| Owner | Filings | Most Recent |
|---|---|---|
| S S 310 | 11 | 09/18/2026 |
| PARK-IT MANAGEMENT | 5 | 07/08/2026 |
| PATH LAND HOLDINGS | 2 | 03/22/2026 |
| CITIBANK NA | 6 | 03/22/2026 |
| MARKLAND NY HOLDINGS | 5 | 03/21/2026 |
| CITI BANK | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| SCHNACKEL ENGINEERS | 1 | 01/04/2023 |
| STONEFIELD ENGINEERING & DESIGN | 2 | 12/05/2022 |
| EMAD BOULESS | 1 | 11/08/2022 |
| THE MCINTOSH GROUP, PLLC | 1 | 04/25/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| PEROTTO CONSULTING MANAGEMENT | 6 | 03/21/2026 |
| PROJECT EXPEDITERS CONSULTING CO. | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CALIBER 1 CONSTRUCTION | General Contractor | 6 | 07/08/2026 |
| CAPITAL CONTR P&H CORP | Plumbing | 2 | 09/18/2026 |
| GREGORY BOWMAN | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| MILROSE CONSULTANTS LLC | 2003 | 1 | 11/08/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | CAPITAL CONTR P&H CORP | 09/17/2026 |
| DOB NOW | Plumbing | Permit Issued | CAPITAL CONTR P&H CORP | 10/17/2025 |
| DOB NOW | General Construction | Permit Issued | CALIBER 1 CONSTRUCTION | 09/17/2025 |
| DOB NOW | General Construction | Permit Issued | CALIBER 1 CONSTRUCTION | 09/16/2025 |
| DOB NOW | General Construction | Signed-off | CALIBER 1 CONSTRUCTION | 12/07/2022 |
| DOB NOW | General Construction | Signed-off | CALIBER 1 CONSTRUCTION | 12/06/2022 |
| BIS | MH | ISSUED | ORION MECHANICAL SYSTEM | 10/05/2016 |
| BIS | OT | ISSUED | DOLPHIN CONSTRUCTION CORP | 11/26/2013 |
| BIS | — | ISSUED | AMERICAN SIGN & ELECL CON | 03/26/2013 |
| BIS | — | ISSUED | AMERICAN SIGN & ELECL CON | 03/26/2013 |
| BIS | — | ISSUED | FRANK TORRONE & SONS | 07/20/2001 |
| BIS | — | ISSUED | FRANK TORRONE & SONS | 07/12/2001 |
| BIS | — | ISSUED | FRANK TORRONE & SONS | 07/12/2001 |
| BIS | PL | ISSUED | FRANK LIQUORI PLBG & HEATING INC | 12/10/1997 |
| BIS | SP | ISSUED | FULL CAPACITY FIRE CORP | 02/05/1997 |
| BIS | — | ISSUED | LETTERA SIGN & ELECTRIC CO. INC. | 06/07/1996 |
| BIS | OT | ISSUED | JOHN F. DAVIE CONSTRUCTION CORP. | 10/12/1995 |
| BIS | EQ | ISSUED | JANTON INDUSTRIES | 04/08/1994 |
| BIS | OT | ISSUED | JANTON INDUSTRIES | 04/08/1994 |
| BIS | MH | ISSUED | PERRY MECHANICAL CONTRACTORS | 04/23/1992 |
| BIS | OT | ISSUED | TIRRO CONSTRUCTION CORP. | 09/04/1991 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/19/2021 | Complete | DANICK ELEC'L CONTR'G COR | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/12/2022 | Final | Gregory Perotto | progress |
| 05/05/2021 | Final | Gregory Perotto | progress |