Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Whole building & multi-floor projectsExtell Development11 filings
USE OF CRAB HOIST DURING 1522 1st AVENUE CONSTRUCTION DURING MAJOR ALTERATION, FILED SEPARATELY UNDER M00623712
On file for this project
3 documents
USE OF SCISSOR LIFT DURING 1522 1st AVENUE CONSTRUCTION DURING MAJOR ALTERATION, FILED SEPARATELY UNDER M00623712
On file for this project
2 documents
USE OF MINI CRANE DURING 1522 1st AVENUE CONSTRUCTION DURING MAJOR ALTERATION, FILED SEPARATELY UNDER M00623712
On file for this project
4 documents
Latest 3 of 11 filings on this floor.
RoofExtell Development4p · 4 filings · 20 docs
ArchitectureElectricalEquipmentGeneralLandscapeMechanicalPlumbingStructural
Issued Permit Scope
Protection and Mechanical Methods · Supported Scaffold
Use of suspended scaffold to install facade panels.
On file for this project
19 documents · 2 drawing sheets
INSTALLATION & USE OF TEMPORARY ROOF & OVERHEAD PROTECTION AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
On file for this project
4 documents · 2 drawing sheets
USE OF BOOM LIFT CONSTRUCTION EQUIPMENT DURING 1522 1st AVENUE CONSTRUCTION DURING MAJOR ALTERATION, FILED SEPARATELY UNDER M00623712
On file for this project
2 documents
Latest 3 of 4 filings on this floor.
BulkheadExtell Development2p · 1 filing · 19 docs
PlumbingStructural
Use of suspended scaffold to install facade panels.
On file for this project
19 documents · 2 drawing sheets
Floor 19Extell Development2p · 1 filing · 19 docs
ArchitectureElectricalEquipmentGeneralLandscapeMechanicalPlumbingStructural
Issued Permit Scope
Protection and Mechanical Methods
Use of suspended scaffold to install facade panels.
On file for this project
19 documents · 2 drawing sheets
Floor 18Extell Development1p · 1 filing · 19 docs
ArchitectureElectricalEquipmentGeneralLandscapeMechanicalPlumbingStructural
Issued Permit Scope
Protection and Mechanical Methods
Use of suspended scaffold to install facade panels.
On file for this project
19 documents · 1 drawing sheet
Floor 17
Floor 16Extell Development1p · 1 filing · 19 docs
ArchitectureElectricalEquipmentGeneralLandscapeMechanicalPlumbingStructural
Issued Permit Scope
Protection and Mechanical Methods
Use of suspended scaffold to install facade panels.
On file for this project
19 documents · 1 drawing sheet
Floor 15
Floor 14
Floor 13
Floor 12Extell Development2p · 1 filing · 19 docs
ArchitectureElectricalEquipmentGeneralLandscapeMechanicalPlumbingStructural
Issued Permit Scope
Protection and Mechanical Methods
Use of suspended scaffold to install facade panels.
On file for this project
19 documents · 2 drawing sheets
Floor 11Extell Development3p · 1 filing · 19 docs
ArchitectureElectricalEquipmentGeneralLandscapeMechanicalPlumbingStructural
Issued Permit Scope
Protection and Mechanical Methods
Use of suspended scaffold to install facade panels.
On file for this project
19 documents · 3 drawing sheets
Floor 10
Floor 9
Floor 8
Floor 7Extell Development1p · 1 filing · 19 docs
ArchitectureElectricalEquipmentGeneralLandscapeMechanicalPlumbingStructural
Issued Permit Scope
Protection and Mechanical Methods
Use of suspended scaffold to install facade panels.
On file for this project
19 documents · 1 drawing sheet
Floor 6
Floor 5
Floor 4
Floor 3
Floor 2
Floor 1Extell Development1p · 2 filings · 8 docs
ArchitectureElectricalEquipmentGeneralMechanicalPlumbingStructural
Issued Permit Scope
Protection and Mechanical Methods
INSTALLATION & USE OF TEMPORARY ROOF & OVERHEAD PROTECTION AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
On file for this project
4 documents
INSTALLATION OF TEMPORARY PERSONNEL/MATERIAL CONSTRUCTION BASEMENT HOIST COMPLEX AS PER PLANS DURING NB CONSTRUCTION. NO CHANGE IN USE, EGRESS OR OCCUPANCY. HOIST COMPLEX TO COMPLY WITH CHAPTER 33 OF NYC BUILDING CODE.
On file for this project
4 documents · 1 drawing sheet
CellarExtell Development2p · 3 filings · 12 docs
ArchitectureCivilElectricalEquipmentMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Protection and Mechanical Methods
INSTALLATION OF TEMPORARY PERSONNEL/MATERIAL CONSTRUCTION BASEMENT HOIST COMPLEX AS PER PLANS DURING NB CONSTRUCTION. NO CHANGE IN USE, EGRESS OR OCCUPANCY. HOIST COMPLEX TO COMPLY WITH CHAPTER 33 OF NYC BUILDING CODE.
On file for this project
4 documents · 1 drawing sheet
INSTALLATION OF TEMPORARY PARTITION WALLS (SHANTIES) AS PER DWGS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
4 documents
INSTALLATION AND USE OF TEMPORARY SUPPORTED SCAFFOLD AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
4 documents · 1 drawing sheet
Sub-CellarExtell Development1 filing · 4 docs
EquipmentGeneralMechanicalStructural
Issued Permit Scope
Supported Scaffold
INSTALLATION AND USE OF TEMPORARY SUPPORTED SCAFFOLD AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
4 documents
BasementExtell Development1p · 1 filing · 4 docs
Mechanical
INSTALLATION OF TEMPORARY PERSONNEL/MATERIAL CONSTRUCTION BASEMENT HOIST COMPLEX AS PER PLANS DURING NB CONSTRUCTION. NO CHANGE IN USE, EGRESS OR OCCUPANCY. HOIST COMPLEX TO COMPLY WITH CHAPTER 33 OF NYC BUILDING CODE.
On file for this project
4 documents · 1 drawing sheet
Site & exteriorExtell Development6 filings · 16 docs
ArchitectureCivilDMElectricalEquipmentGeneralMechanicalStructural
Issued Permit Scope
Construction Fence · Protection and Mechanical Methods · Sidewalk Shed · Supported Scaffold
INSTALLATION & USE OF TEMPORARY SIDEWALK SHED AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
On file for this project
8 documents · 12 drawing sheets
APPLICATION FOR THE INSTALLATION OF CONSTRUCTION FENCE AS PER PLANS. NO CHANGE IN EGRESS, USE OR OCCUPANCY.
On file for this project
2 documents · 2 drawing sheets
INSTALLATION OF TEMPORARY PERSONNEL/MATERIAL CONSTRUCTION BASEMENT HOIST COMPLEX AS PER PLANS DURING NB CONSTRUCTION. NO CHANGE IN USE, EGRESS OR OCCUPANCY. HOIST COMPLEX TO COMPLY WITH CHAPTER 33 OF NYC BUILDING CODE.
On file for this project
4 documents · 7 drawing sheets
Latest 3 of 6 filings on this floor.
Filed — no permit issuedGlobal BMU facade restoration1 filing · 8 docs
ArchitectureGeneralMechanical
Facade Restoration Via BMU As Shown On Plans
On file for this project
8 documents · 4 drawing sheets