← Back
Two family frame
150-29 27 AVENUE
QUEENS · BIN 4108955
💬 Discuss this project
2024Year Built
2.5Stories
B2Building Class
R4AZoning
2,980 sfGross Floor Area
2Units
0 Open ViolationsFDNY Report ↗
Two family frame · Owner of record: 15029 27TH AVE LLC · 2,945 sf lot · 1.01 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalCivil
Floor 23p · 1 filing · 20 docs
Floor 13p · 1 filing · 20 docs
Cellar4p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
CMBM LLC2703/22/2026
PRIMROSE SERVICE203/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
01/18/2019$800K—RICE, AS CO-EXECUTRIX, JOANNE C. → Private party— not available
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TANG STUDIO ARCHITECT LLC701/02/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
TANG STUDIO LLC803/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
PRIMROSE SERVICE INCGeneral Contractor1503/21/2026
CMBM LLCGeneral Contractor207/08/2026
WHITESTONE PLUMBING CORPPlumbing207/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
TANG STUDIO LLC6949501/02/2025
MEHDI GHAZI, P.E. P.C.7129104/17/2024
Building Lifecycle
All (87)Filed (6)Permit Issued (9)Signed Off (2)Violation (2)Inspection (8)Objection (30)Special Inspection (30)
05/29/2026
Signed off — ALT-CO - New Building with Existing Elements to Remain
INSTALL NEW PLUMBING FIXTURES IN CONJUCITON WITH DOB NOW ALT/CO: q00701527-I1 AS PER PLAN. NO CHANGE OF USE, EGRESS OR OCCUPANCY.
Q00701527-S1
08/21/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
02/25/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
MEHDI GHAZI
02/25/2025
Special inspection requirement — HVAC-R and service water heating equipment
MEHDI GHAZI
02/25/2025
Special inspection requirement — Insulation placement and R values
MEHDI GHAZI
02/25/2025
Special inspection requirement — Fenestration air leakage
MEHDI GHAZI
02/25/2025
Special inspection requirement — Air barrier - visual inspection
MEHDI GHAZI
02/25/2025
Special inspection requirement — Fenestration areas
MEHDI GHAZI
02/25/2025
Special inspection requirement — Footing and Foundation
MEHDI GHAZI
02/25/2025
Special inspection requirement — Ventilation and air distribution system
MEHDI GHAZI
02/25/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
MEHDI GHAZI
02/25/2025
Special inspection requirement — HVAC-R and service water heating system controls
MEHDI GHAZI
02/25/2025
Special inspection requirement — Mechanical Systems
Edwin Tang
02/25/2025
Special inspection requirement — Permanent certificate
MEHDI GHAZI
02/25/2025
Special inspection requirement — Final
MEHDI GHAZI
02/25/2025
Special inspection requirement — Air barrier — testing
MEHDI GHAZI
02/21/2025
Special inspection requirement — Fenestration air leakage
02/21/2025
Special inspection requirement — Permanent certificate
02/21/2025
Special inspection requirement — Mechanical Systems
02/21/2025
Special inspection requirement — Ventilation and air distribution system
02/21/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
02/21/2025
Special inspection requirement — Fenestration areas
02/21/2025
Special inspection requirement — Air barrier - visual inspection
02/21/2025
Special inspection requirement — Air barrier — testing
02/21/2025
Special inspection requirement — HVAC-R and service water heating system controls
02/21/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
02/21/2025
Special inspection requirement — Insulation placement and R values
02/21/2025
Special inspection requirement — HVAC-R and service water heating equipment
02/21/2025
Special inspection requirement — Footing and Foundation
02/21/2025
Special inspection requirement — Final
01/24/2025
Special inspection requirement — Energy Code Compliance Inspections
Edwin Tang
01/24/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Edwin Tang
01/22/2025
Objection resolved — Addressed
01/16/2025
Objection raised — Zoning
01/13/2025
Objection resolved — Addressed
01/10/2025
Objection raised — Scope
01/02/2025
Filed — New Building
PROPOSED 2 STORY NEW BUILDING ON EXISTING LOT FOR TWO FAMILY DWELLING HOUSE. (EXISTING FRONT WALL REBUILD AT THE SAME LOCATION AS PER ZR 54-41 and AI1 APPROVED ON 2023.08.23. WITH EXPEDITED NB REVIEW.)
Q00926222-P3
01/02/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
INSTALL NEW PLUMBING FIXTURES IN CONJUCITON WITH DOB NOW ALT/CO: q00701527-I1 AS PER PLAN. NO CHANGE OF USE, EGRESS OR OCCUPANCY.
Q00701527-P3
12/19/2024
Permit issued — Plumbing
Q00701527-S1-PL
09/30/2024
Signed off — Alteration
SUBMIT TEMPORARY CONSTRUCTION FENCE PLAN IN CONJUNCTION WITH ALT/CO APPLICATION Q00701527
Q00773798-I1
06/12/2024
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
06/12/2024
Inspection — Certified Storm Drainage-ST-Piping-Roughing
Certified
View inspection ↗
06/12/2024
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
06/12/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
06/12/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
05/10/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
05/03/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
04/17/2024
Filed — New Building
PROPOSED 2 STORY NEW BUILDING ON EXISTING LOT FOR TWO FAMILY DWELLING HOUSE. (EXISTING FRONT WALL REBUILD AT THE SAME LOCATION AS PER ZR 54-41 and AI1 APPROVED ON 2023.08.23. WITH EXPEDITED NB REVIEW.)
Q00926222-P1
04/08/2024
Permit issued — Plumbing
Q00701527-S1-PL
02/29/2024
Permit issued — Construction Fence
Q00773798-I1-FN
02/27/2024
Permit issued — Earth Work
Q00926222-I1-GC
02/27/2024
Violation issued (ECB, closed)
Construction
12/01/2023
Permit issued — Mechanical Systems
Q00926222-I1-ST
12/01/2023
Permit issued — Mechanical Systems
Q00926222-I1-GC
12/01/2023
Permit issued — Structural
Q00926222-I1-MS
11/29/2023
Permit issued — Earth Work
Q00926222-I1-FO-EA
11/09/2023
Objection resolved — Addressed
11/08/2023
Objection raised — Admin
11/06/2023
Objection resolved — Addressed
11/06/2023
Objection resolved — Addressed
Latest 60 of 87 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offWHITESTONE PLUMBING CORP12/19/2024
DOB NOWPlumbingSigned-offWHITESTONE PLUMBING CORP04/08/2024
DOB NOWConstruction FenceSigned-offCMBM LLC02/29/2024
DOB NOWEarth WorkPermit IssuedPRIMROSE SERVICE INC02/27/2024
DOB NOWMechanical SystemsSigned-offPRIMROSE SERVICE INC12/01/2023
DOB NOWMechanical SystemsPermit IssuedPRIMROSE SERVICE INC12/01/2023
DOB NOWStructuralSigned-offPRIMROSE SERVICE INC12/01/2023
DOB NOWEarth WorkSigned-offPRIMROSE SERVICE INC11/29/2023
DOB NOWConstruction FenceSigned-offCMBM LLC03/31/2023
1 project · most recent 01/02/2025
Air Conditioning Systems Heating Systems
FiledStatusContractorScopeMake / Model / Capacity
01/02/2025Permit IssuedPRIMROSE SERVICE INCAir Conditioning Systems, Heating Systems
Cooling
Mitsubishi Electric MLZ-KP12NA (Indoor Unit #1 - Cooling) MEA 122-06-E 12,000 BTU · Split System ×4
MSZ-FS12NA (Indoor Unit #2 - Cooling) 12,000 BTU · Heat Pump Outdoor ×9
MXZ-SM48NAMHZ2 (Outdoor Unit #1 - Cooling) 48,000 BTU · Vrf Outdoor ×1
MXZ-SM48NAMHZ2 (Outdoor Unit #2 - Cooling) 36,000 BTU · Heat Pump Outdoor ×1
MLZ-KP12NA (Indoor Unit #1 - Cooling) 12,000 BTU · Vrf Indoor ×8
MXZ-SM36NAMHZ (Outdoor Unit #2 - Cooling) 36,000 BTU · Heat Pump Outdoor ×2
MXZ-SM48NAMHZ (Outdoor Unit #1 - Cooling) 48,000 BTU · Split System ×2
Heating
Mitsubishi Electric MLZ-KP12NA (Indoor Unit #1 - Heating) MEA 122-06-E 15,000 BTU · Heat Pump Outdoor ×4
MSZ-FS12NA (Indoor Unit #2 - Heating) 12,300 BTU · Heat Pump Outdoor ×9
MXZ-SM48NAMHZ2 (Outdoor Unit #1 - Heating) 54,000 BTU · Heat Pump Outdoor ×1
MXZ-SM48NAMHZ2(Outdoor Unit #2 - Heating) 42,000 BTU · Heat Pump Outdoor ×1
MLZ-KP12NA (Indoor Unit #1 - Heating) 15,000 BTU · Heat Pump Outdoor ×8
MXZ-SM36NAMHZ (Outdoor Unit #2 - Heating) 42,000 BTU · Heat Pump Outdoor ×2
MXZ-SM48NAMHZ (Outdoor Unit #1 - Heating) 54,000 BTU · Heat Pump Outdoor ×2
1 project · most recent 01/02/2025
Gas Storm Water/Sanitary
FiledStatusContractorScope
01/02/2025Signed-offWHITESTONE PLUMBING CORPGas, Storm, Water/Sanitary
1 project · most recent 05/22/2023
General Wiring
FiledStatusContractorScope
05/22/2023Permit IssuedAL-LECTRIC ELECT'L CONTRGGeneral Wiring
1 project · most recent 01/02/2025
Wood
FiledStatusContractorScope
01/02/2025Permit IssuedPRIMROSE SERVICE INCWood
1 project · most recent 01/02/2025
Earthwork
FiledStatusContractorScope
01/02/2025Permit IssuedPRIMROSE SERVICE INCEarthwork
▾Field Inspections (DOB CAP) — 8
DateTypeResultReport
08/21/2025Pass-Final CND-Occupancy InspectionPassView ↗
06/12/2024Certified Gas-Gas-Piping-RoughingCertifiedView ↗
06/12/2024Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
06/12/2024Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
06/12/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
06/12/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
05/10/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
05/03/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 61
DateRequirementInspectorRole
02/25/2025Mechanical SystemsEdwin Tangspecial
02/25/2025Footing and FoundationMEHDI GHAZIprogress
02/25/2025FinalMEHDI GHAZIprogress
02/25/2025Fenestration areasMEHDI GHAZIenergy_progress
02/25/2025Permanent certificateMEHDI GHAZIenergy_progress
02/25/2025Fenestration air leakageMEHDI GHAZIenergy_progress
02/25/2025Insulation placement and R valuesMEHDI GHAZIenergy_progress
02/25/2025HVAC-R and service water heating equipmentMEHDI GHAZIenergy_progress
02/25/2025Air barrier — testing MEHDI GHAZIenergy_progress
02/25/2025Air barrier - visual inspectionMEHDI GHAZIenergy_progress
02/25/2025Fenestration and door U-factor and product ratingsMEHDI GHAZIenergy_progress
02/25/2025HVAC-R and service water heating system controlsMEHDI GHAZIenergy_progress
02/25/2025HVAC-R and service water piping design and insulationMEHDI GHAZIenergy_progress
02/25/2025Ventilation and air distribution systemMEHDI GHAZIenergy_progress
02/21/2025Mechanical Systems—special
02/21/2025Final—progress
02/21/2025Footing and Foundation—progress
02/21/2025HVAC-R and service water heating equipment—energy_progress
02/21/2025Insulation placement and R values—energy_progress
02/21/2025Fenestration and door U-factor and product ratings—energy_progress
02/21/2025HVAC-R and service water heating system controls—energy_progress
02/21/2025Air barrier — testing —energy_progress
02/21/2025Air barrier - visual inspection—energy_progress
02/21/2025Fenestration air leakage—energy_progress
02/21/2025Fenestration areas—energy_progress
Latest 25 of 61.
▾Documents — 79 on file (BIS + DOB NOW)
▸Plans & Drawings6
▸DOB NOWPlans/Sketch6
08/26/2026Q00773798-I1Request digital key ↗
08/25/2026Q00701527-P1Request digital key ↗
08/25/2026Q00701527-P3Request digital key ↗
Showing 3 of 6 on file for this type
▸Applications & Permits4
▸BISPLAN / WORK APPROVAL APPLICATION2
11/29/2024440815986Open ↗
02/26/2024440815986Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation1
07/05/2024440815986Open ↗
▸BISBPP-DOT: SIDEWALK/CURB/ROAD WORK PERMITS1
08/05/2025440815986Open ↗
▸Zoning, Tax Lot & Property Records6
▸DOB NOWZD1: DOB Zoning Diagram3
08/21/2026Q00926222-P3Open ↗
08/21/2026Q00926222-P1Open ↗
08/21/2026Q00926222-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)2
08/21/2026Q00926222-P3Open ↗
08/21/2026Q00926222-P1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/21/2026Q00926222-I1Open ↗
▸Seals & Professional Certifications31
▸DOB NOWProgress Inspector Seal & Signature18
09/01/2026Q00701527-P1Open ↗
09/01/2026Q00701527-P1Open ↗
09/01/2026Q00701527-P1Open ↗
Showing 3 of 18 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature6
08/26/2026Q00773798-I1Open ↗
08/25/2026Q00701527-P1Open ↗
08/25/2026Q00701527-S1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
09/01/2026Q00701527-P1Open ↗
08/30/2026Q00926222-I1Open ↗
08/24/2026Q00926222-P1Open ↗
Showing 3 of 4 on file for this type
▸BISAPPLICANT OWNER SIGNATURE2
02/26/2024440815986Open ↗
02/08/2024440811445Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
02/26/2024440815986Open ↗
▸Trade Schedules & Equipment2
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)2
08/21/2026Q00926222-P3Open ↗
08/21/2026Q00926222-P1Open ↗
▸Safety & Tenant Protection8
▸DOB NOWStreet Tree Checklist2
08/21/2026Q00926222-P3Open ↗
08/21/2026Q00926222-P1Open ↗
▸BISSTREET TREES: RECEIPT OF STREET TREES SITE PLAN1
07/05/2024440815986Open ↗
▸BISSTREET TREE SUPPORTING DOCUMENT1
08/05/2025440815986Open ↗
▸BISSTREET TREE CHECKLIST1
03/08/2024440815986Open ↗
▸BISSTREET TREES SITE PLAN1
07/05/2024440815986Open ↗
▸DOB NOWStreet Trees Site Plan1
08/21/2026Q00926222-I1Open ↗
▸DOB NOWStreet Tree Sign Off1
08/21/2026Q00926222-I1Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/25/2026Q00701527-P1Open ↗
08/15/2026Q00701527-S1Open ↗
08/13/2026Q00701527-P3Open ↗
▸Inspections & Test Reports1
▸BISBPP - Inspection Appointment Form1
08/05/2025440815986Open ↗
▸Approvals, Objections & Sign-offs1
▸BISBPP-8 - Request Items for Builders Pavement Plan Signoff1
08/05/2025440815986Open ↗
▸Cost, Insurance & Ownership1
▸BISBPP-11 - Affidavit as to Roadway Pavement And/Or Sidewalk and Curb Construction1
08/05/2025440815986Open ↗
▸Filing & Intake Forms5
▸BISBPP: CHECKLIST IN LIEU OF PLANS-ALT32
07/05/2024440815986Open ↗
02/08/2024440811445Open ↗
▸BISADDITIONAL INFORMATION2
12/05/2024440815986Open ↗
07/05/2024440815986Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
02/26/2024440815986Open ↗
▸Other Documents11
▸BISBPP - SUPPORTING DOCUMENTATION2
08/05/2025440815986Open ↗
08/05/2025440815986Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/21/2026Q00926222-P3Open ↗
08/21/2026Q00926222-P1Open ↗
▸DOB NOWSite Survey: Initial2
08/21/2026Q00926222-P3Open ↗
08/21/2026Q00926222-P1Open ↗
▸DOB NOWProperty Ownership Certification2
08/21/2026Q00926222-P3Open ↗
08/21/2026Q00926222-P1Open ↗
▸BISBPP: PHOTOS-SIGNED/SEALED BY APPLICANT1
07/05/2024440815986Open ↗
▸DOB NOWFinal Survey1
08/21/2026Q00926222-I1Open ↗
▸DOB NOWAdjoining Owners Notification1
08/21/2026Q00926222-I1Open ↗