| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/22/2025 | Permit Issued | TARGET PIPING NY LLC | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/13/2024 | Complete | SOLAS ELECTRICAL CORP | — |
| 07/13/2023 | Permit Issued | POWER DIRECT ELECTRIC INC | General Wiring |
| 04/25/2023 | Permit Issued | POWER DIRECT ELECTRIC INC | — |
| Owner | Filings | Most Recent |
|---|---|---|
| OWNERS REP | 7 | 07/08/2026 |
| SKYLINE BUILDERS NYC | 3 | 03/22/2026 |
| 1504-1506 AVE L LLC | 4 | 03/22/2026 |
| CORE SCAFFOLD SYSTEMS | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| KAO HWA LEE ARCHITECTS PC | 7 | 12/22/2025 |
| PAUL PERDEK, PROF. ENG. PLLC | 3 | 03/06/2024 |
| A&D ENGINEERING, PLLC | 3 | 09/22/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| 4444 PPPP CORP | 16 | 03/21/2026 |
| RELIABLE EXPEDITING | 1 | 03/21/2026 |
| AE DESIGN SOLUTION | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SKYLINE BUILDERS NYC CORP | General Contractor | 23 | 08/20/2026 |
| TARGET PIPING NY LLC | Fire Protection | 6 | 08/13/2026 |
| CORE SCAFFOLD SYSTEMS INC. | General Contractor | 5 | 07/08/2026 |
| B&B MECH PLBG & HTG LLC | Plumbing | 3 | 08/26/2026 |
| POWER DIRECT ELECTRIC INC | Electrical | 2 | 03/22/2026 |
| PRIME PIPING & HEATING IN | Fire Protection | 1 | 07/08/2026 |
| SOLAS ELECTRICAL CORP | Electrical | 1 | 03/22/2026 |
| MPI PLUMBING CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HRF SERVICES CORP | 5616 | 8 | 10/16/2025 |
| LEO Y LEE ASSOCIATES | 2481 | 1 | 03/06/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Permit Issued | SKYLINE BUILDERS NYC CORP | 08/18/2026 |
| DOB NOW | Standpipe | Permit Issued | TARGET PIPING NY LLC | 08/12/2026 |
| DOB NOW | Sprinklers | Permit Issued | TARGET PIPING NY LLC | 07/22/2026 |
| DOB NOW | Plumbing | Permit Issued | B&B MECH PLBG & HTG LLC | 07/14/2026 |
| DOB NOW | General Construction | Permit Issued | SKYLINE BUILDERS NYC CORP | 07/13/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | SKYLINE BUILDERS NYC CORP | 06/25/2026 |
| DOB NOW | General Construction | Permit Issued | SKYLINE BUILDERS NYC CORP | 03/12/2026 |
| DOB NOW | General Construction | Permit Issued | SKYLINE BUILDERS NYC CORP | 01/02/2026 |
| DOB NOW | Foundation | Permit Issued | SKYLINE BUILDERS NYC CORP | 01/02/2026 |
| DOB NOW | Construction Fence | Signed-off | SKYLINE BUILDERS NYC CORP | 01/02/2026 |
| DOB NOW | Sprinklers | Permit Issued | TARGET PIPING NY LLC | 08/14/2025 |
| DOB NOW | Standpipe | Permit Issued | TARGET PIPING NY LLC | 07/24/2025 |
| DOB NOW | Plumbing | Permit Issued | TARGET PIPING NY LLC | 07/16/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | SKYLINE BUILDERS NYC CORP | 07/01/2025 |
| DOB NOW | General Construction | Permit Issued | SKYLINE BUILDERS NYC CORP | 03/17/2025 |
| DOB NOW | Construction Fence | Signed-off | SKYLINE BUILDERS NYC CORP | 12/24/2024 |
| DOB NOW | General Construction | Permit Issued | SKYLINE BUILDERS NYC CORP | 09/09/2024 |
| DOB NOW | Standpipe | Permit Issued | TARGET PIPING NY LLC | 08/16/2024 |
| DOB NOW | Standpipe | Permit Issued | TARGET PIPING NY LLC | 07/30/2024 |
| DOB NOW | Plumbing | Permit Issued | TARGET PIPING NY LLC | 07/22/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | SKYLINE BUILDERS NYC CORP | 07/03/2024 |
| DOB NOW | Supported Scaffold | Signed-off | CORE SCAFFOLD SYSTEMS INC | 04/23/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | CORE SCAFFOLD SYSTEMS INC | 04/01/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | CORE SCAFFOLD SYSTEMS INC | 03/20/2024 |
| DOB NOW | Earth Work | Permit Issued | SKYLINE BUILDERS NYC CORP | 03/15/2024 |
| DOB NOW | Support of Excavation | Signed-off | SKYLINE BUILDERS NYC CORP | 12/28/2023 |
| DOB NOW | Construction Fence | Signed-off | SKYLINE BUILDERS NYC CORP | 12/28/2023 |
| DOB NOW | Plumbing | Permit Issued | YG SERVICES INC | 11/03/2023 |
| DOB NOW | Construction Fence | Signed-off | SKYLINE BUILDERS NYC CORP | 11/01/2023 |
| DOB NOW | Sprinklers | Permit Issued | A M B MECHANICAL INC | 09/25/2023 |
| DOB NOW | General Construction | Permit Issued | SKYLINE BUILDERS NYC CORP | 09/15/2023 |
| DOB NOW | Foundation | Permit Issued | SKYLINE BUILDERS NYC CORP | 03/21/2023 |
| DOB NOW | General Construction | Permit Issued | SKYLINE BUILDERS NYC CORP | 02/14/2023 |
| DOB NOW | Support of Excavation | Signed-off | SKYLINE BUILDERS NYC CORP | 02/02/2023 |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/05/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 02/11/2026 | Pass-Final PL - Underground | Pass | View ↗ |
| 09/24/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/06/2024 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 03/07/2024 | Pass-Final PL - Underground | Pass | View ↗ |
| 03/13/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/20/2023 | Pass-Final PL - Underground | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 02/04/2026 | Maintenance information | FAHAD FATEH | energy_progress |
| 02/04/2026 | Fenestration areas | FAHAD FATEH | energy_progress |
| 02/04/2026 | Subgrade Inspections | FAHAD FATEH | special |
| 02/04/2026 | Concrete - Cast-In-Place | FAHAD FATEH | special |
| 02/04/2026 | Exterior Insulation and Finish Systems (EIFS) | FAHAD FATEH | special |
| 02/04/2026 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 02/04/2026 | Fire-Resistance Rated Construction | FAHAD FATEH | progress |
| 02/04/2026 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 02/04/2026 | Protection of exposed foundation insulation | FAHAD FATEH | energy_progress |
| 02/04/2026 | HVAC-R and service water piping design and insulation | FAHAD FATEH | energy_progress |
| 02/04/2026 | Fenestration air leakage | FAHAD FATEH | energy_progress |
| 02/04/2026 | HVAC-R and service water heating system controls | FAHAD FATEH | energy_progress |
| 02/04/2026 | Air barrier - visual inspection | FAHAD FATEH | energy_progress |
| 02/04/2026 | Exterior lighting power | FAHAD FATEH | energy_progress |
| 02/04/2026 | HVAC-R and service water heating equipment | FAHAD FATEH | energy_progress |
| 02/04/2026 | Electrical motors and elevators | FAHAD FATEH | energy_progress |
| 02/04/2026 | Interior lighting power | FAHAD FATEH | energy_progress |
| 02/04/2026 | Lighting controls | FAHAD FATEH | energy_progress |
| 02/04/2026 | Insulation placement and R values | FAHAD FATEH | energy_progress |
| 02/04/2026 | Metering | FAHAD FATEH | energy_progress |
| 02/04/2026 | Fenestration and door U-factor and product ratings | FAHAD FATEH | energy_progress |
| 09/03/2025 | Electrical motors and elevators | FAHAD FATEH | energy_progress |
| 09/03/2025 | Exterior Insulation and Finish Systems (EIFS) | FAHAD FATEH | special |
| 09/03/2025 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 09/03/2025 | Subgrade Inspections | FAHAD FATEH | special |