| Owner | Filings | Most Recent |
|---|---|---|
| PHIPPS HOUSES | 61 | 07/08/2026 |
| FRP PHASE 5 LIHTC | 6 | 03/21/2026 |
| FRV PHASE 5 LIHTC | 2 | 03/21/2026 |
| LETTIRE CONSTRUCTION | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| NY BUILDING ASSOCIATES INC | 2 | 12/08/2025 |
| DAGHER ENGINEERING PLLC | 12 | 11/20/2025 |
| TYLL ENGINEERING AND CONSULTING, PC | 1 | 09/09/2025 |
| PAUL PERDEK, PROF. ENG. PLLC | 4 | 07/25/2024 |
| KN3 ENGINEERING LLC | 1 | 07/18/2024 |
| HANSEN ENGINEERING, PC | 2 | 01/16/2024 |
| LANGAN ENGINEERING | 2 | 07/19/2023 |
| DESIMONE CONSULTING ENGINEERING | 2 | 05/19/2022 |
| GEODESIGN INC. PC | 1 | 05/03/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| A1 EXPEDITING SERVICE | 6 | 03/21/2026 |
| AE DESIGN SOLUTION | 4 | 03/21/2026 |
| S R SOLAR DESIGN | 4 | 03/21/2026 |
| JM ZONING, LLC. | 18 | 03/21/2026 |
| LETTIRE CONSTRUCTION | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| LETTIRE CONSTRUCTION CORP | General Contractor | 15 | 07/08/2026 |
| ROCKLEDGE SCAFFOLD CORP | General Contractor | 7 | 07/08/2026 |
| DEMAR PLUMBING CORP | Fire Protection | 5 | 07/08/2026 |
| ADRIAS PLUMBING CORP | Plumbing | 3 | 07/08/2026 |
| DEMAR MECHANICAL INC | Plumbing | 2 | 07/08/2026 |
| RELIANT ELEC'L CONT'G INC | Electrical | 2 | 03/22/2026 |
| SNG BRICK AND STONE INC | General Contractor | 2 | 07/08/2026 |
| 770 ELECTRIC CORP | General Contractor | 1 | 07/08/2026 |
| BT'S PLUMBING AND HEATING | Plumbing | 1 | 07/08/2026 |
| AGIR ELEC'L LTD. D/B/A | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| NKM ENGINEERING PLLC | 6244 | 2 | 12/08/2025 |
| DOMANI INSPECTION SERVICE | 843 | 14 | 11/20/2025 |
| LEO Y LEE ASSOCIATES | 2481 | 1 | 07/18/2024 |
| GEODESIGN, INC., P.C. | 627 | 2 | 05/19/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | LETTIRE CONSTRUCTION CORP | 11/10/2025 |
| DOB NOW | Solar | Signed-off | 770 ELECTRIC CORP | 08/26/2025 |
| DOB NOW | Construction Fence | Signed-off | LETTIRE CONSTRUCTION CORP | 07/16/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | ROCKLEDGE SCAFFOLD CORP | 04/23/2025 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | ROCKLEDGE SCAFFOLD CORP | 04/23/2025 |
| DOB NOW | Plumbing | Signed-off | BT'S PLUMBING AND HEATING | 04/08/2025 |
| DOB NOW | Plumbing | Signed-off | ADRIAS PLUMBING CORP | 03/18/2025 |
| DOB NOW | Mechanical Systems | Signed-off | LETTIRE CONSTRUCTION CORP | 01/29/2025 |
| DOB NOW | Standpipe | Signed-off | DEMAR PLUMBING CORP | 01/23/2025 |
| DOB NOW | Standpipe | Signed-off | DEMAR PLUMBING CORP | 01/23/2025 |
| DOB NOW | Plumbing | Signed-off | DEMAR MECHANICAL INC | 01/16/2025 |
| DOB NOW | Plumbing | Signed-off | ADRIAS PLUMBING CORP | 12/09/2024 |
| DOB NOW | Suspended Scaffold | Signed-off | SNG BRICK AND STONE INC | 07/25/2024 |
| DOB NOW | Supported Scaffold | Signed-off | SNG BRICK AND STONE INC | 07/25/2024 |
| DOB NOW | Construction Fence | Signed-off | LETTIRE CONSTRUCTION CORP | 07/17/2024 |
| DOB NOW | Structural | Permit Issued | LETTIRE CONSTRUCTION CORP | 05/31/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | ROCKLEDGE SCAFFOLD CORP | 05/09/2024 |
| DOB NOW | Plumbing | Signed-off | ADRIAS PLUMBING CORP | 04/25/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | ROCKLEDGE SCAFFOLD CORP | 04/23/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | ROCKLEDGE SCAFFOLD CORP | 04/23/2024 |
| DOB NOW | Foundation | Permit Issued | LETTIRE CONSTRUCTION CORP | 04/09/2024 |
| DOB NOW | Structural | Permit Issued | LETTIRE CONSTRUCTION CORP | 02/08/2024 |
| DOB NOW | Mechanical Systems | Signed-off | LETTIRE CONSTRUCTION CORP | 02/05/2024 |
| DOB NOW | Standpipe | Signed-off | DEMAR PLUMBING CORP | 01/31/2024 |
| DOB NOW | Standpipe | Signed-off | DEMAR PLUMBING CORP | 01/30/2024 |
| DOB NOW | Standpipe | Signed-off | DEMAR PLUMBING CORP | 01/30/2024 |
| DOB NOW | Plumbing | Signed-off | DEMAR MECHANICAL INC | 01/30/2024 |
| DOB NOW | Support of Excavation | Signed-off | LETTIRE CONSTRUCTION CORP | 12/19/2023 |
| DOB NOW | Earth Work | Signed-off | LETTIRE CONSTRUCTION CORP | 12/19/2023 |
| DOB NOW | Foundation | Permit Issued | LETTIRE CONSTRUCTION CORP | 12/18/2023 |
| DOB NOW | Construction Fence | Signed-off | LETTIRE CONSTRUCTION CORP | 08/30/2023 |
| BIS | — | ISSUED | LETTIRE CONSTRUCTION CORP | 11/03/2025 |
| BIS | — | ISSUED | LETTIRE CONSTRUCTION CORP | 05/20/2025 |
| BIS | — | ISSUED | LETTIRE CONSTRUCTION CORP | 10/31/2024 |
| BIS | — | ISSUED | LETTIRE CONSTRUCTION CORP | 04/15/2024 |
| BIS | — | ISSUED | LETTIRE CONSTRUCTION CORP | 03/07/2024 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/20/2025 | Signed-off | DEMAR PLUMBING CORP | 2 heads, 2 outlets |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/20/2025 | — | — | — |
| 07/19/2023 | Signed-off | NY PLUMBING PROS INC | Storm |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/29/2025 | Complete | RELIANT ELEC'L CONT'G INC | General Wiring, Lighting |
| 12/03/2024 | Complete | RELIANT ELEC'L CONT'G INC | — |
| 12/03/2024 | Complete | RELIANT ELEC'L CONT'G INC | — |
| 12/02/2024 | Complete | GRID CITY ELECTRIC, CORP | 135 meters, 1 new_meters |
| 07/09/2024 | Complete | TF ELECTRICAL CORP | General Wiring |
| 06/11/2024 | Complete | AGIR ELEC'L LTD. D/B/A | — |
| 05/08/2024 | Complete | AGIR ELEC'L LTD. D/B/A | — |
| 04/17/2024 | Complete | ANTHONY G FERRY INC | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/19/2023 | Signed-off | NY PLUMBING PROS INC | 1 scope_items |
| 05/19/2022 | Permit Issued | LETTIRE CONSTRUCTION CORP | 1 scope_items |
| 05/18/2022 | Permit Issued | LETTIRE CONSTRUCTION CORP | Steel, Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/19/2023 | Signed-off | NY PLUMBING PROS INC | Earthwork |
| Date | Type | Result | Report |
|---|---|---|---|
| 11/28/2025 | Pass-Final SP - More than 10 Requested Floors | Pass | View ↗ |
| 07/16/2025 | Pass-Final SD - Fire Pump | Pass | View ↗ |
| 07/08/2025 | Fail-Final SD - Fire Pump | Fail | View ↗ |
| 06/25/2025 | Pass-Final SP - Up to 9 Requested Floors | Pass | View ↗ |
| 06/10/2025 | Pass-Final SD - More than 10 Requested Floors | Pass | View ↗ |
| 05/27/2025 | Pass-Final SP - Up to 9 Requested Floors | Pass | View ↗ |
| 05/15/2025 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 05/14/2025 | Pass-Final SP - Up to 3 Requested Floors | Pass | View ↗ |
| 04/30/2025 | Pass-Final SP - More than 10 Requested Floors | Pass | View ↗ |
| 04/23/2025 | Pass-Final PL - Underground | Pass | View ↗ |
| 10/18/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/09/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/02/2024 | Pass-Final PL - More than 10 Requested Floors | Pass | View ↗ |
| 06/27/2024 | Certified StandPipe - SD - Alarm Sys 64/09 - Finish | Certified | View ↗ |
| 06/27/2024 | Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet) | Certified | View ↗ |
| 05/03/2024 | Pass-Final PL - Underground | Pass | View ↗ |
| 04/24/2024 | Pass-Final PL - Underground | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/19/2025 | Air barrier - visual inspection | NARESH MAHANGU | energy_progress |
| 12/19/2025 | Energy Code Compliance Inspections | NARESH MAHANGU | progress |
| 12/19/2025 | Final | NARESH MAHANGU | progress |
| 12/19/2025 | Fire-Resistant Penetrations and Joints | NARESH MAHANGU | special |
| 12/19/2025 | Structural Stability – Alterations of existing buildings | NARESH MAHANGU | special |
| 12/16/2025 | Sprinkler Systems | JOHN MCMONAGLE | special |
| 12/16/2025 | Standpipe Systems | JOHN MCMONAGLE | special |
| 12/08/2025 | Structural Stability – Alterations of existing buildings | NARESH MAHANGU | special |
| 12/05/2025 | Air barrier - visual inspection | NARESH MAHANGU | energy_progress |
| 12/05/2025 | Fire-Resistant Penetrations and Joints | NARESH MAHANGU | special |
| 12/05/2025 | Energy Code Compliance Inspections | NARESH MAHANGU | progress |
| 12/05/2025 | Final | NARESH MAHANGU | progress |
| 11/19/2025 | Standpipe Systems | JOHN MCMONAGLE | special |
| 11/19/2025 | Sprinkler Systems | JOHN MCMONAGLE | special |
| 10/22/2025 | Sprinkler Systems | JOHN MCMONAGLE | special |
| 10/22/2025 | Standpipe Systems | JOHN MCMONAGLE | special |
| 09/04/2025 | Final | JOHN MCMONAGLE | progress |
| 09/04/2025 | Mechanical Systems | JOHN MCMONAGLE | special |
| 08/07/2025 | HVAC-R and service water heating equipment | JOHN MCMONAGLE | energy_progress |
| 08/07/2025 | HVAC-R and service water piping design and insulation | JOHN MCMONAGLE | energy_progress |
| 08/07/2025 | HVAC-R and service water heating system controls | JOHN MCMONAGLE | energy_progress |
| 08/07/2025 | Electrical motors and elevators | JOHN MCMONAGLE | energy_progress |
| 08/07/2025 | Maintenance information | JOHN MCMONAGLE | energy_progress |
| 08/07/2025 | Energy Code Compliance Inspections | JOHN MCMONAGLE | progress |
| 08/07/2025 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | JOHN MCMONAGLE | special |