1952Year Built
6Stories
D4Building Class
R4Zoning
466,368 sfGross Floor Area
536Units
LL97 CoveredRent Stabilized269 Open Violations 261 unresolved · 8 paperwork only ▸FISP: SAFEFDNY Report ↗
Elevator cooperative · 292,000 sf lot · 1.6 FAR built · Flood zone X
Locations of Work
Structural
Permit Issued — active, not yet Signed-off
RoofUnder Construction5p · 1 filing · 3 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
ALLTECH CONSTRUCTION GROUP404/09/2026
DARA OWNERS1303/22/2026
DARA OWNERS CORP/DARA GUA103/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ASHRAF CORP110/22/2025
SAGHARI ARCHITECTURAL SERVICES, PC108/25/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
AK CONSULTING SERVICES203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
HIGH QUALITY ELEC.OF NYCElectrical103/22/2026
ALLTECH CONSTRUCTION GRGeneral Contractor104/09/2026
K.E.S CONSTRUCTION CO INCGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
NY RESTORATION TECHNOLOGY6187108/25/2025
Building Lifecycle
All (58)Filed (3)Permit Issued (3)Signed Off (2)Facade (FISP) (12)Violation (23)Objection (8)Special Inspection (7)
08/19/2026
Signed off — Alteration
Q01302757-I1
08/10/2026
Signed off — Alteration
Facade repairs per plans. No change in use, egress, or occupancy.
Q01274523-I1
02/14/2026
Violation issued (HPD, open)
A
12/30/2025
Permit issued — General Construction
Q01274523-I1-GC
12/09/2025
Objection resolved — Addressed
10/24/2025
Objection resolved — Addressed
10/23/2025
Permit issued — Sidewalk Shed
Q01302757-I1-SH
10/22/2025
Filed — Alteration
Q01302757-I1
10/03/2025
Permit issued — Suspended Scaffold
Q01292771-I1-SC
09/30/2025
Filed — Alteration
Q01292771-I1
09/19/2025
Objection resolved — Addressed
09/19/2025
Objection resolved — Addressed
09/16/2025
Special inspection requirement — Construction Operations Influencing Adjacent Structures
Hamidreza Saghari
09/12/2025
Objection raised — Cost
09/12/2025
Objection raised — Structural
09/12/2025
Objection raised — Mechanical
09/12/2025
Objection raised — Admin
08/25/2025
Filed — Alteration
Facade repairs per plans. No change in use, egress, or occupancy.
Q01274523-I1
08/20/2025
Special inspection requirement — Post-installed Anchors
Hamidreza Saghari
08/20/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Hamidreza Saghari
08/20/2025
Special inspection requirement — Masonry
Hamidreza Saghari
08/20/2025
Special inspection requirement — Final
Hamidreza Saghari
08/20/2025
Special inspection requirement — Air barrier - visual inspection
Hamidreza Saghari
08/20/2025
Special inspection requirement — Tenant Protection Plan Compliance
Hamidreza Saghari
04/19/2025
Violation issued (HPD, open)
C
04/19/2025
Violation issued (HPD, closed)
C
04/19/2025
Violation issued (HPD, closed)
B
04/19/2025
Violation issued (HPD, open)
C
04/19/2025
Violation issued (HPD, closed)
C
04/19/2025
Violation issued (HPD, closed)
C
11/20/2024
Violation issued (HPD, closed)
B
11/20/2024
Violation issued (HPD, closed)
B
11/11/2024
Violation issued (HPD, closed)
C
11/11/2024
Violation issued (HPD, closed)
B
03/31/2023
Violation issued (HPD, closed)
A
02/16/2023
Cycle 9 facade report submitted
02/16/2023
Cycle 9 facade report signed — SAFE
01/18/2023
Cycle 9 facade inspection completed
12/14/2021
Violation issued (HPD, closed)
B
04/20/2021
Violation issued (HPD, closed)
A
04/20/2021
Violation issued (HPD, closed)
I
03/19/2018
Violation issued (HPD, closed)
B
03/19/2018
Violation issued (HPD, closed)
B
06/18/2015
Cycle 8 facade report submitted
06/18/2015
Cycle 7 facade report submitted
06/05/2015
Cycle 8 facade report signed — SWARMP
06/05/2015
Cycle 7 facade report signed — SWARMP
05/13/2015
Cycle 8 facade inspection completed
05/13/2015
Cycle 7 facade inspection completed
11/25/2014
Violation issued (ECB, open)
Local Law
08/30/2013
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
09/04/2008
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
03/23/2007
Violation issued (ECB, closed)
Elevators
01/24/2007
Cycle 6 facade report submitted
01/11/2007
Cycle 6 facade report signed — SAFE
01/05/2007
Cycle 6 facade inspection completed
05/20/2000
Violation issued (ECB, closed)
Elevators
11/25/1991
Violation issued (ECB, closed)
Elevators
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offK.E.S CONSTRUCTION CO INC12/30/2025
DOB NOWSidewalk ShedSigned-offALLTECH CONSTRUCTION GR10/23/2025
DOB NOWSuspended ScaffoldPermit IssuedK.E.S. CONSTRUCTION CO IN10/03/2025
BISOTISSUEDWINDHAM RESTORATION CORP08/16/2018
BISEQISSUEDPHOENIX SUTTON STR INC07/06/2018
BISOTISSUEDWINDHAM RESTORATION CORP08/23/2017
BISEQISSUEDPHOENIX SUTTON STR INC06/30/2017
BISOTISSUEDWINDHAM RESTORATION CORP06/14/2017
BISOTISSUEDDNA CONTRACTING LLC03/07/2005
BISOTISSUEDDNA CONTRACTING LLC03/10/2004
2 projects · most recent 10/22/2025
FiledStatusContractorScope
10/22/2025CompleteHIGH QUALITY ELEC.OF NYC—
04/18/2024Permit IssuedHYLAN DATACOM & ELECL LLC2 meters, 1 new_meters
▾Special Inspection Requirements (DOB NOW) — 7
DateRequirementInspectorRole
09/16/2025Construction Operations Influencing Adjacent StructuresHamidreza Sagharispecial
08/20/2025Post-installed AnchorsHamidreza Sagharispecial
08/20/2025Structural Stability – Alterations of existing buildingsHamidreza Sagharispecial
08/20/2025MasonryHamidreza Sagharispecial
08/20/2025FinalHamidreza Saghariprogress
08/20/2025Air barrier - visual inspectionHamidreza Sagharienergy_progress
08/20/2025Tenant Protection Plan ComplianceHamidreza Sagharispecial
▾Documents — 51 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
08/19/2026Q01274523-I1Request digital key ↗
08/18/2026Q01292771-I1Request digital key ↗
08/18/2026Q01302757-I1Request digital key ↗
▸Applications & Permits11
▸BISPLAN / WORK APPROVAL APPLICATION6
07/11/2022421489302Open ↗
05/19/2022421489302Open ↗
03/08/2022421489302Open ↗
Showing 3 of 6 on file for this type
▸BISWORK PERMIT APPLICATION5
08/20/2018421489302Open ↗
07/09/2018440416097Open ↗
08/25/2017421489302Open ↗
Showing 3 of 5 on file for this type
▸Seals & Professional Certifications14
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION3
06/21/2017421489302Open ↗
06/21/2017421489302Open ↗
06/21/2017421489302Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT2
06/29/2017440416097Open ↗
06/21/2017421489302Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/19/2026Q01274523-I1Open ↗
08/18/2026Q01302757-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
09/01/2026Q01274523-I1Open ↗
09/01/2026Q01274523-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
09/01/2026Q01274523-I1Open ↗
09/01/2026Q01274523-I1Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
06/21/2017421489302Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
06/29/2017440416097Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
06/29/2017440416097Open ↗
▸Safety & Tenant Protection2
▸BISTENANT PROTECTION PLAN AND NOTES2
06/29/2017440416097Open ↗
06/21/2017421489302Open ↗
▸Environmental & Asbestos2
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
06/21/2017421489302Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/19/2026Q01274523-I1Open ↗
▸Energy Compliance3
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
04/06/2022421489302Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
03/01/2022421489302Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
06/21/2017421489302Open ↗
▸Inspections & Test Reports5
▸BISTECHNICAL REPORT: RESPONSIBILITY4
12/08/2021421489302Open ↗
04/16/2021440416097Open ↗
04/16/2021440416097Open ↗
Showing 3 of 4 on file for this type
▸BISMASONRY1
03/01/2022421489302Open ↗
▸Approvals, Objections & Sign-offs4
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST2
07/12/2022421489302Open ↗
04/16/2021440416097Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
07/09/2018440416097Open ↗
▸BISFINAL1
04/07/2022421489302Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT1
06/21/2017421489302Open ↗
▸BISCOST AFFIDAVIT (FINAL): PW31
04/04/2022421489302Open ↗
▸Filing & Intake Forms2
▸BISEFILING COVER SHEET1
06/21/2017421489302Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
06/29/2017440416097Open ↗
▸Other Documents3
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION1
04/16/2021440416097Open ↗
▸DOB NOWCalculations1
08/13/2026Q01292771-I1Open ↗
▸DOB NOWManufacturer's Specifications1
08/13/2026Q01292771-I1Open ↗