← Back
Walk-up apt, over six families with stores
149 LUDLOW STREET
MANHATTAN · BIN 1005356
💬 Discuss this project
1900Year Built
5Stories
C7Building Class
C4-4AZoning
6,940 sfGross Floor Area
9Units
Rent Stabilized0 Open Violations
Walk-up apt, over six families with stores · Owner of record: 149 LUDLOW TENANTS INC. · 2,188 sf lot · 3.17 FAR built · Flood zone X
Locations of Work
ArchitectureStructural
Floor 55p · 2 filings · 20 docs
Floor 44p · 1 filing · 20 docs
Floor 35p · 1 filing · 20 docs
Floor 24p · 1 filing · 20 docs
Floor 15p · 1 filing · 20 docs
Cellar6p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
149 LUDLOW TENANTS3303/22/2026
149 LUDLOW ST OWNERS203/21/2026
HOQUE CONSTRUCTION103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TAN ENGINEERING PC708/12/2026
ADG ARCHITECTURE AND DESIGN PC507/10/2026
SW ENGINEERING COMPANY111/14/2025
M C STRUCTURAL ENGINEERING208/27/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ADG903/21/2026
ADG ARCHITECTURE DESIGN603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
BELLWOOD NY INCGeneral Contractor607/08/2026
A + SPRINKLER CORPFire Protection107/08/2026
VMC PLUMBING & HEATING INPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
TAN ENGINEERING, P.C.1291508/12/2026
SWL ENGINEERING INSPECTIO6912111/14/2025
M C STRUCTURAL ENGINEERIN4890408/27/2024
Building Lifecycle
All (92)Filed (15)Permit Issued (8)Signed Off (5)Violation (15)Inspection (7)Objection (12)Special Inspection (30)
08/17/2026
Signed off — Alteration CO
Scope of work will include re-supporting stair/well- case putting structure under tenants wall putting steel beam and basement footings as indicated on plans.
M00614840-S2
08/17/2026
Special inspection requirement — HVAC-R and service water heating equipment
Roger Tan
08/17/2026
Special inspection requirement — HVAC-R and service water heating system controls
Roger Tan
08/17/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Roger Tan
08/17/2026
Special inspection requirement — Final
Roger Tan
08/17/2026
Special inspection requirement — Mechanical Systems
Roger Tan
08/14/2026
Signed off — Alteration CO
Scope of work will include re-supporting stair/well- case putting structure under tenants wall putting steel beam and basement footings as indicated on plans.
M00614840-S4
08/12/2026
Filed — Alteration CO
Scope of work will include re-supporting stair/well- case putting structure under tenants wall putting steel beam and basement footings as indicated on plans.
M00614840-P8
07/23/2026
Special inspection requirement — Seismic Resistance of Plumbing, Mechanical, Fuel Gas, and Electrical Components
07/16/2026
Signed off — Alteration CO
Scope of work will include re-supporting stair/well- case putting structure under tenants wall putting steel beam and basement footings as indicated on plans.
M00614840-S1
07/10/2026
Filed — Alteration CO
Scope of work will include re-supporting stair/well- case putting structure under tenants wall putting steel beam and basement footings as indicated on plans.
M00614840-P9
04/09/2026
Inspection — Fail-Final Boiler Equipment Inspection
Fail
View inspection ↗
03/19/2026
Filed — Alteration CO
Scope of work will include re-supporting stair/well- case putting structure under tenants wall putting steel beam and basement footings as indicated on plans.
M00614840-P7
02/03/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
02/02/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
01/30/2026
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
01/20/2026
Signed off — Alteration
Scope of work will include framing work for the 5th FL as indicated on plans .
M01292219-I1
01/20/2026
Signed off — Alteration CO
Scope of work will include re-supporting stair/well- case putting structure under tenants wall putting steel beam and basement footings as indicated on plans.
M00614840-S3
01/16/2026
Permit issued — Structural
M01292219-I1-GC
01/14/2026
Special inspection requirement — Sprinkler Systems
Roger Tan
01/12/2026
Filed — Alteration CO
Scope of work will include re-supporting stair/well- case putting structure under tenants wall putting steel beam and basement footings as indicated on plans.
M00614840-P5
01/08/2026
Filed — Alteration CO
Scope of work will include re-supporting stair/well- case putting structure under tenants wall putting steel beam and basement footings as indicated on plans.
M00614840-P6
12/29/2025
Permit issued — Structural
M01292219-I1-ST
12/22/2025
Objection resolved — Addressed
12/16/2025
Permit issued — Sprinklers
M00614840-S4-EW-SP
11/25/2025
Objection raised — Scope
11/14/2025
Filed — Alteration
Scope of work will include framing work for the 5th FL as indicated on plans .
M01292219-I1
10/28/2025
Special inspection requirement — Structural Steel - High Strength Bolting
JOSHUA LUCKRITZ
10/28/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
JOSHUA LUCKRITZ
10/28/2025
Special inspection requirement — Structural Steel - Details
JOSHUA LUCKRITZ
09/29/2025
Permit issued — Mechanical Systems
M00614840-S2-MS
09/24/2025
Special inspection requirement — Final
Levon Shaginyan
06/27/2025
Permit issued — General Construction
M00614840-I1-GC
05/29/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
04/30/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
04/04/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
12/16/2024
Permit issued — Plumbing
M00614840-S1-PL
11/14/2024
Filed — Alteration CO
Scope of work will include re-supporting stair/well- case putting structure under tenants wall putting steel beam and basement footings as indicated on plans.
M00614840-P3
11/14/2024
Filed — Alteration CO
Scope of work will include re-supporting stair/well- case putting structure under tenants wall putting steel beam and basement footings as indicated on plans.
M00614840-P2
10/29/2024
Permit issued — General Construction
M00614840-I1-GC
10/03/2024
Permit issued — Structural
M00614840-S3-ST
08/27/2024
Filed — Alteration CO
Scope of work will include re-supporting stair/well- case putting structure under tenants wall putting steel beam and basement footings as indicated on plans.
M00614840-P4
08/27/2024
Special inspection requirement — Structural Steel - Details
MICKEY WING KWAN CHAN
08/27/2024
Special inspection requirement — Concrete - Cast-In-Place
MICKEY WING KWAN CHAN
08/27/2024
Special inspection requirement — Subgrade Inspections
MICKEY WING KWAN CHAN
08/27/2024
Special inspection requirement — Final
MICKEY WING KWAN CHAN
08/27/2024
Special inspection requirement — Structural Steel - Welding
MICKEY WING KWAN CHAN
08/27/2024
Special inspection requirement — Post-installed Anchors
MICKEY WING KWAN CHAN
08/27/2024
Special inspection requirement — Structural Steel - High Strength Bolting
MICKEY WING KWAN CHAN
08/27/2024
Special inspection requirement — Structural Cold-Formed Steel
MICKEY WING KWAN CHAN
08/14/2024
Special inspection requirement — Final
MICKEY WING KWAN CHAN
08/14/2024
Special inspection requirement — Sprinkler Systems
Roger Tan
08/14/2024
Special inspection requirement — Mechanical Systems
Roger Tan
08/14/2024
Special inspection requirement — Final
Roger Tan
08/14/2024
Special inspection requirement — HVAC-R and service water heating equipment
Roger Tan
08/14/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
Roger Tan
08/14/2024
Special inspection requirement — HVAC-R and service water heating system controls
Roger Tan
08/14/2024
Special inspection requirement — Concrete - Cast-In-Place
MICKEY WING KWAN CHAN
08/14/2024
Special inspection requirement — Post-installed Anchors
MICKEY WING KWAN CHAN
08/14/2024
Special inspection requirement — Structural Cold-Formed Steel
MICKEY WING KWAN CHAN
Latest 60 of 92 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWStructuralSigned-offBELLWOOD NY INC01/16/2026
DOB NOWStructuralSigned-offBELLWOOD NY INC12/29/2025
DOB NOWSprinklersSigned-offA + SPRINKLER CORP12/16/2025
DOB NOWMechanical SystemsSigned-offBELLWOOD NY INC09/29/2025
DOB NOWGeneral ConstructionPermit IssuedBELLWOOD NY INC06/27/2025
DOB NOWPlumbingSigned-offM. SPINELLI PLB & HTG INC12/16/2024
DOB NOWGeneral ConstructionPermit IssuedBELLWOOD NY INC10/29/2024
DOB NOWStructuralSigned-offBELLWOOD NY INC10/03/2024
BISEQISSUEDROCKLEDGE SCAFFOLD CORP01/23/2014
BISOTISSUEDPRESERV BLD RESTOR MGT IN11/14/2013
BISEQISSUEDROCKLEDGE SCAFFOLD CORP10/11/2013
BISEQISSUEDROCKLEDGE SCAFFOLD CORP12/26/2012
BISEQISSUEDROCKLEDGE SCAFFOLD CORP11/23/2011
BISEQISSUEDROCKLEDGE SCAFFOLD CORP12/14/2010
BISEQISSUEDJ & G GENERAL CONTRACTING05/24/2010
BISOTISSUEDDBA HOUSE OF A DIFFERENT COLOR01/15/2002
BISEQISSUEDHI-TECH BRIDGING, INC03/28/2001
1 project · most recent 08/12/2026
Air Conditioning Systems Others
FiledStatusContractorScopeMake / Model / Capacity
08/12/2026Signed-offBELLWOOD NY INCAir Conditioning Systems, Others
Other
Greenheck Greenheck SP-B110 75 CFM · Exhaust Fan ×3
Greenheck SQ-90-VG 350 CFM · Exhaust Fan ×3
Ventus Vent-US TT250 880 CFM · Exhaust Fan ×3
Cooling
Fujitsu AOU30RGLX 32,000 BTU · Heat Pump Outdoor ×1
AOU36RGLX 36,000 BTU · Heat Pump Outdoor ×1
AOU48RGLX 530,000 BTU · Heat Pump Outdoor ×1
1 project · most recent 08/12/2026
FiledStatusContractorScope
08/12/2026Signed-offA + SPRINKLER CORP162 heads
1 project · most recent 08/12/2026
Water/Sanitary
FiledStatusContractorScope
08/12/2026Signed-offM. SPINELLI PLB & HTG INCWater/Sanitary
4 projects · most recent 02/22/2026
General Wiring
FiledStatusContractorScope
02/22/2026CompleteJP & SON ELECTRIC CORPGeneral Wiring
10/22/2025CompleteJP & SON ELECTRIC CORPGeneral Wiring
11/01/2022CompleteSWITCH ELECT OF THE FIVEGeneral Wiring
08/05/2020Permit IssuedJP & SON ELECTRIC CORPGeneral Wiring
1 project · most recent 08/12/2026
Steel Concrete
FiledStatusContractorScope
08/12/2026Signed-offA + SPRINKLER CORPSteel, Concrete
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
04/09/2026Fail-Final Boiler Equipment InspectionFailView ↗
02/03/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
02/02/2026Pass-Final CND-Occupancy InspectionPassView ↗
01/30/2026Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
05/29/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
04/30/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
04/04/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 34
DateRequirementInspectorRole
08/17/2026HVAC-R and service water heating equipmentRoger Tanenergy_progress
08/17/2026HVAC-R and service water heating system controlsRoger Tanenergy_progress
08/17/2026HVAC-R and service water piping design and insulationRoger Tanenergy_progress
08/17/2026FinalRoger Tanprogress
08/17/2026Mechanical SystemsRoger Tanspecial
07/23/2026Seismic Resistance of Plumbing, Mechanical, Fuel Gas, and Electrical Components—special
01/14/2026Sprinkler SystemsRoger Tanspecial
10/28/2025Structural Steel - High Strength BoltingJOSHUA LUCKRITZspecial
10/28/2025Structural Stability – Alterations of existing buildingsJOSHUA LUCKRITZspecial
10/28/2025Structural Steel - DetailsJOSHUA LUCKRITZspecial
09/24/2025FinalLevon Shaginyanprogress
08/27/2024Structural Steel - DetailsMICKEY WING KWAN CHANspecial
08/27/2024Concrete - Cast-In-PlaceMICKEY WING KWAN CHANspecial
08/27/2024Subgrade InspectionsMICKEY WING KWAN CHANspecial
08/27/2024FinalMICKEY WING KWAN CHANprogress
08/27/2024Structural Steel - WeldingMICKEY WING KWAN CHANspecial
08/27/2024Post-installed AnchorsMICKEY WING KWAN CHANspecial
08/27/2024Structural Steel - High Strength BoltingMICKEY WING KWAN CHANspecial
08/27/2024Structural Cold-Formed SteelMICKEY WING KWAN CHANspecial
08/14/2024FinalMICKEY WING KWAN CHANprogress
08/14/2024Sprinkler SystemsRoger Tanspecial
08/14/2024Mechanical SystemsRoger Tanspecial
08/14/2024FinalRoger Tanprogress
08/14/2024HVAC-R and service water heating equipmentRoger Tanenergy_progress
08/14/2024HVAC-R and service water piping design and insulationRoger Tanenergy_progress
Latest 25 of 34.
▾Documents — 194 on file (BIS + DOB NOW)
▸Plans & Drawings15
▸DOB NOWPlans/Sketch15
08/25/2026M00614840-P1Request digital key ↗
08/25/2026M00614840-S4Request digital key ↗
08/25/2026M00614840-I1Request digital key ↗
Showing 3 of 15 on file for this type
▸Applications & Permits21
▸BISPLAN / WORK APPROVAL APPLICATION13
06/29/2018123211390Open ↗
03/22/2018123211390Open ↗
02/12/2018123211390Open ↗
Showing 3 of 13 on file for this type
▸BISWORK PERMIT APPLICATION8
01/27/2014120557487Open ↗
11/18/2013121632634Open ↗
10/10/2013140121883Open ↗
Showing 3 of 8 on file for this type
▸Zoning, Tax Lot & Property Records1
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026M00614840-I1Open ↗
▸Seals & Professional Certifications71
▸DOB NOWSpecial Inspector Seal & Signature19
09/29/2026M01292219-I1Open ↗
09/01/2026M00614840-S2Open ↗
09/01/2026M00614840-S4Open ↗
Showing 3 of 19 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION18
09/25/2018123211390Open ↗
09/25/2018123211390Open ↗
08/01/2018123211390Open ↗
Showing 3 of 18 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature15
08/25/2026M00614840-S1Open ↗
08/25/2026M00614840-I1Open ↗
08/25/2026M00614840-P2Open ↗
Showing 3 of 15 on file for this type
▸DOB NOWProgress Inspector Seal & Signature7
09/29/2026M01292219-I1Open ↗
09/01/2026M00614840-S2Open ↗
09/01/2026M00614840-S2Open ↗
Showing 3 of 7 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST4
12/15/2010120557487Open ↗
07/27/2010120424059Open ↗
05/13/2010120350841Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM4
12/15/2010120557487Open ↗
07/27/2010120424059Open ↗
05/13/2010120350841Open ↗
Showing 3 of 4 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
10/10/2013140121883Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
10/10/2013140121883Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
03/24/2017140619472Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
10/10/2013140121883Open ↗
▸Safety & Tenant Protection7
▸DOB NOWStreet Tree Checklist5
08/25/2026M00614840-P9Open ↗
08/13/2026M00614840-P7Open ↗
08/13/2026M00614840-I1Open ↗
Showing 3 of 5 on file for this type
▸BISTenant Protection Plan and Notes2
02/12/2018123211390Open ↗
03/24/2017140619472Open ↗
▸Environmental & Asbestos25
▸DOB NOWDEP ACP-5: Asbestos Assessment Report15
08/25/2026M00614840-P1Open ↗
08/25/2026M00614840-S4Open ↗
08/25/2026M00614840-S3Open ↗
Showing 3 of 15 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)5
02/12/2018123211390Open ↗
04/01/2014121952903Open ↗
10/10/2013140121883Open ↗
Showing 3 of 5 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER2
12/15/2010120557487Open ↗
05/13/2010120350841Open ↗
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'2
07/27/2010120424059Open ↗
10/24/2008110372007Open ↗
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)1
09/09/2013121632634Open ↗
▸Energy Compliance6
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS4
09/25/2018123211390Open ↗
02/12/2018123211390Open ↗
04/01/2014121952903Open ↗
Showing 3 of 4 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS1
09/25/2018123211390Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
03/24/2017140619472Open ↗
▸Inspections & Test Reports2
▸BISTECHNICAL REPORT: RESPONSIBILITY2
03/24/2017140619472Open ↗
10/10/2013140121883Open ↗
▸Approvals, Objections & Sign-offs12
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST5
09/25/2018123211390Open ↗
07/31/2014140121883Open ↗
07/17/2014120557487Open ↗
Showing 3 of 5 on file for this type
▸BISADMINISTRATIVE OBJECTIONS4
07/12/2013121632634Open ↗
12/15/2010120557487Open ↗
07/27/2010120424059Open ↗
Showing 3 of 4 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION3
12/28/2012120557487Open ↗
12/28/2012120557487Open ↗
11/26/2011120557487Open ↗
▸Cost, Insurance & Ownership11
▸BISCOST AFFIDAVIT11
09/25/2018123211390Open ↗
06/29/2018123211390Open ↗
02/12/2018123211390Open ↗
Showing 3 of 11 on file for this type
▸Filing & Intake Forms17
▸BISEFILING COVER SHEET7
02/12/2018123211390Open ↗
04/01/2014121952903Open ↗
07/12/2013121632634Open ↗
Showing 3 of 7 on file for this type
▸BISADDITIONAL INFORMATION6
08/01/2018123211390Open ↗
08/01/2018123211390Open ↗
03/21/2018123211390Open ↗
Showing 3 of 6 on file for this type
▸BISBOROUGH INTAKE FORM2
09/25/2018123211390Open ↗
06/29/2018123211390Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET2
03/24/2017140619472Open ↗
10/10/2013140121883Open ↗
▸Other Documents6
▸DOB NOWProperty Ownership Certification5
08/25/2026M00614840-I1Open ↗
08/25/2026M00614840-P1Open ↗
08/25/2026M00614840-P9Open ↗
Showing 3 of 5 on file for this type
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
10/10/2013140121883Open ↗