| Firm | Filings | Most Recent |
|---|---|---|
| PARKER AND WEST ENGINEERING, PLLC | 1 | 03/19/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| SUNRUN | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SUNRUN INSTALLATION SVC | General Contractor | 2 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| PARKER AND WEST ENGINEERI | 5272 | 1 | 03/19/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | SUNRUN INSTALLATION SVC | 03/31/2025 |
| BIS | OT | ISSUED | FOREST HILLS BUILDERS LLC | 09/02/2011 |
| BIS | PL | ISSUED | ATTACK PLG | 08/18/2005 |
| BIS | PL | ISSUED | CITY TESTING & PLUMBING I | 04/16/2003 |
| BIS | OT | ISSUED | ALMA CONTRACTING | 04/11/2003 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/19/2025 | Complete | SUNRUN SOLAR ELECTL CORP | — |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/14/2025 | Fire-Resistant Penetrations and Joints | Walid Abdulla | special |
| 03/14/2025 | Structural Stability – Alterations of existing buildings | Walid Abdulla | special |
| 03/14/2025 | Energy Code Compliance Inspections | Walid Abdulla | progress |
| 03/14/2025 | Final | Walid Abdulla | progress |
| 03/14/2025 | Air barrier - visual inspection | Walid Abdulla | energy_progress |