1968Year Built
2Stories
C0Building Class
R3-1Zoning
2,162 sfGross Floor Area
3Units
Three families · 3,180 sf lot · 0.68 FAR built · Flood zone X500
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
PARKER AND WEST ENGINEERING, PLLC103/04/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SUNRUN103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SUNRUN INSTALLATION SVCGeneral Contractor203/21/2026
SUNRUN SOLAR ELECTL CORPElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
PARKER AND WEST ENGINEERI5272103/04/2024
Building Lifecycle
All (9)Filed (1)Permit Issued (1)Signed Off (1)Special Inspection (6)
05/13/2024
Signed off — Alteration
Q01010836-I1
03/20/2024
Permit issued — Solar
Q01010836-I1-SL
03/04/2024
Filed — Alteration
Q01010836-I1
03/04/2024
Special inspection requirement — Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)
Walid Abdulla
02/26/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Walid Abdulla
02/26/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
Walid Abdulla
02/26/2024
Special inspection requirement — Energy Code Compliance Inspections
Walid Abdulla
02/26/2024
Special inspection requirement — Final
Walid Abdulla
02/26/2024
Special inspection requirement — Air barrier - visual inspection
Walid Abdulla
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offSUNRUN INSTALLATION SVC03/20/2024
1 project · most recent 03/04/2024
FiledStatusContractorScope
03/04/2024CompleteSUNRUN SOLAR ELECTL CORP—
▾Special Inspection Requirements (DOB NOW) — 6
DateRequirementInspectorRole
03/04/2024Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)Walid Abdullaspecial
02/26/2024Fire-Resistant Penetrations and JointsWalid Abdullaspecial
02/26/2024Structural Stability – Alterations of existing buildingsWalid Abdullaspecial
02/26/2024Energy Code Compliance InspectionsWalid Abdullaprogress
02/26/2024FinalWalid Abdullaprogress
02/26/2024Air barrier - visual inspectionWalid Abdullaenergy_progress
▾Documents — 10 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/23/2026Q01010836-I1Request digital key ↗
▸Seals & Professional Certifications7
▸DOB NOWProgress Inspector Seal & Signature3
08/23/2026Q01010836-I1Open ↗
08/23/2026Q01010836-I1Open ↗
08/23/2026Q01010836-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature3
08/23/2026Q01010836-I1Open ↗
08/23/2026Q01010836-I1Open ↗
08/23/2026Q01010836-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026Q01010836-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026Q01010836-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01010836-I1Open ↗