← Back
Elevator apt, fireproof without stores
Jameco Park
148-15 89 AVENUE · Jamaica · BIN 4310504
💬 Discuss this project
2023Year Built
8Stories
D3Building Class
R7XZoning
52,996 sfGross Floor Area
69Units
Rent Stabilized4 Open Violations ▸FDNY Report ↗
Elevator apt, fireproof without stores · Owner of record: 89 AVE HOLDINGS LLC · 13,675 sf lot · 3.88 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionEquipmentLandscapeCivilGeneral
Roof1 filing
Floor 11 filing
Site & exterior4 filings
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
RUBIN EQUITIES6107/08/2026
OWNERS REP1107/08/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
06/13/2022$5.3M—Private party → 89 AVE REALTY LLC— not available
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
EXPEDITING 4 U1903/21/2026
AE DESIGN SOLUTION1203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ON STAR MANAGEMENT LLCGeneral Contractor2107/08/2026
CORE SCAFFOLD SYSTEMS INC.General Contractor1007/08/2026
S WIEDER ARCHITECT P CGeneral Contractor303/22/2026
PRIME PIPING & HEATING INFire Protection307/08/2026
A. M. PLUMBING COMPANYPlumbing107/08/2026
SHMUEL WIEDERElectrical103/21/2026
BLZ ELECTRIC INC 001756General Contractor103/22/2026
PAUL LEFKOWITZElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HRF SERVICES CORP56161406/05/2024
Building Lifecycle
All (162)Filed (25)Permit Issued (16)Signed Off (13)Violation (12)Inspection (20)Objection (46)Special Inspection (30)
07/02/2026
Violation issued (HPD, open)
B
07/02/2026
Violation issued (HPD, open)
B
03/23/2026
Violation issued (FDNY_NOV, closed)
03/23/2026
Violation issued (FDNY_NOV, closed)
03/23/2026
Violation issued (FDNY_NOV, closed)
11/21/2025
Violation issued (HPD, closed)
I
10/07/2025
Violation issued (HPD, closed)
C
05/20/2025
Violation issued (FDNY_NOV, closed)
05/20/2025
Violation issued (FDNY_NOV, closed)
06/14/2024
Special inspection requirement — Insulation placement and R values
FAHAD FATEH
06/14/2024
Special inspection requirement — Energy Code Compliance Inspections
FAHAD FATEH
06/14/2024
Special inspection requirement — Protection of exposed foundation insulation
FAHAD FATEH
06/14/2024
Special inspection requirement — Fenestration areas
FAHAD FATEH
06/14/2024
Special inspection requirement — Metering
FAHAD FATEH
06/14/2024
Special inspection requirement — Interior lighting power
FAHAD FATEH
06/14/2024
Special inspection requirement — Maintenance information
FAHAD FATEH
06/14/2024
Special inspection requirement — Electrical motors and elevators
FAHAD FATEH
06/14/2024
Special inspection requirement — Air barrier continuity plan testing
FAHAD FATEH
06/14/2024
Special inspection requirement — Exterior lighting power
FAHAD FATEH
06/14/2024
Special inspection requirement — Lighting controls
FAHAD FATEH
06/14/2024
Special inspection requirement — Air barrier - visual inspection
FAHAD FATEH
06/14/2024
Special inspection requirement — Fenestration and door U-factor and product ratings
FAHAD FATEH
06/14/2024
Special inspection requirement — Fenestration air leakage
FAHAD FATEH
06/14/2024
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
FAHAD FATEH
06/14/2024
Special inspection requirement — Fire-Resistance Rated Construction
FAHAD FATEH
06/14/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
06/14/2024
Special inspection requirement — Lighting in dwelling units
FAHAD FATEH
06/05/2024
Filed — New Building
PROPOSED NEW EIGHT STORY AND CELLAR RESIDENTIAL BUILDING.
Q00718735-A2
06/05/2024
Special inspection requirement — Energy Code Compliance Inspections
FAHAD FATEH
06/05/2024
Special inspection requirement — Protection of exposed foundation insulation
FAHAD FATEH
06/05/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
06/05/2024
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
FAHAD FATEH
06/05/2024
Special inspection requirement — Air barrier continuity plan testing
FAHAD FATEH
06/05/2024
Special inspection requirement — Exterior lighting power
FAHAD FATEH
06/05/2024
Special inspection requirement — Fenestration areas
FAHAD FATEH
06/05/2024
Special inspection requirement — Interior lighting power
FAHAD FATEH
06/05/2024
Special inspection requirement — Fenestration air leakage
FAHAD FATEH
06/05/2024
Special inspection requirement — Electrical motors and elevators
FAHAD FATEH
06/05/2024
Special inspection requirement — Maintenance information
FAHAD FATEH
06/05/2024
Special inspection requirement — Lighting controls
FAHAD FATEH
05/21/2024
Violation issued (HPD, open)
C
05/21/2024
Violation issued (HPD, open)
C
05/21/2024
Violation issued (HPD, closed)
B
12/21/2023
Signed off — New Building
PROPOSED NEW EIGHT STORY AND CELLAR RESIDENTIAL BUILDING.
Q00718735-S4
12/21/2023
Signed off — Alteration
Q00727647-I1
11/27/2023
Filed — New Building
PROPOSED NEW EIGHT STORY AND CELLAR RESIDENTIAL BUILDING.
Q00718735-A1
11/10/2023
Signed off — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Q00819933-I1
11/10/2023
Signed off — Alteration
INSTALLATION OF TEMPORARY ROOF PROTECTION AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Q00819944-I1
11/10/2023
Signed off — Alteration
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Q00819914-I1
11/10/2023
Signed off — Alteration
INSTALLATION OF TEMPORARY OVERHEAD PROTECTION AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Q00819950-I1
10/24/2023
Signed off — Alteration
CURB CUT APPLICATION FILED IN CONJUNCTION WITH NEW BUILDING JOB #Q00718735.
Q00728788-I1
10/17/2023
Inspection — Pass-Final Curb Cut Non-Directive 14
Pass
View inspection ↗
09/29/2023
Permit issued — Curb Cut
Q00728788-I1-CC
09/28/2023
Filed — New Building
PROPOSED NEW EIGHT STORY AND CELLAR RESIDENTIAL BUILDING.
Q00718735-P9
09/21/2023
Signed off — New Building
PROPOSED NEW EIGHT STORY AND CELLAR RESIDENTIAL BUILDING.
Q00718735-S6
09/14/2023
Signed off — New Building
PROPOSED NEW EIGHT STORY AND CELLAR RESIDENTIAL BUILDING.
Q00718735-S5
09/11/2023
Inspection — Pass-Final SD - Up to 9 Requested Floors
Pass
View inspection ↗
09/07/2023
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
09/06/2023
Inspection — Certified StandPipe-SD-Piping-Hydrostatic Test
Certified
View inspection ↗
09/04/2023
Signed off — New Building
PROPOSED NEW EIGHT STORY AND CELLAR RESIDENTIAL BUILDING.
Q00718735-S7
Latest 60 of 162 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWCurb CutSigned-offON STAR MANAGEMENT LLC09/29/2023
DOB NOWConstruction FenceSigned-offON STAR MANAGEMENT LLC06/07/2023
DOB NOWMechanical SystemsSigned-offON STAR MANAGEMENT LLC03/14/2023
DOB NOWStructuralSigned-offON STAR MANAGEMENT LLC03/14/2023
DOB NOWSprinklersSigned-offA M B MECHANICAL INC02/03/2023
DOB NOWSprinklersSigned-offA M B MECHANICAL INC02/03/2023
DOB NOWPlumbingSigned-offA. M. PLUMBING COMPANY02/02/2023
DOB NOWSidewalk ShedSigned-offCORE SCAFFOLD SYSTEMS INC01/30/2023
DOB NOWProtection and Mechanical MethodsSigned-offCORE SCAFFOLD SYSTEMS INC01/30/2023
DOB NOWSupported ScaffoldSigned-offCORE SCAFFOLD SYSTEMS INC01/30/2023
DOB NOWProtection and Mechanical MethodsSigned-offCORE SCAFFOLD SYSTEMS INC01/30/2023
DOB NOWGeneral ConstructionPermit IssuedON STAR MANAGEMENT LLC01/26/2023
DOB NOWStandpipeSigned-offA M B MECHANICAL INC01/25/2023
DOB NOWEarth WorkSigned-offON STAR MANAGEMENT LLC12/20/2022
DOB NOWSupport of ExcavationSigned-offON STAR MANAGEMENT LLC12/07/2022
DOB NOWConstruction FenceSigned-offON STAR MANAGEMENT LLC06/10/2022
1 project · most recent 06/05/2024
Air Conditioning Systems Heating Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
06/05/2024Signed-offON STAR MANAGEMENT LLCAir Conditioning Systems, Heating Systems, Ventilation Systems
Cooling
Mitsubishi Electric MXZ-SM36NAM 36,000 BTU · Condensing Unit ×136
MXZ-SM36NAM-U1 36,000 BTU · Condensing Unit ×4
MXZ-SM60NAM-U1 60,000 BTU · Condensing Unit ×2
PUHY-P72TNU-A 72,000 BTU · Vrf Outdoor ×2
PUZ-A12NKA7 12,000 BTU · Condensing Unit ×2
Heating
Mitsubishi Electric MXZ-SM36NAM 42,000 BTU · Condensing Unit ×136
MXZ-SM36NAM-U1 42,000 BTU · Condensing Unit ×4
MXZ-SM60NAM-U1 66,000 BTU · Condensing Unit ×2
PUHY-P72TNU-A 80,000 BTU · Vrf Outdoor ×2
PUZ-A12NKA7 14,000 BTU · Condensing Unit ×2
Ventilation
Greenheck G-080-VG 240 CFM · Exhaust Fan ×18
CUE-080-VG 210 CFM · Kitchen Exhaust ×16
G-090-VG 420 CFM · Exhaust Fan ×6
CUE-095-VG 390 CFM · Kitchen Exhaust ×2
SP-110-VG 110 CFM · Kitchen Exhaust ×2
SP-80-VG 80 CFM · Exhaust Fan ×2
1 project · most recent 06/05/2024
Sprinkler System
FiledStatusContractorScope
06/05/2024Signed-offPRIME PIPING & HEATING INSprinkler System
1 project · most recent 06/05/2024
Storm Water/Sanitary
FiledStatusContractorScope
06/05/2024Signed-offA. M. PLUMBING COMPANYStorm, Water/Sanitary
5 projects · most recent 11/27/2025
General Wiring
FiledStatusContractorScope
11/27/2025CompleteBLZ ELECTRIC INC.General Wiring
09/26/2023CompleteTFK ELECTRIC CORPGeneral Wiring
05/04/2023CompletePOWER DIRECT ELECTRIC INC—
02/20/2023CompleteTFK ELECTRIC CORP—
01/30/2023CompleteSOLAS ELECTRICAL CORP—
1 project · most recent 06/05/2024
Concrete
FiledStatusContractorScope
06/05/2024Signed-offON STAR MANAGEMENT LLCConcrete
▾Field Inspections (DOB CAP) — 20
DateTypeResultReport
10/17/2023Pass-Final Curb Cut Non-Directive 14PassView ↗
09/11/2023Pass-Final SD - Up to 9 Requested FloorsPassView ↗
09/07/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
09/06/2023Certified StandPipe-SD-Piping-Hydrostatic TestCertifiedView ↗
08/24/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
08/24/2023Fail-Final SD - Up to 9 Requested FloorsFailView ↗
08/24/2023Fail-Final SP - Up to 9 Requested FloorsFailView ↗
08/21/2023Fail-Final SP - Up to 9 Requested FloorsFailView ↗
08/21/2023Pass-Final SD - Up to 9 Requested FloorsPassView ↗
08/18/2023Pass-Final CND-Occupancy InspectionPassView ↗
08/15/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
08/10/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
08/10/2023Certified StandPipe-SD-Piping-Hydrostatic TestCertifiedView ↗
06/05/2023Certified StandPipe - SD - Alarm Sys 64/09 - FinishCertifiedView ↗
06/05/2023Certified StandPipe - SD - Hydrostatic 63/09 Test (100 Foot Increments)CertifiedView ↗
06/02/2023Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet)CertifiedView ↗
05/22/2023Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
03/09/2023Pass-Final House ConnectionPassView ↗
02/15/2023Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
02/15/2023Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 148
DateRequirementInspectorRole
06/14/2024Maintenance informationFAHAD FATEHenergy_progress
06/14/2024MeteringFAHAD FATEHenergy_progress
06/14/2024Air barrier - visual inspectionFAHAD FATEHenergy_progress
06/14/2024Insulation placement and R valuesFAHAD FATEHenergy_progress
06/14/2024Lighting controlsFAHAD FATEHenergy_progress
06/14/2024Lighting in dwelling unitsFAHAD FATEHenergy_progress
06/14/2024Electrical motors and elevatorsFAHAD FATEHenergy_progress
06/14/2024Protection of exposed foundation insulationFAHAD FATEHenergy_progress
06/14/2024Air barrier continuity plan testingFAHAD FATEHenergy_progress
06/14/2024Fenestration and door U-factor and product ratingsFAHAD FATEHenergy_progress
06/14/2024Exterior lighting powerFAHAD FATEHenergy_progress
06/14/2024Fenestration areasFAHAD FATEHenergy_progress
06/14/2024Exterior Insulation and Finish Systems (EIFS)FAHAD FATEHspecial
06/14/2024Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
06/14/2024Fire-Resistance Rated ConstructionFAHAD FATEHprogress
06/14/2024Energy Code Compliance InspectionsFAHAD FATEHprogress
06/14/2024Fenestration air leakageFAHAD FATEHenergy_progress
06/14/2024Interior lighting powerFAHAD FATEHenergy_progress
06/05/2024Lighting in dwelling unitsFAHAD FATEHenergy_progress
06/05/2024Fenestration and door U-factor and product ratingsFAHAD FATEHenergy_progress
06/05/2024MeteringFAHAD FATEHenergy_progress
06/05/2024Lighting controlsFAHAD FATEHenergy_progress
06/05/2024Fenestration air leakageFAHAD FATEHenergy_progress
06/05/2024Exterior lighting powerFAHAD FATEHenergy_progress
06/05/2024Air barrier continuity plan testingFAHAD FATEHenergy_progress
Latest 25 of 148.
▾Documents — 178 on file (BIS + DOB NOW)
▸Plans & Drawings25
▸DOB NOWPlans/Sketch25
08/26/2026Q00727647-I1Request digital key ↗
08/25/2026Q00718735-S3Request digital key ↗
08/25/2026Q00718735-S4Request digital key ↗
Showing 3 of 25 on file for this type
▸Applications & Permits5
▸BISPLAN / WORK APPROVAL APPLICATION3
06/27/2023440726886Open ↗
06/21/2023440726886Open ↗
05/26/2022440726886Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation2
12/15/2022440726886Open ↗
05/26/2022440726886Open ↗
▸Zoning, Tax Lot & Property Records11
▸DOB NOWZD1: DOB Zoning Diagram5
08/13/2026Q00718735-I1Open ↗
08/13/2026Q00718735-A2Open ↗
08/13/2026Q00718735-P1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWZoning Exhibit form (1-5)5
08/13/2026Q00718735-P9Open ↗
08/13/2026Q00718735-P1Open ↗
08/13/2026Q00718735-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026Q00718735-I1Open ↗
▸Seals & Professional Certifications78
▸DOB NOWProgress Inspector Seal & Signature28
09/29/2026Q00718735-S2Open ↗
09/29/2026Q00718735-S2Open ↗
09/29/2026Q00718735-S2Open ↗
Showing 3 of 28 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature25
08/25/2026Q00718735-I1Open ↗
08/25/2026Q00718735-S1Open ↗
08/25/2026Q00718735-S2Open ↗
Showing 3 of 25 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature22
09/29/2026Q00718735-S2Open ↗
09/29/2026Q00718735-S2Open ↗
09/29/2026Q00718735-S2Open ↗
Showing 3 of 22 on file for this type
▸BISAPPLICANT OWNER SIGNATURE2
05/26/2022440726886Open ↗
05/26/2022440726886Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
05/26/2022440726886Open ↗
▸Trade Schedules & Equipment1
▸DOB NOWStandpipe Alarms Drawings1
08/13/2026Q00718735-I1—
▸Safety & Tenant Protection11
▸DOB NOWStreet Tree Checklist5
08/13/2026Q00718735-P5Open ↗
08/13/2026Q00718735-P1Open ↗
08/13/2026Q00718735-A2Open ↗
Showing 3 of 5 on file for this type
▸BISSTREET TREE SIGNOFF1
05/21/2024440726886Open ↗
▸BISBPP: STREET TREES SITE PLAN1
12/15/2022440726886Open ↗
▸BISSTREET TREE CHECKLIST1
05/26/2022440726886Open ↗
▸DOB NOWStreet Trees Site Plan1
08/13/2026Q00718735-I1Open ↗
▸DOB NOWStreet Tree Sign Off1
08/13/2026Q00718735-I1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026Q00718735-I1Open ↗
▸Environmental & Asbestos16
▸DOB NOWOER: Notice to Proceed8
08/13/2026Q00718735-S2Open ↗
08/13/2026Q00718735-S5Open ↗
08/13/2026Q00718735-I1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWOER: Notice of Satisfaction6
08/13/2026Q00718735-S2Open ↗
08/13/2026Q00718735-A2Open ↗
08/13/2026Q00718735-S3Open ↗
Showing 3 of 6 on file for this type
▸BISENVIRONMENTAL RESTRICTIONS - OER NOTICE OF SATISFACTION1
05/21/2024440726886Open ↗
▸BISENVIRONMENTAL RESTRICTIONS - OER NOTICE TO PROCEED1
12/15/2022440726886Open ↗
▸Energy Compliance3
▸DOB NOWPreliminary Commissioning Report Certification2
08/13/2026Q00718735-S4Open ↗
08/13/2026Q00718735-S5Open ↗
▸DOB NOWEN2: As Built Energy Analysis1
08/13/2026Q00718735-I1Open ↗
▸Inspections & Test Reports3
▸DOB NOWSOIL REPORT2
08/13/2026Q00718735-S2Open ↗
08/13/2026Q00718735-P3Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026Q00718735-S2Open ↗
▸Filing & Intake Forms6
▸BISADDITIONAL INFORMATION4
07/05/2023440726886Open ↗
12/15/2022440726886Open ↗
05/26/2022440726886Open ↗
Showing 3 of 4 on file for this type
▸BISBPP: CHECKLIST IN LIEU OF PLANS-ALT31
05/26/2022440726886Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
05/26/2022440726886Open ↗
▸Other Documents19
▸DOB NOWSite Survey: Initial5
08/13/2026Q00718735-P1Open ↗
08/13/2026Q00718735-P5Open ↗
08/13/2026Q00718735-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone5
08/13/2026Q00718735-P5Open ↗
08/13/2026Q00718735-I1Open ↗
08/13/2026Q00718735-P1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWProperty Ownership Certification5
08/25/2026Q00718735-P5Open ↗
08/25/2026Q00718735-P9Open ↗
08/25/2026Q00718735-A2Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWAdjoining Owners Notification2
08/13/2026Q00718735-S1Open ↗
08/13/2026Q00718735-S2Open ↗
▸BISBPP: PHOTOS-SIGNED/SEALED BY APPLICANT1
12/14/2022440726886Open ↗
▸DOB NOWFinal Survey1
08/13/2026Q00718735-I1Open ↗