| Owner | Filings | Most Recent |
|---|---|---|
| GOLDEN PROPERTIES | 2 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 12/06/2018 | $1.7M | — | TRACT, LLC → SEA SEA, LLC | $1,137/sf building |
| 07/07/2015 | $700K | — | Private party → GOLDEN PROPERTIES, LLC | $479/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| FL&M ENGINEERING DESIGN &INSPECTION | 2 | 09/11/2026 |
| ENGINEERING PROFESSIONAL SERVICE P. | 4 | 07/08/2026 |
| STRUCTURAL ENGINEERING TECHNOLOGIES | 3 | 04/20/2026 |
| EYAL LEVITT ARCHITECT PC | 3 | 03/18/2026 |
| ADROIT ENGINEERING PLLC | 3 | 01/21/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| EXSPEEDIUM | 8 | 03/21/2026 |
| AVALON DESIGNS | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ROYAL HOME IMPROVEMENTS INC | General Contractor | 14 | 07/08/2026 |
| SWIFT SERVICES CORP | General Contractor | 6 | 03/21/2026 |
| SAFETY FIRE SPRINKLER CORP | Fire Protection | 3 | 09/07/2026 |
| HARTZION ENTERPRISES CORP | General Contractor | 3 | 09/13/2026 |
| P.H. WORKS INC | Plumbing | 1 | 06/28/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HRF SERVICES CORP | 5616 | 7 | 07/08/2026 |
| ADROIT ENGINEERING PLLC | 8885 | 1 | 11/27/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Standpipe | Permit Issued | SAFETY FIRE SPRINKLER CORP | 09/03/2026 |
| DOB NOW | Foundation | Permit Issued | ROYAL HOME IMPROVEMENTS I | 12/23/2025 |
| DOB NOW | Construction Fence | Signed-off | ROYAL HOME IMPROVEMENTS I | 06/25/2025 |
| DOB NOW | Full Demolition | Signed-off | SWIFT SERVICES CORP | 03/20/2025 |
| DOB NOW | Construction Fence | Signed-off | ROYAL HOME IMPROVEMENTS I | 07/23/2024 |
| BIS | OT | ISSUED | KISHAN PLUMBING & HEATING | 01/03/2018 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 09/11/2026 | Permit Issued | HARTZION ENTERPRISES CORP | Air Conditioning Systems, Heating and Air Conditioning Systems, Ventilation Systems | Cooling Mitsubishi Electric PUY-A18NKA7 18,000 BTU · Condensing Unit ×1 Heat / Cool Mitsubishi Electric PUZ - A18NKA7 18,000 BTU · Condensing Unit ×1 PUZ - A24NHA7 24,000 BTU · Condensing Unit ×1 SUZ - KA18NA2 18,000 BTU · Condensing Unit ×1 Ventilation Mitsubishi Electric LGH-F470RVX2-E 470 CFM · Erv ×4 LGH-F600RVX2-E 600 CFM · Erv ×2 LGH-F300RVX2-E 300 CFM · Erv ×1 LGH-F380RVX2-E 380 CFM · Erv ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/11/2026 | Permit Issued | SAFETY FIRE SPRINKLER COR | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/11/2026 | Permit Issued | P.H. WORKS INC | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/11/2026 | Permit Issued | HARTZION ENTERPRISES CORP | Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/11/2026 | Permit Issued | HARTZION ENTERPRISES CORP | Fence, Scaffold, Sidewalk Shed |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/12/2026 | Duct leakage testing, insulation and design | — | energy_progress |
| 03/12/2026 | HVAC-R and service water heating equipment | — | energy_progress |
| 03/12/2026 | Maintenance information | — | energy_progress |
| 03/12/2026 | Shutoff dampers | — | energy_progress |
| 03/12/2026 | HVAC-R and service water heating system controls | FAHAD FATEH | energy_progress |
| 03/12/2026 | Heating Systems | — | special |
| 03/12/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 03/12/2026 | Post-installed Anchors | — | special |
| 03/12/2026 | Energy Code Compliance Inspections | — | progress |
| 03/12/2026 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 03/12/2026 | HVAC-R and service water heating system controls | — | energy_progress |
| 03/12/2026 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | FAHAD FATEH | special |
| 03/12/2026 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 03/12/2026 | HVAC-R and service water piping design and insulation | FAHAD FATEH | energy_progress |
| 03/12/2026 | HVAC-R and service water heating equipment | FAHAD FATEH | energy_progress |
| 03/12/2026 | Maintenance information | FAHAD FATEH | energy_progress |
| 03/09/2026 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 03/09/2026 | Post-installed Anchors | FAHAD FATEH | special |
| 03/09/2026 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 02/06/2026 | Final | — | progress |
| 02/06/2026 | Sprinkler Systems | FAHAD FATEH | special |
| 02/06/2026 | Standpipe Systems | FAHAD FATEH | special |
| 02/06/2026 | Mechanical Systems | — | special |
| 12/05/2024 | Concrete - Cast-In-Place | FAHAD FATEH | special |
| 12/05/2024 | Deep Foundation Elements | FAHAD FATEH | special |