| Owner | Filings | Most Recent |
|---|---|---|
| UNIT 11B TRUST | 3 | 07/08/2026 |
| DOUGLAS ELLIMAN PROPERTY MANAGEMENT | 6 | 07/08/2026 |
| 150 CHARLES STREET CONDOMINIUM | 5 | 07/08/2026 |
| 150 CHARLES STREET HOLDINGS LL | 17 | 03/22/2026 |
| DOUGLAS ELLIMAN | 8 | 03/22/2026 |
| PLAZA CONSTRUCTION | 11 | 03/22/2026 |
| NAVILLUS CONTRACTING | 5 | 03/22/2026 |
| EMPIRE STEEL CORP | 1 | 03/22/2026 |
| LAQUILA GROUP | 2 | 03/22/2026 |
| HOMECREST | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| TSF ENGINEERING, PC | 5 | 08/12/2026 |
| ANZ CONSULTING ENGINEERING, PLLC | 5 | 05/06/2026 |
| KOHLER RONAN, LLC | 6 | 04/29/2026 |
| NEW AGE ENGINEERING PLLC | 1 | 04/14/2026 |
| BRENT BUCK ARCHITECTS PLLC | 2 | 04/08/2026 |
| VINCENT J. LIOTTA P.E. | 4 | 12/18/2025 |
| GACE DPC | 2 | 12/16/2025 |
| SOLE PROPRIETORSHIP | 2 | 12/11/2025 |
| KOHN ARCHITECTURE, PLLC | 2 | 10/08/2025 |
| FREDERIC ZONSIUS | 1 | 09/05/2025 |
| MM ARCHITECT PC | 2 | 05/29/2025 |
| SETH P. ROYE ARCHITECT PC | 1 | 12/02/2024 |
| GILSANZ MURRAY STEFICEK LLP | 1 | 06/06/2024 |
| COOKFOX ARCHITECTS | 3 | 06/04/2024 |
| ALNOUR CONSULTING | 1 | 05/09/2024 |
| ARMANDO ROSE ARCHITECT PLLC | 1 | 05/22/2023 |
| ANDREW WILKINSON ARCHITECT | 1 | 04/11/2023 |
| COSTA ARCH & ENG LLP | 2 | 12/05/2022 |
| CES ENGINEERING LLC | 4 | 09/14/2022 |
| EAST END ENGINEERING | 1 | 07/15/2022 |
| PATTI & ANTHES CONSULTING ENGINEERS | 4 | 11/19/2021 |
| ERIC SHEFFIELD ARCHITECT | 3 | 11/09/2021 |
| PHILIP HABIB & ASSOCIATES | 7 | 07/02/2020 |
| PLUS GROUP CONSULTING ENGINEERING | 1 | 01/10/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| MICHAEL ZENREICH ARCHITECT | 8 | 03/21/2026 |
| ANZALONE ARCHITECTURE | 8 | 03/21/2026 |
| FZAD ARCHITECTURE + DESIGN | 3 | 03/21/2026 |
| JAM CONSULTANTS, INC. | 48 | 03/21/2026 |
| RIGGING CONSULTANTS | 2 | 03/21/2026 |
| JONATHAN B. HELD A.I.A. | 1 | 03/21/2026 |
| OUTSOURCE CONSULTANTS, INC. | 2 | 03/21/2026 |
| COSTA ARCHITECTURE & ENGINEERING LL | 12 | 03/21/2026 |
| CLARKE CONSTRUCTION CONSULTANTS | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| PLAZA CONSTRUCTION LLC | General Contractor | 12 | 07/08/2026 |
| SILVERLINING INTERIORS | General Contractor | 12 | 04/12/2026 |
| FLOWCON INC | General Contractor | 12 | 07/01/2026 |
| RIVERSIDE BUILDERS INC | General Contractor | 5 | 06/27/2026 |
| HIGH TECH CONSTRUCTION SY | General Contractor | 4 | 07/08/2026 |
| GRG RESTORATION & SOLUTIO | General Contractor | 4 | 04/09/2026 |
| ARCON PLBG SOLUTIONS | Plumbing | 3 | 07/08/2026 |
| THE ORGANIC GARDENER NYC* | General Contractor | 3 | 03/21/2026 |
| RENOVATION WITH PASSION I | General Contractor | 3 | 03/21/2026 |
| UNIVERSAL FIRE SPR LLC | Fire Protection | 2 | 07/08/2026 |
| FORTE EXPRESS P & H INC | Plumbing | 2 | 07/08/2026 |
| DONATO PLUMBING, INC | Plumbing | 2 | 08/26/2026 |
| NEW MILLENNIUM P & H CORP | Plumbing | 2 | 07/08/2026 |
| MASTER PLBG AND HTG INC | Fire Protection | 2 | 07/08/2026 |
| EZ RUNER CONSTRUCTION CORP | Plumbing | 1 | 07/08/2026 |
| MASTER 2 PLBG & HTG INC | Plumbing | 1 | 09/15/2026 |
| PIOTR RADZIK | Electrical | 1 | 03/21/2026 |
| ORBIT PLBG & HTG INC | Plumbing | 1 | 07/08/2026 |
| REDLINE ELECTRIC INC | Electrical | 1 | 03/22/2026 |
| SAFETECH ELECL CONTNG COR | Electrical | 1 | 03/22/2026 |
| SUPER CHARGED ELEC. INC. | Electrical | 1 | 03/22/2026 |
| TOMASZ PUZA | Electrical | 1 | 03/21/2026 |
| CAPITOL FIRE SPRINKLER CO | Fire Protection | 1 | 07/08/2026 |
| KG SPRINKLER CORP | Fire Protection | 1 | 07/08/2026 |
| RIGID PLBG CONTRACTORS IN | Fire Protection | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| FZAD ARCHITECTURE + DESIG | 2041 | 6 | 08/12/2026 |
| ANZ CONSULTING ENGINEERIN | 3946 | 7 | 05/06/2026 |
| NEW AGE ENGINEERING PLLC | 7746 | 1 | 04/14/2026 |
| VINCENT J. LIOTTA P. E. | 1974 | 4 | 12/18/2025 |
| SOCOTEC ENGINEERING | 4983 | 2 | 12/16/2025 |
| THOMAS VELTRE, P.E, P.C. | 459 | 2 | 12/11/2025 |
| KOHN ARCHITECTURE PLLC | 1523 | 2 | 10/08/2025 |
| THE EIPEL ENGINEERING GRO | 2714 | 1 | 10/08/2025 |
| TSF ENGINEERING, PC | 1274 | 2 | 09/09/2025 |
| MM ARCHITECT PC | 3934 | 2 | 05/29/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | FLOWCON INC | 09/30/2026 |
| DOB NOW | Plumbing | Permit Issued | MASTER 2 PLBG & HTG INC | 09/14/2026 |
| DOB NOW | Plumbing | Permit Issued | DONATO PLUMBING, INC | 08/12/2026 |
| DOB NOW | Structural | Permit Issued | FLOWCON INC | 06/29/2026 |
| DOB NOW | General Construction | Permit Issued | FLOWCON INC | 06/29/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | FLOWCON INC | 06/29/2026 |
| DOB NOW | Plumbing | Signed-off | ARCON PLBG SOLUTIONS | 05/11/2026 |
| DOB NOW | Mechanical Systems | Signed-off | THE METRO GROUP, INC | 04/27/2026 |
| DOB NOW | Plumbing | Permit Issued | ARCON PLBG SOLUTIONS | 04/24/2026 |
| DOB NOW | Mechanical Systems | Signed-off | GRG RESTORATION & SOLUTIO | 03/26/2026 |
| DOB NOW | General Construction | Signed-off | GRG RESTORATION & SOLUTIO | 03/24/2026 |
| DOB NOW | General Construction | Permit Issued | FLOWCON INC | 03/09/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | FLOWCON INC | 03/09/2026 |
| DOB NOW | General Construction | Permit Issued | FLOWCON INC | 03/09/2026 |
| DOB NOW | Structural | Permit Issued | FLOWCON INC | 03/06/2026 |
| DOB NOW | Structural | Permit Issued | FLOWCON INC | 03/05/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | FLOWCON INC | 03/04/2026 |
| DOB NOW | Plumbing | Permit Issued | ORBIT PLBG & HTG INC | 01/22/2026 |
| DOB NOW | General Construction | Permit Issued | SCORDIO CONSTRUCTION INC | 01/08/2026 |
| DOB NOW | Sprinklers | Signed-off | RIGID PLBG CONTRACTORS IN | 12/03/2025 |
| DOB NOW | Plumbing | Permit Issued | EZ RUNER CONSTRUCTION COR | 11/26/2025 |
| DOB NOW | General Construction | Permit Issued | FLOWCON INC | 11/14/2025 |
| DOB NOW | Sprinklers | Permit Issued | DONATO PLUMBING, INC | 11/13/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | FLOWCON INC | 11/13/2025 |
| DOB NOW | Structural | Permit Issued | FLOWCON INC | 11/13/2025 |
| DOB NOW | Sprinklers | Permit Issued | H M SPRINKLER INC | 11/13/2025 |
| DOB NOW | Mechanical Systems | Signed-off | GRG RESTORATION & SOLUTIO | 11/07/2025 |
| DOB NOW | Structural | Signed-off | SILVERLINING INTERIORS | 11/06/2025 |
| DOB NOW | General Construction | Signed-off | GRG RESTORATION & SOLUTIO | 10/30/2025 |
| DOB NOW | General Construction | Signed-off | RIVERSIDE BUILDERS INC | 09/09/2025 |
| DOB NOW | Mechanical Systems | Signed-off | RIVERSIDE BUILDERS INC | 09/09/2025 |
| DOB NOW | Mechanical Systems | Signed-off | SILVERLINING INTERIORS | 08/15/2025 |
| DOB NOW | General Construction | Signed-off | SILVERLINING INTERIORS | 08/15/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | SKYLINE RESTORATION INC | 06/26/2025 |
| DOB NOW | Mechanical Systems | Signed-off | RIVERSIDE BUILDERS INC | 06/11/2025 |
| DOB NOW | Sprinklers | Signed-off | MASTER PLBG AND HTG INC | 06/10/2025 |
| DOB NOW | General Construction | Signed-off | RIVERSIDE BUILDERS INC | 06/04/2025 |
| DOB NOW | Sprinklers | Signed-off | MASTER PLBG AND HTG INC | 05/13/2025 |
| DOB NOW | Structural | Signed-off | SILVERLINING INTERIORS | 12/05/2024 |
| DOB NOW | Plumbing | Permit Issued | ARCON PLBG SOLUTIONS | 10/25/2024 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 05/06/2026 | Signed-off | RIVERSIDE BUILDERS INC | Air Conditioning Systems | Cooling Mitsubishi Electric PEFY-P12NMAU-E4 13,500 BTU · Vrf Indoor ×3 PEFY-P18NMAU-E5 20,000 BTU · Vrf Indoor ×1 PEFY-P24NMAU-E4 27,000 BTU · Vrf Indoor ×1 |
| 04/14/2026 | Signed-off | THE METRO GROUP, INC | Others | Other Schebler EVD UL-1738 APPROVED 1 BTU · Chimney ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/06/2026 | Signed-off | MASTER PLBG AND HTG INC | Sprinkler System |
| 09/09/2025 | Signed-off | RIGID PLBG CONTRACTORS IN | 5 heads |
| 07/25/2025 | Permit Issued | KG SPRINKLER CORP | 81 heads |
| 09/14/2022 | Signed-off | CAPITOL FIRE SPRINKLER CO | 19 heads |
| 11/19/2021 | — | — | — |
| 01/10/2020 | Signed-off | UNIVERSAL FIRE SPR LLC | 54 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/12/2026 | Permit Issued | EZ RUNER CONSTRUCTION COR | Gas, Water/Sanitary |
| 05/06/2026 | Signed-off | ARCON PLBG SOLUTIONS | Water/Sanitary |
| 04/29/2026 | Permit Issued | MASTER 2 PLBG & HTG INC | Gas, Water/Sanitary |
| 12/17/2025 | Permit Issued | DONATO PLUMBING, INC | Gas, Water/Sanitary |
| 10/08/2025 | Permit Issued | ORBIT PLBG & HTG INC | Water/Sanitary |
| 09/09/2025 | — | — | — |
| 07/25/2025 | Permit Issued | DONATO PLUMBING, INC | Gas, Water/Sanitary |
| 09/14/2022 | Signed-off | NEW MILLENNIUM P & H CORP | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/08/2026 | Complete | MARKS ELECTRIC CORP | General Wiring |
| 05/27/2026 | Complete | GLENDALE ELECTL CONTNG IN | — |
| 05/01/2026 | Permit Issued | THE METRO GROUP ELECTRIC | General Wiring |
| 04/29/2026 | Complete | P & Z ELECTRIC CORP | General Wiring |
| 04/24/2026 | Complete | A.X.M. ELECTRIC CORP | General Wiring |
| 02/02/2026 | Complete | GLENDALE ELECTL CONTNG IN | — |
| 01/14/2026 | Permit Issued | GLENDALE ELECTL CONTNG IN | General Wiring |
| 11/18/2025 | Permit Issued | APOLLO ELECTRIC INC. | — |
| 07/15/2025 | Complete | KINGS ELECTRIC CO., INC. | — |
| 06/06/2025 | Complete | APOLLO ELECTRIC INC. | General Wiring |
| 04/24/2025 | Complete | WARREN OSTROFF ELEC., INC | — |
| 07/29/2024 | Complete | APOLLO ELECTRIC INC. | — |
| 07/19/2024 | Complete | REDLINE ELECTRIC INC | — |
| 03/20/2024 | Permit Issued | SAFETECH ELECL CONTNG COR | General Wiring |
| 01/30/2024 | Complete | VERTEX ELECTRIC CORP. | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/17/2025 | Permit Issued | DONATO PLUMBING, INC | Steel |
| 07/25/2025 | Permit Issued | FLOWCON INC | Steel |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/25/2025 | Permit Issued | FLOWCON INC | Tenant Protection Plan 72 Hour |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/25/2025 | Permit Issued | SKYLINE ACCESS LLC | — |
| 04/10/2024 | Permit Issued | — | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/10/2026 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 06/17/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/05/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/23/2026 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 04/07/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 04/06/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/01/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/31/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 03/30/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/27/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/19/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/18/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 03/16/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/13/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 02/19/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 02/17/2026 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 02/13/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 01/29/2026 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 12/17/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 12/17/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 12/15/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/16/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/12/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/02/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/15/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/10/2026 | Fire-Resistant Penetrations and Joints | Frederic Zonsius | special |
| 08/10/2026 | Tenant Protection Plan Compliance | Frederic Zonsius | special |
| 08/10/2026 | Energy Code Compliance Inspections | Nicholas Tucci | progress |
| 08/10/2026 | HVAC-R and service water heating system controls | Nicholas Tucci | energy_progress |
| 08/10/2026 | HVAC-R and service water piping design and insulation | Nicholas Tucci | energy_progress |
| 08/10/2026 | HVAC-R and service water heating equipment | Nicholas Tucci | energy_progress |
| 07/16/2026 | HVAC-R and service water heating equipment | Nicholas Tucci | energy_progress |
| 07/16/2026 | Energy Code Compliance Inspections | Nicholas Tucci | progress |
| 07/16/2026 | Fire-Resistant Penetrations and Joints | Frederic Zonsius | special |
| 07/16/2026 | Tenant Protection Plan Compliance | Frederic Zonsius | special |
| 07/16/2026 | HVAC-R and service water piping design and insulation | Nicholas Tucci | energy_progress |
| 07/16/2026 | HVAC-R and service water heating system controls | Nicholas Tucci | energy_progress |
| 06/18/2026 | Energy Code Compliance Inspections | Nicholas Tucci | progress |
| 06/18/2026 | Tenant Protection Plan Compliance | Frederic Zonsius | special |
| 06/18/2026 | Fire-Resistant Penetrations and Joints | Frederic Zonsius | special |
| 06/18/2026 | HVAC-R and service water piping design and insulation | Nicholas Tucci | energy_progress |
| 06/18/2026 | HVAC-R and service water heating system controls | Nicholas Tucci | energy_progress |
| 06/18/2026 | HVAC-R and service water heating equipment | Nicholas Tucci | energy_progress |
| 05/20/2026 | Fire-Resistant Penetrations and Joints | ALBERT ZIRINO | special |
| 05/20/2026 | HVAC-R and service water piping design and insulation | ALBERT ZIRINO | energy_progress |
| 05/20/2026 | Energy Code Compliance Inspections | ALBERT ZIRINO | progress |
| 04/26/2026 | Energy Code Compliance Inspections | BRENT BUCK | progress |
| 04/26/2026 | Post-installed Anchors | ALBERT ZIRINO | special |
| 04/26/2026 | Fire-Resistant Penetrations and Joints | ALBERT ZIRINO | special |
| 04/26/2026 | Final | BRENT BUCK | progress |