| Owner | Filings | Most Recent |
|---|---|---|
| Kamali Organization | 3 | 07/08/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 06/26/2024 | $1.6M | — | — → — | $605/sf building |
| 04/24/2023 | $600K | — | MARVEK DEVELOPMENT LLC → Private party | $233/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| Arnold Montag Architect AM/PM Desi | 2 | 03/22/2024 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Kaieteur Construction | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Afm Inspections & Engineering | 4675 | 1 | 09/02/2021 |
| Arnold Montag Architect | 4599 | 2 | 09/02/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Permit Issued | Kaieteur Construction | 01/27/2025 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/03/2025 | Complete | Ayyub Electric | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/22/2024 | Permit Issued | Kaieteur Construction | Concrete, Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/11/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/14/2022 | Concrete - Cast-In-Place | — | special |
| 09/14/2022 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | — | special |
| 09/14/2022 | Subgrade Inspections | — | special |
| 09/14/2022 | Wall Panels, Curtain Walls, and Veneers | — | special |
| 09/14/2022 | Final | — | progress |
| 09/14/2022 | Fire-Resistance Rated Construction | — | progress |
| 09/14/2022 | Footing and Foundation | — | progress |
| 09/14/2022 | Structural Wood Frame | — | progress |