| Owner | Filings | Most Recent |
|---|---|---|
| NYC School Construction Authority | 114 | 07/08/2026 |
| Generate Hudson Solar | 4 | 03/21/2026 |
| NYC Department of Education | 3 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Eme Consulting Engineering Group | 2 | 12/10/2025 |
| NYMS Consulting | 4 | 12/13/2021 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Central Mechanical Systems | Scaffold | 25 | 07/08/2026 |
| Central Mechanical Systems | specialty_contractor | 10 | 07/08/2026 |
| Cedar Electrical Contractors | Electrical | 1 | 03/21/2026 |
| Charan Electrical Enterp's | Electrical | 1 | 03/22/2026 |
| A & S Electric | Electrical | 1 | 03/21/2026 |
| Enl Mechanical | specialty_contractor | 1 | 04/09/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| JPC Logistics Dba JPCL EN | 351 | 2 | 12/10/2025 |
| Universal Testing and Ins | 400 | 3 | 12/13/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | Central Mechanical System | 03/10/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | Central Mechanical System | 01/08/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | Central Mechanical System | 01/07/2026 |
| DOB NOW | Construction Fence | Permit Issued | Central Mechanical System | 01/07/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Enl Mechanical | 12/19/2025 |
| DOB NOW | Mechanical Systems | Signed-off | Central Mechanical System | 03/26/2025 |
| DOB NOW | Supported Scaffold | Permit Issued | Central Mechanical System | 01/27/2025 |
| DOB NOW | Sidewalk Shed | Permit Issued | Central Mechanical System | 01/08/2025 |
| DOB NOW | Mechanical Systems | Signed-off | Central Mechanical System | 03/27/2024 |
| DOB NOW | Construction Fence | Permit Issued | Central Mechanical System | 01/10/2024 |
| DOB NOW | Supported Scaffold | Permit Issued | Central Mechanical System | 01/10/2024 |
| DOB NOW | Sidewalk Shed | Permit Issued | Central Mechanical System | 01/09/2024 |
| DOB NOW | Mechanical Systems | Signed-off | Central Mechanical System | 10/06/2023 |
| DOB NOW | Mechanical Systems | Signed-off | Central Mechanical System | 04/01/2023 |
| DOB NOW | Sidewalk Shed | Permit Issued | Central Mechanical System | 03/30/2023 |
| DOB NOW | Mechanical Systems | Signed-off | Central Mechanical System | 01/12/2023 |
| DOB NOW | Sidewalk Shed | Permit Issued | Central Mechanical System | 01/05/2023 |
| DOB NOW | Sidewalk Shed | Permit Issued | Central Mechanical System | 01/05/2023 |
| DOB NOW | Construction Fence | Permit Issued | Central Mechanical System | 12/27/2022 |
| DOB NOW | Construction Fence | Permit Issued | Central Mechanical System | 12/06/2022 |
| DOB NOW | Mechanical Systems | Signed-off | Central Mechanical System | 01/10/2022 |
| DOB NOW | Sidewalk Shed | Permit Issued | Central Mechanical System | 01/07/2022 |
| DOB NOW | Boiler Equipment | Signed-off | Champion Combustion | 01/07/2022 |
| DOB NOW | Sidewalk Shed | Permit Issued | Central Mechanical System | 01/03/2022 |
| DOB NOW | Construction Fence | Permit Issued | Central Mechanical System | 12/06/2021 |
| BIS | OT | ISSUED | Central Mechanical Systems | 03/27/2026 |
| BIS | MH | ISSUED | Central Mechanical Systems | 03/27/2026 |
| BIS | OT | ISSUED | Central Mechanical Systems | 03/27/2026 |
| BIS | OT | ISSUED | Central Mechanical Systems | 03/27/2026 |
| BIS | OT | ISSUED | Central Mechanical Systems | 03/11/2026 |
| BIS | MH | ISSUED | Central Mechanical Systems | 03/11/2026 |
| BIS | OT | ISSUED | Central Mechanical Systems | 03/11/2026 |
| BIS | OT | ISSUED | Central Mechanical Systems | 03/11/2026 |
| BIS | MH | ISSUED | Central Mechanical Systems | 03/26/2025 |
| BIS | OT | ISSUED | Central Mechanical Systems | 03/26/2025 |
| BIS | OT | ISSUED | Central Mechanical Systems | 03/26/2025 |
| BIS | OT | ISSUED | Central Mechanical Systems | 03/26/2025 |
| BIS | OT | ISSUED | Central Mechanical Systems | 03/29/2024 |
| BIS | OT | ISSUED | Central Mechanical Systems | 03/29/2024 |
| BIS | OT | ISSUED | Central Mechanical Systems | 03/29/2024 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 12/10/2025 | Permit Issued | Enl Mechanical | Heating and Air Conditioning Systems | Heat / Cool |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/12/2025 | Complete | Charan Electrical Enterp's | — |
| 06/04/2025 | Permit Issued | Lvi NYC Electrical | Lighting |
| 04/25/2025 | Complete | Gemini Electric Co | — |
| 02/02/2024 | Complete | Tower Electric | General Wiring, Lighting |
| 12/30/2022 | Complete | Prince Electric | — |
| 11/21/2022 | Complete | Charan Electrical Enterp's | — |
| 01/06/2022 | Complete | Tower Electric | — |
| 09/27/2021 | Complete | All Systems Electric NY | General Wiring |
| 08/05/2020 | Complete | Charan Electrical Enterp's | — |
| 01/18/2020 | Complete | Laser Electrical Contracting | — |
| 11/27/2019 | Complete | Charan Electrical Enterp's | — |
| 01/07/2019 | Complete | Charan Electrical Enterp's | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/07/2022 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/12/2025 | HVAC-R and service water piping design and insulation | Asma Hashmi | energy_progress |
| 12/12/2025 | HVAC-R and service water heating equipment | Asma Hashmi | energy_progress |
| 12/12/2025 | Fire-Resistant Penetrations and Joints | Asma Hashmi | special |
| 12/12/2025 | Mechanical Systems | Asma Hashmi | special |
| 12/12/2025 | Post-installed Anchors | Asma Hashmi | special |
| 12/12/2025 | Energy Code Compliance Inspections | Asma Hashmi | progress |
| 12/12/2025 | Final | Asma Hashmi | progress |
| 12/12/2025 | HVAC-R and service water heating system controls | Asma Hashmi | energy_progress |
| 12/12/2025 | Maintenance information | Asma Hashmi | energy_progress |
| 12/08/2025 | HVAC-R and service water heating system controls | Asma Hashmi | energy_progress |
| 12/08/2025 | Maintenance information | Asma Hashmi | energy_progress |
| 12/08/2025 | Fire-Resistant Penetrations and Joints | Asma Hashmi | special |
| 12/08/2025 | Mechanical Systems | Asma Hashmi | special |
| 12/08/2025 | Post-installed Anchors | Asma Hashmi | special |
| 12/08/2025 | Energy Code Compliance Inspections | Asma Hashmi | progress |
| 12/08/2025 | Final | Asma Hashmi | progress |
| 12/08/2025 | HVAC-R and service water heating equipment | Asma Hashmi | energy_progress |
| 12/08/2025 | HVAC-R and service water piping design and insulation | Asma Hashmi | energy_progress |
| 11/24/2021 | HVAC-R and service water piping design and insulation | NELSON LOPEZ | energy_progress |
| 11/24/2021 | Mechanical Systems | NELSON LOPEZ | special |
| 11/24/2021 | Final | NELSON LOPEZ | progress |
| 11/24/2021 | Chimneys and vents | NELSON LOPEZ | special |
| 11/24/2021 | Post-installed Anchors | NELSON LOPEZ | special |
| 11/23/2021 | Fuel-Oil Storage and Fuel-Oil Piping Systems | NELSON LOPEZ | special |
| 11/01/2021 | Post-installed Anchors | NELSON LOPEZ | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| P.S. 21 Edward Hart | Education | Floor 1, Roof | Project Q00956352 Project Q00571083 |