← Back
Three families
147 EAST 18 STREET
MANHATTAN · Gramercy · BIN 1017880
💬 Discuss this project
1854Year Built
4Stories
C0Building Class
R8BZoning
3,204 sfGross Floor Area
3Units
Rent Stabilized1 Open Violation ▸
Three families · Owner of record: NEW AMSTERDAM 147 E 18TH ST LLC · 1,733 sf lot · 1.85 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbing
Roof15p · 3 filings · 20 docs
Floor 333p · 3 filings · 20 docs
Floor 256p · 4 filings · 20 docs
Floor 155p · 4 filings · 20 docs
Cellar19p · 3 filings · 20 docs
Sub-Basement12p · 2 filings · 20 docs
Site & exterior3p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NEW AMSTERDAM 147 E 18TH STREET6907/08/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
03/05/2021$4.5M—18 IS ROSIE LLC → NEW AMSTERDAM 147 E 18TH ST LLC$1,404/sf building
06/19/2014$4.1M—— → —$1,280/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
CTHREE ARCHITECTURE + DESIGN, PC807/02/2026
STARTECH ENGINEERING P.C.909/24/2025
STRATFORD ENGINEERING408/05/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
EC BUILDING CONSULTANTS603/21/2026
CTHREE ARCHITECTURE + DESIGN203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
DMA CONTRACTING INCGeneral Contractor2407/08/2026
BLAZE PLUMBING & HEATINGPlumbing307/08/2026
PRO ELECTRIC CORP.Electrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
CTHREE ARCHITECTURE + DES1124505/04/2026
INTEGRITY CONSULTING SERV666109/24/2025
STRATFORD ENGINEERING997408/05/2025
STARTECH ENGINEERING P.C.1041210/27/2022
Building Lifecycle
All (101)Filed (21)Permit Issued (19)Signed Off (5)Violation (9)Inspection (11)Objection (6)Special Inspection (30)
07/08/2026
Special inspection requirement — Energy Code Compliance Inspections
Salvatore Croce
07/08/2026
Special inspection requirement — Final
Salvatore Croce
07/08/2026
Special inspection requirement — Fenestration areas
Salvatore Croce
07/08/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
Salvatore Croce
07/08/2026
Special inspection requirement — Fenestration air leakage
Salvatore Croce
07/02/2026
Filed — Alteration
REPLACEMENT OF ALL EXTERIOR WINDOWS, REAR DOORS, AND ROOF RECOVERING. NO CHANGE TO USE OCCUPANCY OR EGRESS.
M00749975-P2
06/12/2026
Signed off — Alteration
3RD FLOOR CEILING JOIST REINFORCEMENT FOR REMOVAL OF LOAD BEARING WALLS. FILED IN RESPONSE TO ECB VIOLATION NUMBER 39143050J.
M00685854-I1
06/12/2026
Objection resolved — Addressed
06/11/2026
Objection resolved — Addressed
05/21/2026
Objection raised — Other
05/21/2026
Objection raised — Accessibility
05/04/2026
Filed — Alteration
INTERIOR RENOVATION OF EXISTING RESIDENTIAL BUILDING ON CELLAR & BASEMENT LEVEL. REMOVAL OF NON-LOAD BEARING PARTITIONS AND DOORS AND INSTALLATION OF NEW PARTITIONS AND FINISHES . NO CHANGE TO USE ,OCCUPANCY OR EGRESS
M00553529-P1
04/28/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
04/28/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Salvatore Croce
04/28/2026
Special inspection requirement — Energy Code Compliance Inspections
Salvatore Croce
04/28/2026
Special inspection requirement — Final
Salvatore Croce
04/28/2026
Special inspection requirement — Interior lighting power
Salvatore Croce
04/24/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
04/24/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
04/20/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
03/04/2026
Signed off — Alteration
3RD FLOOR CEILING JOIST REINFORCEMENT FOR REMOVAL OF LOAD BEARING WALLS. FILED IN RESPONSE TO ECB VIOLATION NUMBER 39143050J.
M00685854-S1
02/11/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
02/02/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
01/05/2026
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
12/21/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Salvatore Croce
12/21/2025
Special inspection requirement — Energy Code Compliance Inspections
Salvatore Croce
12/21/2025
Special inspection requirement — Final
Salvatore Croce
12/21/2025
Special inspection requirement — Interior lighting power
Salvatore Croce
12/15/2025
Permit issued — Plumbing
M01285612-I1-PL
12/15/2025
Permit issued — Plumbing
M01286754-I1-PL
12/09/2025
Filed — Alteration
3RD FLOOR CEILING JOIST REINFORCEMENT FOR REMOVAL OF LOAD BEARING WALLS. FILED IN RESPONSE TO ECB VIOLATION NUMBER 39143050J.
M00685854-P3
10/28/2025
Objection resolved — Addressed
10/27/2025
Objection raised — Admin
09/24/2025
Filed — Alteration
Alteration involving the installation of a new gas-fired water heater and miscellaneous work.
M01286754-I1
09/24/2025
Filed — Alteration
M01285612-I1
09/22/2025
Special inspection requirement — Tenant Protection Plan Compliance
ALEKSANDR LEVIN
09/19/2025
Permit issued — Structural
M00685854-S1-ST
09/19/2025
Permit issued — General Construction
M00685854-I1-GC
08/22/2025
Permit issued — General Construction
M00685854-I1-GC
08/19/2025
Permit issued — Structural
M00685854-S1-ST
08/05/2025
Filed — Alteration
3RD FLOOR CEILING JOIST REINFORCEMENT FOR REMOVAL OF LOAD BEARING WALLS. FILED IN RESPONSE TO ECB VIOLATION NUMBER 39143050J.
M00685854-P2
08/04/2025
Special inspection requirement — Post-installed Anchors
Xianzhang Chen
08/04/2025
Special inspection requirement — Structural Cold-Formed Steel
Xianzhang Chen
08/04/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Xianzhang Chen
08/04/2025
Special inspection requirement — Structural Steel - Details
Xianzhang Chen
08/04/2025
Special inspection requirement — Structural Steel - High Strength Bolting
Xianzhang Chen
08/04/2025
Special inspection requirement — Final
Xianzhang Chen
06/27/2025
Permit issued — Structural
M00685854-S1-ST
05/29/2025
Filed — Alteration
3RD FLOOR CEILING JOIST REINFORCEMENT FOR REMOVAL OF LOAD BEARING WALLS. FILED IN RESPONSE TO ECB VIOLATION NUMBER 39143050J.
M00685854-P1
04/04/2025
Signed off — Alteration
Installation of a new gas-fired water heater in the cellar and plumbing work on the third-floor bathroom.
M00721016-I1
03/27/2025
Violation issued (ECB, closed)
Construction
03/27/2025
Violation issued (ECB, closed)
Unknown
03/20/2025
Filed — Alteration
3RD FLOOR CEILING JOIST REINFORCEMENT FOR REMOVAL OF LOAD BEARING WALLS. FILED IN RESPONSE TO ECB VIOLATION NUMBER 39143050J.
M00685854-S1
03/19/2025
Filed — Alteration
Installation of a new gas-fired water heater in the cellar and plumbing work on the third-floor bathroom.
M00721016-P4
03/07/2025
Signed off — Alteration
installation of new supporting steel at stair and floor sistering along with roof dunnage
M01051277-I1
02/28/2025
Signed off — Alteration
M00674328-I1
02/26/2025
Permit issued — Structural
M01051277-I1-ST
02/13/2025
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
02/13/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
02/13/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
Latest 60 of 101 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offBLAZE PLUMBING & HEATING12/15/2025
DOB NOWPlumbingSigned-offBLAZE PLUMBING & HEATING12/15/2025
DOB NOWStructuralSigned-offDMA CONTRACTING INC09/19/2025
DOB NOWGeneral ConstructionSigned-offDMA CONTRACTING INC09/19/2025
DOB NOWGeneral ConstructionSigned-offDMA CONTRACTING INC08/22/2025
DOB NOWStructuralSigned-offDMA CONTRACTING INC08/19/2025
DOB NOWStructuralSigned-offDMA CONTRACTING INC06/27/2025
DOB NOWStructuralSigned-offDMA CONTRACTING INC02/26/2025
DOB NOWGeneral ConstructionSigned-offDMA CONTRACTING INC09/06/2024
DOB NOWGeneral ConstructionSigned-offDMA CONTRACTING INC09/05/2024
DOB NOWGeneral ConstructionSigned-offDMA CONTRACTING INC09/05/2024
DOB NOWMechanical SystemsPermit IssuedDMA CONTRACTING INC09/05/2024
DOB NOWGeneral ConstructionSigned-offDMA CONTRACTING INC09/05/2024
DOB NOWPlumbingSigned-offBLAZE PLUMBING & HEATING05/01/2024
DOB NOWGeneral ConstructionSigned-offDMA CONTRACTING INC03/28/2024
DOB NOWGeneral ConstructionSigned-offDMA CONTRACTING INC03/28/2024
DOB NOWMechanical SystemsPermit IssuedDMA CONTRACTING INC03/28/2024
DOB NOWGeneral ConstructionSigned-offDMA CONTRACTING INC03/28/2024
DOB NOWGeneral ConstructionSigned-offDMA CONTRACTING INC03/28/2024
1 project · most recent 10/27/2022
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
10/27/2022Permit IssuedDMA CONTRACTING INCHeating and Air Conditioning Systems
Heat / Cool
Mitsubishi Electric PVFY-P18NAMU-E1 12,000 BTU · Vrf Indoor ×4
1 project · most recent 09/24/2025
Gas Water/Sanitary
FiledStatusContractorScope
09/24/2025Signed-offBLAZE PLUMBING & HEATINGGas, Water/Sanitary
4 projects · most recent 01/09/2025
General Wiring
FiledStatusContractorScope
01/09/2025Permit IssuedE & M ELECTRICAL NY CORPGeneral Wiring
03/20/2024Permit IssuedPRO ELECTRIC CORP.General Wiring
08/16/2023CompletePRO ELECTRIC CORP.General Wiring
09/01/2021Permit IssuedPRO ELECTRIC CORP.General Wiring
1 project · most recent 12/09/2025
Steel
FiledStatusContractorScope
12/09/2025Signed-offDMA CONTRACTING INCSteel
1 project · most recent 09/24/2025
Tenant Protection Plan 72 Hour
FiledStatusContractorScope
09/24/2025Signed-offBLAZE PLUMBING & HEATINGTenant Protection Plan 72 Hour
▾Field Inspections (DOB CAP) — 11
DateTypeResultReport
04/28/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
04/24/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
04/24/2026Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
04/20/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
02/11/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
02/02/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/05/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
02/13/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
02/13/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
02/13/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
09/27/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 48
DateRequirementInspectorRole
07/08/2026Energy Code Compliance InspectionsSalvatore Croceprogress
07/08/2026FinalSalvatore Croceprogress
07/08/2026Fenestration areasSalvatore Croceenergy_progress
07/08/2026Fenestration and door U-factor and product ratingsSalvatore Croceenergy_progress
07/08/2026Fenestration air leakageSalvatore Croceenergy_progress
04/28/2026Fire-Resistant Penetrations and JointsSalvatore Crocespecial
04/28/2026Energy Code Compliance InspectionsSalvatore Croceprogress
04/28/2026FinalSalvatore Croceprogress
04/28/2026Interior lighting powerSalvatore Croceenergy_progress
12/21/2025Fire-Resistant Penetrations and JointsSalvatore Crocespecial
12/21/2025Energy Code Compliance InspectionsSalvatore Croceprogress
12/21/2025FinalSalvatore Croceprogress
12/21/2025Interior lighting powerSalvatore Croceenergy_progress
09/22/2025Tenant Protection Plan ComplianceALEKSANDR LEVINspecial
08/04/2025Post-installed AnchorsXianzhang Chenspecial
08/04/2025Structural Cold-Formed SteelXianzhang Chenspecial
08/04/2025Structural Stability – Alterations of existing buildingsXianzhang Chenspecial
08/04/2025Structural Steel - DetailsXianzhang Chenspecial
08/04/2025Structural Steel - High Strength BoltingXianzhang Chenspecial
08/04/2025FinalXianzhang Chenprogress
05/14/2024Structural Steel - WeldingXianzhang Chenspecial
05/14/2024Structural Steel - High Strength BoltingXianzhang Chenspecial
05/14/2024FinalXianzhang Chenprogress
05/14/2024Structural Cold-Formed SteelXianzhang Chenspecial
05/14/2024Structural Steel - DetailsXianzhang Chenspecial
Latest 25 of 48.
▾Documents — 122 on file (BIS + DOB NOW)
▸Plans & Drawings21
▸DOB NOWPlans/Sketch21
09/03/2026M00553529-I1Request digital key ↗
09/02/2026M00674328-I1Request digital key ↗
09/01/2026M00721033-P1Request digital key ↗
Showing 3 of 21 on file for this type
▸Applications & Permits21
▸DOB NOWLPC Approval/Permit21
09/01/2026M00749975-P2Open ↗
09/01/2026M00749975-I1Open ↗
08/14/2026M00553529-P1Open ↗
Showing 3 of 21 on file for this type
▸Seals & Professional Certifications55
▸DOB NOWProgress Inspector Seal & Signature27
09/02/2026M00749975-P1Open ↗
09/02/2026M00749975-P1Open ↗
09/02/2026M00749975-P1Open ↗
Showing 3 of 27 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature21
09/03/2026M00553529-P1Open ↗
09/02/2026M00674328-I1Open ↗
09/01/2026M00721033-P1Open ↗
Showing 3 of 21 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature7
09/01/2026M01051277-I1Open ↗
09/01/2026M00721033-P1Open ↗
09/01/2026M01286754-I1Open ↗
Showing 3 of 7 on file for this type
▸Environmental & Asbestos19
▸DOB NOWDEP ACP-5: Asbestos Assessment Report18
09/02/2026M00674328-I1Open ↗
09/01/2026M00721033-P1Open ↗
09/01/2026M00721033-I1Open ↗
Showing 3 of 18 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form1
09/01/2026M00749975-I1Open ↗
▸Energy Compliance2
▸DOB NOWEN2: As Built Energy Analysis2
08/22/2026M00685854-I1Open ↗
08/13/2026M00674328-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWLandmark Approval1
08/13/2026M00749975-I1Open ↗
▸Other Documents3
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone3
09/01/2026M00749975-P2Open ↗
08/13/2026M00749975-I1Open ↗
08/13/2026M00749975-P1Open ↗