING HEREWITH TAX ABATEMENT APPLICATION FOR INSTALLATION OF ROOF MOUNTED SOLAR PANELS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Q00968758-I1
12/27/2023
Permit issued — Solar
Q00968758-I1-SL
12/15/2023
Filed — Alteration
FILING HEREWITH TAX ABATEMENT APPLICATION FOR INSTALLATION OF ROOF MOUNTED SOLAR PANELS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Q00968758-I1
12/15/2023
Special inspection requirement — Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)
Walid Abdulla
11/28/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Walid Abdulla
11/28/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
Walid Abdulla
11/28/2023
Special inspection requirement — Energy Code Compliance Inspections
Walid Abdulla
11/28/2023
Special inspection requirement — Final
Walid Abdulla
11/28/2023
Special inspection requirement — Air barrier - visual inspection
Walid Abdulla
03/26/2010
Violation issued (HPD, open)
A
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offSUNRUN INSTALLATION SVC12/27/2023
BISPLISSUEDFIRST CHOICE PLUMBING COR12/01/2008
BIS—ISSUEDAZCONA, INC04/04/2008
BISPLISSUEDFIRST CHOICE PLBG CORP.10/24/2007
1 project · most recent 12/15/2023
FiledStatusContractorScope
12/15/2023CompleteSUNRUN SOLAR ELECTL CORP—
▾Special Inspection Requirements (DOB NOW) — 6
DateRequirementInspectorRole
12/15/2023Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)Walid Abdullaspecial
11/28/2023Fire-Resistant Penetrations and JointsWalid Abdullaspecial
11/28/2023Structural Stability – Alterations of existing buildingsWalid Abdullaspecial
11/28/2023Energy Code Compliance InspectionsWalid Abdullaprogress
11/28/2023FinalWalid Abdullaprogress
11/28/2023Air barrier - visual inspectionWalid Abdullaenergy_progress
▾Documents — 9 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/23/2026Q00968758-I1Request digital key ↗
▸Seals & Professional Certifications7
▸DOB NOWProgress Inspector Seal & Signature3
08/23/2026Q00968758-I1Open ↗
08/23/2026Q00968758-I1Open ↗
08/23/2026Q00968758-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature3
08/23/2026Q00968758-I1Open ↗
08/23/2026Q00968758-I1Open ↗
08/23/2026Q00968758-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/23/2026Q00968758-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q00968758-I1Open ↗