| Owner | Filings | Most Recent |
|---|---|---|
| JASCO, INC | 5 | 03/22/2026 |
| 1506 SOUTHERN, LLC | 1 | 03/22/2026 |
| KODRA CONSTRUCTION | 7 | 03/22/2026 |
| KIRI CONSTRUCTION | 1 | 03/22/2026 |
| KODRA CONSTRUCTION CORP 1 | 1 | 03/22/2026 |
| J&H ELECTRICAL CONTRACTING INC | 2 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 11/09/2021 | $1.3M | — | TRID LLC → 1506 SOUTHERN, LLC | $59/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| BADALY ARCHITECTS | 16 | 08/19/2026 |
| ASR ENGINEERING PC | 1 | 07/30/2023 |
| BADALY ENGINEERING PLLC | 1 | 08/18/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| KC EXPEDITING INC | 1 | 03/21/2026 |
| ADVANCED BUILDERS SERVICES | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| KIRI CONSTRUCTION CORP | General Contractor | 10 | 08/25/2026 |
| KODRA CONSTRUCTION CORP | General Contractor | 4 | 07/08/2026 |
| JASCO, INC | General Contractor | 3 | 03/21/2026 |
| INFINITI ESC PLUMBING COR | Plumbing | 3 | 07/08/2026 |
| J&H ELECTRICAL CONT INC | Electrical | 2 | 03/22/2026 |
| GO PRO FIRE PROTECTION C | Fire Protection | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| BADALY ARCHITECT PLLC | 7137 | 14 | 08/19/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Support of Excavation | Permit Issued | KIRI CONSTRUCTION CORP | 08/24/2026 |
| DOB NOW | Curb Cut | Signed-off | KIRI CONSTRUCTION CORP | 04/11/2025 |
| DOB NOW | Boiler Equipment | Signed-off | INFINITI ESC PLUMBING COR | 03/19/2025 |
| DOB NOW | Foundation | Permit Issued | KODRA CONSTRUCTION CORP | 11/14/2024 |
| DOB NOW | Plumbing | Signed-off | INFINITI ESC PLUMBING COR | 10/30/2024 |
| DOB NOW | Construction Fence | Permit Issued | KIRI CONSTRUCTION CORP | 05/28/2024 |
| DOB NOW | Sprinklers | Signed-off | INFINITI ESC PLUMBING COR | 10/31/2023 |
| DOB NOW | Sprinklers | Signed-off | GO PRO FIRE PROTECTION C | 10/31/2023 |
| DOB NOW | Mechanical Systems | Permit Issued | KODRA CONSTRUCTION CORP | 10/19/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | JASCO, INC | 07/31/2023 |
| DOB NOW | Construction Fence | Permit Issued | KIRI CONSTRUCTION CORP | 04/19/2023 |
| DOB NOW | Construction Fence | Permit Issued | KIRI CONSTRUCTION CORP | 04/11/2023 |
| DOB NOW | Foundation | Permit Issued | KODRA CONSTRUCTION CORP | 01/03/2023 |
| DOB NOW | Construction Fence | Permit Issued | KIRI CONSTRUCTION CORP | 04/15/2022 |
| BIS | — | ISSUED | KODRA CONSTRUCTION CORP | 11/16/2022 |
| BIS | — | ISSUED | KODRA CONSTRUCTION CORP | 06/17/2022 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/19/2026 | Permit Issued | KIRI CONSTRUCTION CORP | Air Conditioning Systems, Associated Ducts and Piping, Heating Systems, Ventilation Systems | Cooling International Comfort Products PHB436000K000B0 48,000 BTU · Rooftop Unit ×1 PHD448000 48,000 BTU · Rooftop Unit ×4 Trane 4YCC4048A1070A 46,500 BTU · Condensing Unit ×1 Heating International Comfort Products PHB436000K000B0 46,000 BTU · Rooftop Unit ×1 PHD448000 46,000 BTU · Rooftop Unit ×4 Trane 4YCC4048A1070A 70,000 BTU · Condensing Unit ×1 Ventilation Floaire DDAR10 1,385 CFM ×11 Ducts & Piping International Comfort Products PHB436000K000B0 20,000 BTU · Ductwork ×8 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/19/2026 | Signed-off | GO PRO FIRE PROTECTION C | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/19/2026 | Signed-off | INFINITI ESC PLUMBING COR | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/23/2026 | Complete | J&H ELECTRICAL CONT INC | General Wiring |
| 08/01/2023 | Complete | RICHARD NEU | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/19/2026 | Permit Issued | KIRI CONSTRUCTION CORP | Steel, Masonry |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/29/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 07/10/2025 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 06/18/2025 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 05/02/2025 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 04/18/2025 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |
| 03/18/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 01/14/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/28/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/24/2024 | Certified Sprinkler-Dry Pipe Valve (SP)-Dry Pipe Valve Test | Certified | View ↗ |
| 05/24/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 02/09/2024 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 02/09/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/13/2023 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 11/13/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/19/2026 | Fenestration and door U-factor and product ratings | MOHAMMAD BADALY | energy_progress |
| 08/19/2026 | Metering | MOHAMMAD BADALY | energy_progress |
| 08/19/2026 | Lighting controls | MOHAMMAD BADALY | energy_progress |
| 08/19/2026 | Fenestration air leakage | MOHAMMAD BADALY | energy_progress |
| 08/19/2026 | Air barrier - visual inspection | MOHAMMAD BADALY | energy_progress |
| 08/19/2026 | Chimneys and vents | MOHAMMAD BADALY | special |
| 08/19/2026 | Concrete - Cast-In-Place | MOHAMMAD BADALY | special |
| 08/19/2026 | Fire-Resistant Penetrations and Joints | MOHAMMAD BADALY | special |
| 08/19/2026 | Heating Systems | MOHAMMAD BADALY | special |
| 08/19/2026 | Masonry | MOHAMMAD BADALY | special |
| 08/19/2026 | Mechanical Systems | MOHAMMAD BADALY | special |
| 08/19/2026 | Structural Cold-Formed Steel | MOHAMMAD BADALY | special |
| 08/19/2026 | Structural Steel - Details | MOHAMMAD BADALY | special |
| 08/19/2026 | Structural Steel - High Strength Bolting | MOHAMMAD BADALY | special |
| 08/19/2026 | Structural Steel - Welding | MOHAMMAD BADALY | special |
| 08/19/2026 | Subgrade Inspections | MOHAMMAD BADALY | special |
| 08/19/2026 | Subsurface Investigations (Borings/Test Pits) | SOORJBALLY HARILALL | special |
| 08/19/2026 | Energy Code Compliance Inspections | MOHAMMAD BADALY | progress |
| 08/19/2026 | Final | MOHAMMAD BADALY | progress |
| 08/19/2026 | Fire-Resistance Rated Construction | MOHAMMAD BADALY | progress |
| 08/19/2026 | Footing and Foundation | MOHAMMAD BADALY | progress |
| 08/19/2026 | Duct leakage testing, insulation and design | MOHAMMAD BADALY | energy_progress |
| 08/19/2026 | HVAC-R and service water heating system controls | MOHAMMAD BADALY | energy_progress |
| 08/19/2026 | Lighting in dwelling units | MOHAMMAD BADALY | energy_progress |
| 08/19/2026 | Air barrier — testing | MOHAMMAD BADALY | energy_progress |