DOB11/12/2025The borough commission has ordered all work stop under application # B00550409-I1 immediately due to construction superintendent withdrawal. Stop all work and make site safe.
ECB11/12/2025At the time of inspection, observed a single-family semi-detached building, stalled construction site approx. 9 cubic yards of excessive construction debris stored in the front yard exposure 1. Posing a fire an$12K due
ECB11/12/2025Failure to comply with the commission order to file a certificate of correction with the department of building for notice of violation # 39540774Y issued on 05/29/2025 pursuant to 28-204.4: noted: fence violat$10K due
ECB05/29/2025At the time of inspection of a inactive job site, an excessive amount of combustible debris was observed stored in a pile at exp#1 and exp#2. This accumulation constitutes a fire hazard, posing potential risk t$6K due
ECB05/29/2025At the time of inspection, a construction fence was observed in place under permit number B00571033-I1-fn. The permit expired on 02/19/2022,which is contrary to code requirements.$6K due
ECB05/29/2025At time of inspection, inactive jobsite. Observed, construction fence in place at exp#1 & #2 not built or maintained per bc- fence out of plumb and at risk of collapse. Viewing panel covers missing at exp#1. Th$5K due
ECB04/09/2024Observed excessive debris at front yard, debris consisting of wood, brick , garbage and other debris and materials, this condition pose a tripping hazard, fire hazard and rodent infestation affecting adjacent b$12K due
ECB04/09/2024Observed construction fence in place around all exposures, upon review the department records ( BIS & DOB now) observed that construction fence permit# B00571033 expired on 2/19/2022 and has not been renewed re$6K due
ECB04/11/2023Observed at exp.1/front main entrance, staircase up to 2ND flr & 2ND flr landing/corridor have no railing for protection. While 3-men on premises working against a full swo., provide guard rails$25K due
ECB04/11/2023Observed at exp.1/front, construction fence is defective due to missing viewing panel covers. Also, at exp.2/l. Side, construction fence is currently out of plumb due to leaning onto adjacent property & at the$5K due
ECB04/11/2023Unlawfully continued work while on notice of a stop work order.note:at time of inspection observed 3-men on premises doing construction work sheetrocking throughout interior of 1ST & 2ND fl all contrary to stop$25K due
ECB04/11/2023Observed at exp.1 & 2, excessive combustible/construction debris being stored on premises & scattered throughout. Debris piled up over 4FT(h) creating a haven for vermin & rodents, also a fire hazard to adjacen$12K due
ECB03/20/2023Temporary construction equipment on site - expired construction fence permit. Permit # B00571033-I1-fn expired as of 2/19/2022. No active permits for fence at time of inspection., renew permit$6K due
ECB03/20/2023Failure to maintain building and all parts thereof ina code-compliant maner: observed stalled job site with inactive permits; combustible debris piled at front yard, construction fence warped and leaning at exp$6K due
ECB12/23/2022At the time of inspection of inactive jobsite observed excessive combustible debri stored on site at exp 1 with approx. 30C.y. Of plywood and other combustibles accumulated in a pile and creating a fire hazard$12K due
ECB12/23/2022In response to complaint observed construction fence out of plumb at exp 2 and in danger of collapse under high wind advisory onto adjacent property and cause damage to neighbor property stored in yard. Also ob$12K due
ECB04/21/2022Temp equipment onsite-const fence permit EXPIRED2/19/22.atoi observed 2STYB under const,interior work in progress.doing further research on dobnow&BIS it was noted that const fence permit B00571033-I1-fn expire$6K due
ECB04/21/2022Work w/o permit work permit EXPIRED2/19/22 atoi observed active const on 2STYB,work on 2STY in progress doing further rev&research it was noted permit B00550409-I1-gccx EXPIRED2/19/22.code stips permit shall be$6K due
ECB04/21/2022Failure to institute/maintain safety equipment measure or temp const-no handrailds,no guardrails atoi observed 2STYB under const work on 1&2FL in progress.walking around site following condition noted (1)no han$12K due