| Owner | Filings | Most Recent |
|---|---|---|
| BLUE STAR GROUP | 18 | 04/09/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| PARKER AND WEST ENGINEERING, PLLC | 1 | 10/30/2025 |
| JOSEPH M. MORACE, A.I.A., ARCHITECT | 4 | 10/10/2025 |
| A TECH ENGINEERING NYC, PLLC. | 1 | 03/21/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| BLUE STAR HOLDING | 8 | 03/21/2026 |
| SUNRUN | 1 | 03/21/2026 |
| A TECH ENGINEERING NYC | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| BLUE STAR GROUP LLC | General Contractor | 2 | 04/09/2026 |
| CAPITAL CONTR P&H CORP | Plumbing | 2 | 07/08/2026 |
| SUNRUN INSTALLATION SVC | General Contractor | 1 | 04/09/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| PARKER AND WEST ENGINEERI | 5272 | 1 | 10/30/2025 |
| A TECH ENGINEERING NYC, P | 6738 | 2 | 10/10/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | SUNRUN INSTALLATION SVC | 11/06/2025 |
| DOB NOW | Curb Cut | Signed-off | BLUE STAR GROUP LLC | 09/18/2025 |
| DOB NOW | Plumbing | Signed-off | CAPITAL CONTR P&H CORP | 05/09/2025 |
| DOB NOW | Plumbing | Signed-off | CAPITAL CONTR P&H CORP | 05/09/2025 |
| DOB NOW | Structural | Permit Issued | BLUE STAR GROUP LLC | 04/23/2025 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/10/2025 | Signed-off | CAPITAL CONTR P&H CORP | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/05/2025 | Complete | TRUE ELECTRIC CORP. | General Wiring |
| 10/30/2025 | Complete | SUNRUN SOLAR ELECTL CORP | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/10/2025 | Signed-off | BLUE STAR GROUP LLC | Concrete, Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 12/23/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/12/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 12/12/2025 | Pass-Final Storm Drainage-ST-Fixtures-Finish | Pass | View ↗ |
| 12/02/2025 | Certified Sprinkler (PL)-SP-Fixtures (PL)-Finish | Certified | View ↗ |
| 11/26/2025 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 11/26/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/15/2025 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 08/19/2025 | Certified Sprinkler (PL)-Sprinkler-Hydro | Certified | View ↗ |
| 08/07/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/09/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/20/2026 | Concrete - Cast-In-Place | anthony santoro | special |
| 01/20/2026 | Subsurface Investigations (Borings/Test Pits) | anthony santoro | special |
| 01/20/2026 | Mechanical Systems | anthony santoro | special |
| 01/20/2026 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | anthony santoro | special |
| 01/20/2026 | Wood – Prefabricated I-Joists | anthony santoro | special |
| 01/20/2026 | Fire-Resistant Penetrations and Joints | anthony santoro | special |
| 01/20/2026 | Subgrade Inspections | anthony santoro | special |
| 01/20/2026 | Footing and Foundation | anthony santoro | progress |
| 01/20/2026 | Fire-Resistance Rated Construction | anthony santoro | progress |
| 01/20/2026 | Structural Wood Frame | anthony santoro | progress |
| 01/20/2026 | Final | anthony santoro | progress |
| 01/20/2026 | Energy Code Compliance Inspections | anthony santoro | progress |
| 01/20/2026 | Ventilation and air distribution system | anthony santoro | energy_progress |
| 01/20/2026 | Metering | anthony santoro | energy_progress |
| 01/20/2026 | Electric vehicle service equipment requirements | anthony santoro | energy_progress |
| 01/20/2026 | Air barrier — testing | anthony santoro | energy_progress |
| 01/20/2026 | Fenestration air leakage | anthony santoro | energy_progress |
| 01/20/2026 | Fenestration areas | anthony santoro | energy_progress |
| 01/20/2026 | HVAC-R and service water piping design and insulation | anthony santoro | energy_progress |
| 01/20/2026 | Interior lighting power | anthony santoro | energy_progress |
| 01/20/2026 | HVAC-R and service water heating system controls | anthony santoro | energy_progress |
| 01/20/2026 | Fenestration and door U-factor and product ratings | anthony santoro | energy_progress |
| 01/20/2026 | Permanent certificate | anthony santoro | energy_progress |
| 01/20/2026 | Air barrier - visual inspection | anthony santoro | energy_progress |
| 01/20/2026 | HVAC-R and service water heating equipment | anthony santoro | energy_progress |