| Owner | Filings | Most Recent |
|---|---|---|
| NJH Properties | 3 | 07/08/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| MB Architect | 5 | 09/25/2024 |
| KZ Engineering | 2 | 09/06/2023 |
| Royal T&E | 1 | 11/29/2018 |
| Frank Petruso Architect | 1 | 08/13/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| Synergy Building Consultants | 2 | 03/21/2026 |
| Danico Services | 2 | 03/21/2026 |
| Frank Petrusoarchitect P | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Yafe Meod | Scaffold | 5 | 07/08/2026 |
| Yafe Meod | General Contractor | 3 | 03/21/2026 |
| Gul & G Contracting | Scaffold | 3 | 03/21/2026 |
| CS Bridge | Scaffold | 2 | 04/08/2026 |
| Artistic Design | Scaffold | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| George J. Xerakias, PE | 1658 | 2 | 01/08/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Construction Fence | Permit Issued | Yafe Meod | 02/03/2026 |
| DOB NOW | Construction Fence | Permit Issued | Yafe Meod | 12/09/2024 |
| DOB NOW | Full Demolition | Signed-off | Yafe Meod | 12/20/2023 |
| DOB NOW | Construction Fence | Signed-off | Yafe Meod | 09/22/2023 |
| DOB NOW | Supported Scaffold | Signed-off | CS Bridge | 09/07/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | CS Bridge | 09/07/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | Gul & G Contracting | 11/29/2018 |
| DOB NOW | Construction Fence | Signed-off | Artistic Design | 09/19/2018 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/31/2023 | Complete | Nash Electric Services | — |
| 11/20/2018 | Complete | WCK Electric | — |
| 09/24/2018 | Complete | Stellmann Electrical | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/08/2024 | Signed-off | Yafe Meod | Fence |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/08/2025 | Duct leakage testing, insulation and design | — | energy_progress |
| 06/09/2024 | Protection of exposed foundation insulation | — | energy_progress |
| 05/31/2024 | Air barrier - visual inspection | — | energy_progress |
| 05/02/2024 | Energy Code Compliance Inspections | — | progress |
| 05/02/2024 | Fire-Resistance Rated Construction | — | progress |
| 05/02/2024 | Metering | — | energy_progress |
| 05/02/2024 | Fenestration areas | — | energy_progress |
| 05/02/2024 | Permanent certificate | — | energy_progress |
| 05/02/2024 | HVAC-R and service water heating equipment | — | energy_progress |
| 05/02/2024 | Air barrier — testing | — | energy_progress |
| 05/02/2024 | Shutoff dampers | — | energy_progress |
| 05/02/2024 | Insulation placement and R values | — | energy_progress |
| 05/02/2024 | HVAC-R and service water heating system controls | — | energy_progress |
| 05/02/2024 | Ventilation and air distribution system | — | energy_progress |
| 05/02/2024 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 05/02/2024 | Maintenance information | — | energy_progress |
| 05/02/2024 | Interior lighting power | — | energy_progress |
| 05/02/2024 | Exterior lighting power | — | energy_progress |
| 05/02/2024 | Fenestration air leakage | — | energy_progress |
| 05/02/2024 | Exterior Insulation and Finish Systems (EIFS) | — | special |
| 05/02/2024 | Fire-Resistant Penetrations and Joints | — | special |
| 05/02/2024 | Fenestration and door U-factor and product ratings | — | energy_progress |
| 05/02/2024 | Lighting controls | — | energy_progress |
| 04/18/2024 | Final | — | progress |
| 04/18/2024 | Mechanical Systems | — | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Atlantic Ship Agencies | Industrial / Warehouse | Floor 1 | Project Q01117449 Project Q00929016 Project Q00929019 Project Q00859438 Project Q00069101 |