← Back
QUEENS
152-14 BAYSIDE AVENUE
QUEENS · Murray Hill-Broadway Flushing · BIN 4109391
💬 Discuss this project
—Year Built
—Stories
—Building Class
—Zoning
—Gross Floor Area
—Units
Flood zone X
Locations of Work
Electrical
Roof1p · 1 filing · 10 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MOMENTUM SOLAR204/13/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
JEFFREY MARINELLOElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SHAHRISH SHUVO ENGINEERIN8524204/13/2026
Building Lifecycle
All (9)Filed (2)Permit Issued (1)Objection (2)Special Inspection (4)
04/13/2026
Filed — Alteration
Installation of solar panels, rooftop, railed, grid-tied, 29 modules, 11.6 KW
Q00978548-P1
08/06/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Shahrish Shuvo
08/06/2024
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
08/06/2024
Special inspection requirement — Final
Mina Makar
08/06/2024
Special inspection requirement — Air barrier - visual inspection
Mina Makar
01/26/2024
Permit issued — Solar
Q00978548-I1-SL
01/18/2024
Objection resolved — Addressed
01/09/2024
Objection raised — Other
01/04/2024
Filed — Alteration
Installation of solar panels, rooftop, railed, grid-tied, 29 modules, 11.6 KW
Q00978548-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarPermit IssuedMOMENTUM SOLAR01/26/2024
1 project · most recent 01/02/2024
FiledStatusContractorScope
01/02/2024CompleteISLAND ELECTRIC CORP—
1 project · most recent 04/13/2026
FiledStatusContractorScope
04/13/2026Permit IssuedMOMENTUM SOLAR58 panels, 23.2 kw, 510 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 4
DateRequirementInspectorRole
08/06/2024Fire-Resistant Penetrations and JointsShahrish Shuvospecial
08/06/2024Energy Code Compliance InspectionsMina Makarprogress
08/06/2024FinalMina Makarprogress
08/06/2024Air barrier - visual inspectionMina Makarenergy_progress
▾Documents — 11 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/17/2026Q00978548-I1Request digital key ↗
08/17/2026Q00978548-P1Request digital key ↗
▸Applications & Permits1
▸BISPLAN / WORK APPROVAL APPLICATION1
03/31/2022401862365Open ↗
▸Seals & Professional Certifications5
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/17/2026Q00978548-I1Open ↗
08/17/2026Q00978548-P1Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
08/23/2026Q00978548-P1Open ↗
08/23/2026Q00978548-P1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/23/2026Q00978548-P1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/17/2026Q00978548-I1Open ↗
08/17/2026Q00978548-P1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q00978548-I1Open ↗