Two stories - detached, small or mid-size
149TH PLACE
QUEENS · BIN 4624905
💬 Discuss this project
2024Year Built
2.5Stories
A1Building Class
R2Zoning
3,302 sfGross Floor Area
1Units
0 Open ViolationsFDNY Report ↗
Two stories - detached, small or mid-size · 5,257 sf lot · 0.63 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalCivil
Floor 210p · 1 filing · 20 docs
Floor 110p · 1 filing · 20 docs
Cellar14p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
TT T CONSTRUCTION403/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
07/21/2023$980K—— → —— not available
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
AMERILAND BROOK LLC808/27/2025
SYNERGIC DESIGN ARCHITECTS107/25/2025
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
TT&T CONSTRUCTION INCGeneral Contractor907/08/2026
PRIMROSE SERVICE INCGeneral Contractor807/08/2026
ACCORD POWER INCGeneral Contractor107/08/2026
INTELOGIC ELECTRIC, INC.Electrical103/22/2026
ROCK E SMALL PLBG&HTG INCPlumbing107/08/2026
L&L CONSTRUCTION DEVELOPGeneral Contractor104/09/2026
THOMAS KELLYElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AMERILAND BROOK LLC1506608/27/2025
SYNERGIC DESIGN LLC8561107/25/2025
Building Lifecycle
All (72)Filed (9)Permit Issued (13)Signed Off (4)Violation (7)Inspection (7)Objection (2)Special Inspection (30)
06/16/2026
Signed off — New Building
PROPOSE A NEW TWO STORY WITH ONE FAMILY HOUSE. OBTAIN NEW C OF O.
Q00961432-S1
06/12/2026
Signed off — New Building
PROPOSE A NEW TWO STORY WITH ONE FAMILY HOUSE. OBTAIN NEW C OF O.
Q00961432-S3
05/01/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
05/01/2026
Inspection — Pass-Final Curb Cut Non-Directive 14
Pass
View inspection ↗
04/17/2026
Signed off — New Building
PROPOSE A NEW TWO STORY WITH ONE FAMILY HOUSE. OBTAIN NEW C OF O.
Q00961432-S2
11/19/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
11/06/2025
Permit issued — Curb Cut
Q00961432-S3-CC
09/11/2025
Signed off — Alteration
Q01260910-I1
09/05/2025
Special inspection requirement — Fenestration areas
XIAOHONG ZHAO
09/05/2025
Special inspection requirement — Duct leakage testing, insulation and design
XIAOHONG ZHAO
09/05/2025
Special inspection requirement — Metering
XIAOHONG ZHAO
09/05/2025
Special inspection requirement — Insulation placement and R values
XIAOHONG ZHAO
09/05/2025
Special inspection requirement — HVAC-R and service water heating system controls
XIAOHONG ZHAO
09/05/2025
Special inspection requirement — Electric vehicle service equipment requirements
XIAOHONG ZHAO
09/05/2025
Special inspection requirement — Ventilation and air distribution system
XIAOHONG ZHAO
09/05/2025
Special inspection requirement — Maintenance information
XIAOHONG ZHAO
09/05/2025
Special inspection requirement — Concrete - Cast-In-Place
XIAOHONG ZHAO
09/05/2025
Special inspection requirement — Structural Steel - Details
XIAOHONG ZHAO
09/05/2025
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
XIAOHONG ZHAO
09/05/2025
Special inspection requirement — Structural Steel - High Strength Bolting
XIAOHONG ZHAO
09/05/2025
Special inspection requirement — Designated Seismic System
XIAOHONG ZHAO
09/05/2025
Special inspection requirement — Heating Systems
XIAOHONG ZHAO
09/05/2025
Special inspection requirement — Wood – Seismic Resistance
XIAOHONG ZHAO
09/05/2025
Special inspection requirement — Structural Steel - Welding
XIAOHONG ZHAO
09/05/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
XIAOHONG ZHAO
09/05/2025
Special inspection requirement — Chimneys and vents
XIAOHONG ZHAO
09/05/2025
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
TONY ONYEAGORO
09/05/2025
Special inspection requirement — Subgrade Inspections
XIAOHONG ZHAO
09/05/2025
Special inspection requirement — Mechanical Systems
XIAOHONG ZHAO
09/05/2025
Special inspection requirement — Masonry
XIAOHONG ZHAO
09/05/2025
Special inspection requirement — Final
BRIAN ILL
09/05/2025
Special inspection requirement — Footing and Foundation
XIAOHONG ZHAO
09/05/2025
Special inspection requirement — Structural Wood Frame
XIAOHONG ZHAO
09/05/2025
Special inspection requirement — Energy Code Compliance Inspections
XIAOHONG ZHAO
09/05/2025
Special inspection requirement — Fire-Resistance Rated Construction
XIAOHONG ZHAO
09/05/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
XIAOHONG ZHAO
09/05/2025
Special inspection requirement — Interior lighting power
XIAOHONG ZHAO
09/05/2025
Special inspection requirement — Air barrier - visual inspection
XIAOHONG ZHAO
09/02/2025
Objection resolved — Addressed
08/27/2025
Filed — New Building
PROPOSE A NEW TWO STORY WITH ONE FAMILY HOUSE. OBTAIN NEW C OF O.
Q00961432-P5
08/15/2025
Objection raised — Admin
07/29/2025
Permit issued — Solar
Q01260910-I1-SL
07/26/2025
Filed — New Building
PROPOSE A NEW TWO STORY WITH ONE FAMILY HOUSE. OBTAIN NEW C OF O.
Q00961432-P3
07/25/2025
Filed — Alteration
Q01260910-I1
04/17/2025
Permit issued — Mechanical Systems
Q00961432-I1-GC
11/22/2024
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
11/22/2024
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
11/22/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
11/20/2024
Inspection — Certified Sprinkler (PL)-Sprinkler-Hydro
Certified
View inspection ↗
10/03/2024
Permit issued — Plumbing
Q00961432-S2-PL
09/26/2024
Permit issued — General Construction
Q00961432-I1-MS
09/25/2024
Permit issued — Construction Fence
Q00961432-S1-FN
09/25/2024
Permit issued — Structural
Q00961432-I1-GC
07/23/2024
Filed — New Building
PROPOSE A NEW TWO STORY WITH ONE FAMILY HOUSE. OBTAIN NEW C OF O.
Q00961432-P1
07/11/2024
Filed — New Building
PROPOSE A NEW TWO STORY WITH ONE FAMILY HOUSE. OBTAIN NEW C OF O.
Q00961432-P2
05/24/2024
Violation issued (ECB, closed)
Construction
05/24/2024
Violation issued (ECB, closed)
Construction
05/24/2024
Violation issued (ECB, closed)
Construction
05/24/2024
Violation issued (ECB, closed)
Construction
05/24/2024
Violation issued (ECB, closed)
Construction
Latest 60 of 72 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWCurb CutSigned-offL&L CONSTRUCTION DEVELOP11/06/2025
DOB NOWSolarSigned-offACCORD POWER INC07/29/2025
DOB NOWMechanical SystemsPermit IssuedPRIMROSE SERVICE INC04/17/2025
DOB NOWPlumbingSigned-offROCK E SMALL PLBG&HTG INC10/03/2024
DOB NOWGeneral ConstructionSigned-offPRIMROSE SERVICE INC09/26/2024
DOB NOWConstruction FenceSigned-offPRIMROSE SERVICE INC09/25/2024
DOB NOWStructuralPermit IssuedPRIMROSE SERVICE INC09/25/2024
DOB NOWStructuralSigned-offTT&T CONSTRUCTION INC04/08/2024
DOB NOWMechanical SystemsSigned-offTT&T CONSTRUCTION INC04/04/2024
DOB NOWEarth WorkPermit IssuedTT&T CONSTRUCTION INC04/03/2024
DOB NOWFoundationSigned-offTT&T CONSTRUCTION INC03/04/2024
DOB NOWMechanical SystemsSigned-offTT&T CONSTRUCTION INC02/29/2024
DOB NOWConstruction FenceSigned-offTT&T CONSTRUCTION INC02/20/2024
BIS—ISSUEDSTANLEY SEEMAN, STANLEY RIDGE, I08/30/2007
BISEQISSUEDSTANLEY SEEMAN, STANLEY RIDGE, I03/01/2007
BIS—ISSUEDSTANLEY SEEMAN, STANLEY RIDGE, I03/01/2007
BIS—ISSUEDSTANLEY SEEMAN, STANLEY RIDGE, I10/31/2006
BISEQISSUEDSTANLEY SEEMAN, STANLEY RIDGE, I03/28/2006
BIS—ISSUEDSTANLEY SEEMAN, STANLEY RIDGE, I03/28/2006
1 job · most recent 08/27/2025
Associated Ducts and Piping Heating Systems
FiledStatusContractorScopeMake / Model / Capacity
08/27/2025Signed-offL&L CONSTRUCTION DEVELOPAssociated Ducts and Piping, Heating Systems
Heating
Williamson GWA-100-N-T 100,000 BTU · Boiler ×3
Ducts & Piping
Delta Breeze SLIM50 50 CFM · Exhaust Fan ×15
A.O. Smith GCR-40 200 40,000 BTU · Water Heater ×3
Air King EG20BL 130 CFM · Kitchen Exhaust ×3
1 job · most recent 08/27/2025
Gas Plumbing-Sprinkler Storm Water/Sanitary
FiledStatusContractorScope
08/27/2025Signed-offROCK E SMALL PLBG&HTG INCGas, Plumbing-Sprinkler, Storm, Water/Sanitary
2 jobs · most recent 07/29/2025
General Wiring
FiledStatusContractorScope
07/29/2025CompleteACCORD POWER ELECTRIC LLC—
06/24/2025CompleteINTELOGIC ELECTRIC, INC.General Wiring
1 job · most recent 08/27/2025
Steel Concrete Masonry Wood
FiledStatusContractorScope
08/27/2025Signed-offL&L CONSTRUCTION DEVELOPSteel, Concrete, Masonry, Wood
1 job · most recent 08/27/2025
Fence
FiledStatusContractorScope
08/27/2025Signed-offL&L CONSTRUCTION DEVELOPFence
1 job · most recent 08/27/2025
Earthwork
FiledStatusContractorScope
08/27/2025Signed-offL&L CONSTRUCTION DEVELOPEarthwork
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
05/01/2026Pass-Final CND-Occupancy InspectionPassView ↗
05/01/2026Pass-Final Curb Cut Non-Directive 14PassView ↗
11/19/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
11/22/2024Certified Gas-Gas-Piping-RoughingCertifiedView ↗
11/22/2024Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
11/22/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
11/20/2024Certified Sprinkler (PL)-Sprinkler-HydroCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 134
DateRequirementInspectorRole
09/05/2025Fenestration and door U-factor and product ratingsXIAOHONG ZHAOenergy_progress
09/05/2025HVAC-R and service water heating system controlsXIAOHONG ZHAOenergy_progress
09/05/2025Electric vehicle service equipment requirementsXIAOHONG ZHAOenergy_progress
09/05/2025Duct leakage testing, insulation and designXIAOHONG ZHAOenergy_progress
09/05/2025Air barrier - visual inspectionXIAOHONG ZHAOenergy_progress
09/05/2025Air barrier — testing XIAOHONG ZHAOenergy_progress
09/05/2025Fenestration air leakageXIAOHONG ZHAOenergy_progress
09/05/2025HVAC-R and service water heating equipmentXIAOHONG ZHAOenergy_progress
09/05/2025Exterior lighting powerXIAOHONG ZHAOenergy_progress
09/05/2025Permanent certificateXIAOHONG ZHAOenergy_progress
09/05/2025Concrete - Cast-In-PlaceXIAOHONG ZHAOspecial
09/05/2025Structural Steel - DetailsXIAOHONG ZHAOspecial
09/05/2025Excavations - Sheeting, Shoring, and BracingXIAOHONG ZHAOspecial
09/05/2025Structural Steel - High Strength BoltingXIAOHONG ZHAOspecial
09/05/2025Designated Seismic SystemXIAOHONG ZHAOspecial
09/05/2025Heating SystemsXIAOHONG ZHAOspecial
09/05/2025Wood – Seismic ResistanceXIAOHONG ZHAOspecial
09/05/2025Structural Steel - WeldingXIAOHONG ZHAOspecial
09/05/2025Fire-Resistant Penetrations and JointsXIAOHONG ZHAOspecial
09/05/2025Chimneys and ventsXIAOHONG ZHAOspecial
09/05/2025Subsurface Investigations (Borings/Test Pits)TONY ONYEAGOROspecial
09/05/2025Subgrade InspectionsXIAOHONG ZHAOspecial
09/05/2025Mechanical SystemsXIAOHONG ZHAOspecial
09/05/2025MasonryXIAOHONG ZHAOspecial
09/05/2025FinalBRIAN ILLprogress
Latest 25 of 134.
▾Documents — 102 on file (BIS + DOB NOW)
▸Plans & Drawings9
▸DOB NOWPlans/Sketch9
08/23/2026Q00961432-P5Request digital key ↗
08/23/2026Q00961432-P2Request digital key ↗
08/23/2026Q00961432-P1Request digital key ↗
Showing 3 of 9 on file for this type
▸Applications & Permits4
▸BISApplication Withdrawal/Address Change Form OP-1133
09/17/2020402297073Open ↗
09/17/2020402297073Open ↗
09/17/2020402297073Open ↗
▸BISPLAN / WORK APPROVAL APPLICATION1
09/17/2020402297073Open ↗
▸Zoning, Tax Lot & Property Records8
▸DOB NOWZD1: DOB Zoning Diagram3
08/13/2026Q00961432-P1Open ↗
08/13/2026Q00961432-P3Open ↗
08/13/2026Q00961432-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)3
08/13/2026Q00961432-P3Open ↗
08/13/2026Q00961432-I1Open ↗
08/13/2026Q00961432-P1Open ↗
▸BISRESTRICTION: RESTRICTIVE DECLARATION1
09/17/2020402297073Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026Q00961432-I1Open ↗
▸Seals & Professional Certifications51
▸DOB NOWProgress Inspector Seal & Signature22
09/29/2026Q00961432-I1Open ↗
09/29/2026Q00961432-I1Open ↗
09/29/2026Q00961432-I1Open ↗
Showing 3 of 22 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature20
09/29/2026Q00961432-I1Open ↗
09/29/2026Q00961432-I1Open ↗
09/29/2026Q00961432-I1Open ↗
Showing 3 of 20 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature9
08/23/2026Q00961432-S3Open ↗
08/23/2026Q00961432-P5Open ↗
08/23/2026Q00961432-P3Open ↗
Showing 3 of 9 on file for this type
▸Trade Schedules & Equipment3
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)3
08/13/2026Q00961432-P1Open ↗
08/13/2026Q00961432-I1Open ↗
08/13/2026Q00961432-P3Open ↗
▸Safety & Tenant Protection6
▸DOB NOWStreet Tree Checklist3
08/23/2026Q00961432-P1Open ↗
08/23/2026Q00961432-I1Open ↗
08/15/2026Q00961432-P3Open ↗
▸BISBPP: STREET TREES SITE PLAN1
10/24/2024440813354Open ↗
▸BISSTREET TREE CHECKLIST1
12/06/2023440813354Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026Q00961432-I1Open ↗
▸Inspections & Test Reports5
▸DOB NOWSOIL REPORT3
08/13/2026Q00961432-P1Open ↗
08/13/2026Q00961432-P3Open ↗
08/13/2026Q00961432-I1Open ↗
▸DOB NOWGeotechnical Report (BC 1803.6)1
08/13/2026Q00961432-I1Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026Q00961432-I1Open ↗
▸Approvals, Objections & Sign-offs2
▸BISLETTERS - SUPPORTING DOCUMENTATION1
09/17/2020402297073Open ↗
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01260910-I1Open ↗
▸Filing & Intake Forms2
▸BISADDITIONAL INFORMATION1
10/24/2024440813354Open ↗
▸BISBPP: CHECKLIST IN LIEU OF PLANS-ALT31
12/06/2023440813354Open ↗
▸Other Documents12
▸DOB NOWSite Survey: Initial3
08/13/2026Q00961432-I1Open ↗
08/13/2026Q00961432-P1Open ↗
08/13/2026Q00961432-P3Open ↗
▸DOB NOWProperty Ownership Certification3
08/23/2026Q00961432-P1Open ↗
08/23/2026Q00961432-I1Open ↗
08/15/2026Q00961432-P3Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone3
08/13/2026Q00961432-P1Open ↗
08/13/2026Q00961432-P3Open ↗
08/13/2026Q00961432-I1Open ↗
▸BISRECORDS MGMT FEE PAYMENT RECEIPT1
10/24/2024440813354Open ↗
▸BISBPP - SUPPORTING DOCUMENTATION1
12/06/2023440813354Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026Q00961432-I1Open ↗