| Owner | Filings | Most Recent |
|---|---|---|
| J G CONSTRUCTION SRVCS | 11 | 03/22/2026 |
| TWO HATTON LLC | 1 | 03/22/2026 |
| SMR CRAFTWORKS INC 1 | 1 | 03/22/2026 |
| CRAFT WORKS INC SMR | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 07/06/2023 | $6.2M | — | Private party → TWO HATTON LLC | $939/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| BAXT INGUI ARCHITECTS | 7 | 04/28/2026 |
| RJD ENGINEERING LLC | 7 | 01/29/2026 |
| D'HUY ENGINEERING, INC. | 2 | 01/21/2026 |
| ASHRAF CORP | 1 | 03/14/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| GAMILL ENGINEERING, PC | 28 | 03/21/2026 |
| KMA DESIGNS LLC | 2 | 03/21/2026 |
| BAXT INGUI ARCHITECTS PC | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SMR CRAFTWORKS INC | General Contractor | 13 | 07/08/2026 |
| J & G CONSTRUCTION SVCS | General Contractor | 12 | 03/21/2026 |
| AQUEDUCT MECHANICAL CORP | Plumbing | 2 | 07/08/2026 |
| AQUEDUCT MECHANICAL CORP | Fire Protection | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| MACIA INSPECTION & TESTIN | 402 | 16 | 04/28/2026 |
| JSPECS,INC | 9429 | 1 | 07/17/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Foundation | Signed-off | TAP METRO ELECTRIC, LLC | 03/10/2026 |
| DOB NOW | Structural | Signed-off | TAP METRO ELECTRIC, LLC | 03/10/2026 |
| DOB NOW | General Construction | Permit Issued | TAP METRO ELECTRIC, LLC | 10/30/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | J & G CONSTRUCTION SVCS | 02/28/2025 |
| DOB NOW | Supported Scaffold | Signed-off | J & G CONSTRUCTION SVCS | 02/28/2025 |
| DOB NOW | Plumbing | Signed-off | AQUEDUCT MECHANICAL CORP | 11/15/2024 |
| DOB NOW | General Construction | Permit Issued | TAP METRO ELECTRIC, LLC | 09/25/2024 |
| DOB NOW | Mechanical Systems | Signed-off | TAP METRO ELECTRIC, LLC | 08/14/2024 |
| DOB NOW | Sprinklers | Signed-off | AQUEDUCT MECHANICAL CORP | 07/23/2024 |
| DOB NOW | General Construction | Permit Issued | TAP METRO ELECTRIC, LLC | 07/12/2024 |
| DOB NOW | Supported Scaffold | Signed-off | J & G CONSTRUCTION SVCS | 03/15/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | J & G CONSTRUCTION SVCS | 03/15/2024 |
| DOB NOW | General Construction | Permit Issued | TAP METRO ELECTRIC, LLC | 12/19/2023 |
| DOB NOW | Plumbing | Signed-off | AQUEDUCT MECHANICAL CORP | 12/07/2023 |
| DOB NOW | General Construction | Signed-off | TAP METRO ELECTRIC, LLC | 11/28/2023 |
| DOB NOW | General Construction | Signed-off | TAP METRO ELECTRIC, LLC | 08/08/2023 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 01/29/2026 | Signed-off | SMR CRAFTWORKS INC | Heating and Air Conditioning Systems, Ventilation Systems | Heat / Cool Mitsubishi Electric PEFY-P08NMAU-E4 9,000 BTU · Vrf Indoor ×8 MXZ-SM48NAMHZ2-U1 54,000 BTU · Condensing Unit ×4 PEFY-P12NMAU-E4 13,500 BTU · Vrf Indoor ×4 PVFY-P18NAMU-E1 20,000 BTU · Vrf Indoor ×4 PVFY-P08NAMU-E1 9,000 BTU · Vrf Indoor ×2 PVFY-P12NAMU-E1 13,500 BTU · Vrf Indoor ×2 Ventilation Zehnder COMFO AIR Q450 203 CFM · Erv ×4 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/12/2026 | Complete | SUPER CHARGED ELEC. INC. | General Wiring |
| 03/15/2024 | Complete | RICHARD NEU | — |
| 01/05/2024 | Complete | SUPER CHARGED ELEC. INC. | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/24/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 09/12/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/21/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 08/18/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 12/13/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 12/13/2024 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 12/13/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/02/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/13/2026 | Mechanical Systems | CHUNG CHING JEN | special |
| 04/13/2026 | Fire-Resistant Penetrations and Joints | CHUNG CHING JEN | special |
| 04/13/2026 | Final | CHUNG CHING JEN | progress |
| 03/04/2026 | Post-installed Anchors | CHUNG CHING JEN | special |
| 03/04/2026 | Masonry | CHUNG CHING JEN | special |
| 03/04/2026 | Structural Steel - High Strength Bolting | CHUNG CHING JEN | special |
| 03/04/2026 | Wood – Seismic Resistance | CHUNG CHING JEN | special |
| 03/04/2026 | Final | CHUNG CHING JEN | progress |
| 03/04/2026 | Structural Cold-Formed Steel | CHUNG CHING JEN | special |
| 03/04/2026 | Concrete - Cast-In-Place | CHUNG CHING JEN | special |
| 03/04/2026 | Footing and Foundation | CHUNG CHING JEN | progress |
| 03/04/2026 | Structural Steel - Details | CHUNG CHING JEN | special |
| 03/04/2026 | Structural Stability – Alterations of existing buildings | CHUNG CHING JEN | special |
| 03/04/2026 | Structural Steel - Welding | CHUNG CHING JEN | special |
| 01/23/2026 | Mechanical Systems | CHUNG CHING JEN | special |
| 01/23/2026 | Fire-Resistant Penetrations and Joints | CHUNG CHING JEN | special |
| 01/23/2026 | Final | CHUNG CHING JEN | progress |
| 01/21/2026 | Fenestration areas | CHUNG CHING JEN | energy_progress |
| 01/21/2026 | Permanent certificate | CHUNG CHING JEN | energy_progress |
| 01/21/2026 | Insulation placement and R values | CHUNG CHING JEN | energy_progress |
| 01/21/2026 | Fenestration air leakage | CHUNG CHING JEN | energy_progress |
| 01/21/2026 | Fire-Resistance Rated Construction | CHUNG CHING JEN | progress |
| 01/21/2026 | Tenant Protection Plan Compliance | — | special |
| 01/21/2026 | Energy Code Compliance Inspections | CHUNG CHING JEN | progress |
| 01/21/2026 | Lighting in dwelling units | CHUNG CHING JEN | energy_progress |