Two stories - detached, small or mid-size
148-18 LABURNUM AVENUE
QUEENS · East Flushing · BIN 4123977
💬 Discuss this project
1920Year Built
2Stories
A1Building Class
R2AZoning
1,306 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · 4,000 sf lot · 0.33 FAR built · Flood zone X
Locations of Work
Electrical
Roof1p · 1 filing · 8 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TRINITY SOLAR LLC201/12/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ACA ASSOCIATES203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
REDLINE ELECTRIC INCElectrical103/22/2026
TRINITY SOLAR LLCGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BITOPI CONSULTANTS LLC7036201/12/2026
Building Lifecycle
All (8)Filed (2)Permit Issued (1)Signed Off (1)Special Inspection (4)
01/13/2026
Signed off — Alteration
Installation of solar system on the roof as per plan. No change in use, egress or occupancy
Q01192849-I1
01/12/2026
Filed — Alteration
Installation of solar system on the roof as per plan. No change in use, egress or occupancy
Q01192849-P1
01/12/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
KAMRUL AHSAN
01/12/2026
Special inspection requirement — Energy Code Compliance Inspections
Ayracon Almaraz
01/12/2026
Special inspection requirement — Final
Ayracon Almaraz
01/12/2026
Special inspection requirement — Air barrier - visual inspection
Ayracon Almaraz
03/19/2025
Permit issued — Solar
Q01192849-I1-SL
03/12/2025
Filed — Alteration
Installation of solar system on the roof as per plan. No change in use, egress or occupancy
Q01192849-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offTRINITY SOLAR LLC03/19/2025
1 project · most recent 03/06/2025
FiledStatusContractorScope
03/06/2025CompleteREDLINE ELECTRIC INC—
▾Special Inspection Requirements (DOB NOW) — 4
DateRequirementInspectorRole
01/12/2026Fire-Resistant Penetrations and JointsKAMRUL AHSANspecial
01/12/2026Energy Code Compliance InspectionsAyracon Almarazprogress
01/12/2026FinalAyracon Almarazprogress
01/12/2026Air barrier - visual inspectionAyracon Almarazenergy_progress
▾Documents — 11 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/20/2026Q01192849-I1Request digital key ↗
08/20/2026Q01192849-P1Request digital key ↗
▸Seals & Professional Certifications6
▸DOB NOWProgress Inspector Seal & Signature3
09/02/2026Q01192849-P1Open ↗
09/02/2026Q01192849-P1Open ↗
09/02/2026Q01192849-P1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/20/2026Q01192849-I1Open ↗
08/20/2026Q01192849-P1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
09/02/2026Q01192849-P1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/20/2026Q01192849-I1Open ↗
08/20/2026Q01192849-P1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01192849-I1Open ↗