| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/22/2022 | Complete | AMOR ELECTRIC CORP | General Wiring |
| Firm | Filings | Most Recent |
|---|---|---|
| KBN SERVICES LLC | 5 | 02/03/2025 |
| FRANK J QUATELA ARCHITECT P.C | 2 | 09/06/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| Manetta architecture design pllc | 14 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| USA BUILDING CONTR INC | General Contractor | 6 | 03/21/2026 |
| HAPPY HOME LLC | General Contractor | 1 | 07/08/2026 |
| HIGHLEVEL GROUP INC | General Contractor | 1 | 07/08/2026 |
| MASTER INTERIORS CORP | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| RICHMOND TESTING LAB | 263 | 7 | 02/03/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | USA BUILDING CONTR INC | 07/10/2024 |
| DOB NOW | Structural | Signed-off | USA BUILDING CONTR INC | 07/09/2024 |
| DOB NOW | General Construction | Signed-off | MASTER INTERIORS CORP | 11/27/2023 |
| DOB NOW | Mechanical Systems | Signed-off | HAPPY HOME LLC | 11/15/2023 |
| DOB NOW | Structural | Signed-off | HIGHLEVEL GROUP INC | 08/15/2023 |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/20/2025 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 02/01/2025 | Post-installed Anchors | RICHARD LEMANSKY | special |
| 02/01/2025 | Structural Stability – Alterations of existing buildings | RICHARD LEMANSKY | special |
| 02/01/2025 | Structural Steel - Welding | RICHARD LEMANSKY | special |
| 02/01/2025 | Final | RICHARD LEMANSKY | progress |
| 02/01/2025 | Structural Wood Frame | RICHARD LEMANSKY | progress |
| 12/06/2023 | Structural Wood Frame | RICHARD LEMANSKY | progress |
| 12/06/2023 | Final | RICHARD LEMANSKY | progress |
| 12/06/2023 | Post-installed Anchors | RICHARD LEMANSKY | special |
| 12/06/2023 | Structural Stability – Alterations of existing buildings | RICHARD LEMANSKY | special |
| 12/06/2023 | Structural Steel - Welding | RICHARD LEMANSKY | special |
| 12/06/2023 | Tenant Protection Plan Compliance | RICHARD LEMANSKY | special |
| 10/30/2023 | Structural Steel - Welding | RICHARD LEMANSKY | special |
| 10/30/2023 | Post-installed Anchors | RICHARD LEMANSKY | special |
| 10/30/2023 | Structural Stability – Alterations of existing buildings | RICHARD LEMANSKY | special |
| 10/30/2023 | Tenant Protection Plan Compliance | RICHARD LEMANSKY | special |
| 10/30/2023 | Final | RICHARD LEMANSKY | progress |
| 10/30/2023 | Structural Wood Frame | RICHARD LEMANSKY | progress |
| 09/18/2023 | Post-installed Anchors | RICHARD LEMANSKY | special |
| 09/18/2023 | Structural Stability – Alterations of existing buildings | RICHARD LEMANSKY | special |
| 09/18/2023 | Tenant Protection Plan Compliance | RICHARD LEMANSKY | special |
| 09/18/2023 | Final | RICHARD LEMANSKY | progress |
| 09/18/2023 | Structural Wood Frame | RICHARD LEMANSKY | progress |