← Back
Walk-up apt, over six families with stores
1524 AMSTERDAM AVENUE
MANHATTAN · Manhattanville-West Harlem · BIN 1059796
💬 Discuss this project
1905Year Built
6Stories
C7Building Class
R7AZoning
15,530 sfGross Floor Area
17Units
Rent Stabilized31 Open Violations 30 unresolved · 1 paperwork only ▸
Walk-up apt, over six families with stores · Owner of record: AMSTERDAM GARVEY HOUSING DEVELOPMENT FUN D CORP. · 4,000 sf lot · 3.88 FAR built · Flood zone X
Locations of Work
ArchitectureElectricalMechanicalPlumbingEquipment
Permit Issued — active, not yet Signed-off
RoofUnder Construction11p · 2 filings · 20 docs
Floor 611p · 1 filing · 20 docs
Floor 511p · 1 filing · 20 docs
Floor 411p · 1 filing · 20 docs
Floor 311p · 1 filing · 20 docs
Floor 211p · 1 filing · 20 docs
Floor 121p · 3 filings · 20 docs
Cellar17p · 2 filings · 20 docs
Site & exterior2p · 1 filing · 2 docs
Filed — no permit issued1p · 1 filing · 4 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
WEST HARLEM GROUP ASSISTANCE2409/13/2026
WHGA GARVEY HDFC303/21/2026
AMSTERDAM GARVEY HOUSING DEVELOPMENT FUN D CORP.203/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
SYNERGIC DESIGN ARCHITECTS108/20/2026
P. M. ARCHITECTURE, PC1804/08/2026
PAUL PERDEK, PROF. ENG. PLLC112/09/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
A1 EXPEDITING SERVICE203/21/2026
PM ARCHITECTURE PC3003/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
J-J PLUMBING CORPPlumbing907/08/2026
NOTIAS CONSTRUCTION INCGeneral Contractor504/09/2026
ACCORD POWER INCGeneral Contractor109/13/2026
AKM CONSTRUCTION NY CORPGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SYNERGIC DESIGN LLC8561108/20/2026
SOCOTEC ENGINEERING49831604/08/2026
Building Lifecycle
All (144)Filed (20)Permit Issued (15)Signed Off (5)Violation (60)Inspection (12)Objection (2)Special Inspection (30)
09/11/2026
Permit issued — Solar
M01348459-I1-SL
08/20/2026
Filed — Alteration
Installation of 24.2 kw solar energy system on two adjacent roof, Lot #105 system size 12.32KW DC and Lot #106, system size 11.88 KW DC with one interconnection to Lot#106 No change of occupancy, use or egress. Work is being paid for under Job# M01377419.
M01348459-I1
05/20/2026
Violation issued (HPD, open)
A
05/20/2026
Violation issued (HPD, open)
A
05/20/2026
Violation issued (HPD, open)
B
05/20/2026
Violation issued (HPD, open)
C
05/20/2026
Violation issued (HPD, open)
C
05/20/2026
Violation issued (HPD, closed)
C
04/29/2026
Violation issued (HPD, closed)
B
04/29/2026
Violation issued (HPD, open)
C
04/29/2026
Violation issued (HPD, closed)
B
04/29/2026
Violation issued (HPD, closed)
B
04/28/2026
Signed off — Alteration
PLUMBING WORK AS PER PLAN .PROVIDING 2 NEW INDIRECT HWH. BOILER PIPING WORK AT CELLAR. M01046947-I1 AND M01046947-S1 FILED FOR BOILER WORKTYPES. NO CHANGE TO USE EGRESS OR OCCUPANCY ON THIS FILING.
M01046947-S1
04/28/2026
Signed off — Alteration
Replace and relocate plumbing fixtures at kitchen bath per revised layout at apt 1A. No change in use egress or occupancy.
M00829056-I1
04/18/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
04/10/2026
Signed off — Alteration
Interior work at common space of building, roof replacement. All work is as per plan. No change to use, egress, or occupancy under this filing.
M00826554-I1
04/10/2026
Signed off — Alteration
Renovated bathrooms and kitchens at Apt 1A for ADA compliance no change to use egress or occupancy
M00830453-I1
04/10/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
04/09/2026
Special inspection requirement — HVAC-R and service water heating system controls
ALEXIS SCHLESSINGERMAN
04/09/2026
Special inspection requirement — Heating Systems
ALEXIS SCHLESSINGERMAN
04/09/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
ALEXIS SCHLESSINGERMAN
04/09/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
ALEXIS SCHLESSINGERMAN
04/09/2026
Special inspection requirement — Tenant Protection Plan Compliance
ALEXIS SCHLESSINGERMAN
04/09/2026
Special inspection requirement — HVAC-R and service water heating equipment
ALEXIS SCHLESSINGERMAN
04/08/2026
Filed — Alteration
PLUMBING WORK AS PER PLAN .PROVIDING 2 NEW INDIRECT HWH. BOILER PIPING WORK AT CELLAR. M01046947-I1 AND M01046947-S1 FILED FOR BOILER WORKTYPES. NO CHANGE TO USE EGRESS OR OCCUPANCY ON THIS FILING.
M01046947-P6
04/08/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
ALEXIS SCHLESSINGERMAN
04/08/2026
Special inspection requirement — Heating Systems
ALEXIS SCHLESSINGERMAN
04/08/2026
Special inspection requirement — Tenant Protection Plan Compliance
ALEXIS SCHLESSINGERMAN
04/08/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
ALEXIS SCHLESSINGERMAN
04/08/2026
Special inspection requirement — HVAC-R and service water heating equipment
ALEXIS SCHLESSINGERMAN
04/08/2026
Special inspection requirement — HVAC-R and service water heating system controls
ALEXIS SCHLESSINGERMAN
04/07/2026
Filed — Alteration
PLUMBING WORK AS PER PLAN .PROVIDING 2 NEW INDIRECT HWH. BOILER PIPING WORK AT CELLAR. M01046947-I1 AND M01046947-S1 FILED FOR BOILER WORKTYPES. NO CHANGE TO USE EGRESS OR OCCUPANCY ON THIS FILING.
M01046947-P7
04/07/2026
Special inspection requirement — Tenant Protection Plan Compliance
ALEXIS SCHLESSINGERMAN
04/06/2026
Filed — Alteration
PLUMBING WORK AS PER PLAN .PROVIDING 2 NEW INDIRECT HWH. BOILER PIPING WORK AT CELLAR. M01046947-I1 AND M01046947-S1 FILED FOR BOILER WORKTYPES. NO CHANGE TO USE EGRESS OR OCCUPANCY ON THIS FILING.
M01046947-P5
04/02/2026
Inspection — Pass-Final Boiler Equipment Inspection
Pass
View inspection ↗
04/02/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
ALEXIS SCHLESSINGERMAN
04/02/2026
Special inspection requirement — Tenant Protection Plan Compliance
04/02/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
ALEXIS SCHLESSINGERMAN
04/02/2026
Special inspection requirement — Tenant Protection Plan Compliance
ALEXIS SCHLESSINGERMAN
04/02/2026
Special inspection requirement — HVAC-R and service water heating system controls
ALEXIS SCHLESSINGERMAN
04/02/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
ALEXIS SCHLESSINGERMAN
04/02/2026
Special inspection requirement — Heating Systems
ALEXIS SCHLESSINGERMAN
04/02/2026
Special inspection requirement — Heating Systems
ALEXIS SCHLESSINGERMAN
04/02/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
ALEXIS SCHLESSINGERMAN
04/02/2026
Special inspection requirement — HVAC-R and service water heating equipment
ALEXIS SCHLESSINGERMAN
04/02/2026
Special inspection requirement — HVAC-R and service water heating system controls
ALEXIS SCHLESSINGERMAN
04/02/2026
Special inspection requirement — HVAC-R and service water heating equipment
ALEXIS SCHLESSINGERMAN
03/31/2026
Special inspection requirement — Tenant Protection Plan Compliance
03/30/2026
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
03/29/2026
Violation issued (HPD, open)
C
03/29/2026
Violation issued (HPD, open)
B
03/19/2026
Permit issued — Boiler Equipment
M01046947-S2-BE
03/03/2026
Violation issued (HPD, open)
B
03/03/2026
Violation issued (HPD, open)
B
02/19/2026
Filed — Alteration
PLUMBING WORK AS PER PLAN .PROVIDING 2 NEW INDIRECT HWH. BOILER PIPING WORK AT CELLAR. M01046947-I1 AND M01046947-S1 FILED FOR BOILER WORKTYPES. NO CHANGE TO USE EGRESS OR OCCUPANCY ON THIS FILING.
M01046947-P3
02/18/2026
Filed — Alteration
PLUMBING WORK AS PER PLAN .PROVIDING 2 NEW INDIRECT HWH. BOILER PIPING WORK AT CELLAR. M01046947-I1 AND M01046947-S1 FILED FOR BOILER WORKTYPES. NO CHANGE TO USE EGRESS OR OCCUPANCY ON THIS FILING.
M01046947-P4
02/13/2026
Special inspection requirement — Tenant Protection Plan Compliance
01/23/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
01/19/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Malathi Ananthakrishnan
01/19/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Malathi Ananthakrishnan
Latest 60 of 144 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarPermit IssuedACCORD POWER INC09/11/2026
DOB NOWBoiler EquipmentSigned-offJ-J PLUMBING CORP03/19/2026
DOB NOWPlumbingSigned-offJ-J PLUMBING CORP09/19/2025
DOB NOWPlumbingSigned-offJ-J PLUMBING CORP09/03/2025
DOB NOWGeneral ConstructionSigned-offNOTIAS CONSTRUCTION INC08/13/2025
DOB NOWGeneral ConstructionSigned-offNOTIAS CONSTRUCTION INC08/12/2025
DOB NOWPlumbingSigned-offJ-J PLUMBING CORP07/16/2025
DOB NOWBoiler EquipmentSigned-offJ-J PLUMBING CORP07/16/2025
DOB NOWPlumbingSigned-offJ-J PLUMBING CORP07/16/2025
DOB NOWSidewalk ShedSigned-offAKM CONSTRUCTION NY12/09/2024
DOB NOWPlumbingSigned-offJ-J PLUMBING CORP10/16/2024
DOB NOWPlumbingSigned-offJ-J PLUMBING CORP08/14/2024
DOB NOWBoiler EquipmentSigned-offJ-J PLUMBING CORP08/14/2024
DOB NOWGeneral ConstructionSigned-offNOTIAS CONSTRUCTION INC06/27/2024
DOB NOWGeneral ConstructionSigned-offNOTIAS CONSTRUCTION INC06/26/2024
BISEQISSUEDROCK SCAFFOLDING CORP04/22/2011
BISEQISSUEDROCK SCAFFOLDING CORP11/01/2010
BISMHISSUEDAL B'S SERVICES INC12/02/1991
BISOTISSUEDNOVALEX CONST.,INC.07/22/1991
1 project · most recent 04/08/2026
Gas
FiledStatusContractorScope
04/08/2026Signed-offJ-J PLUMBING CORPGas
1 project · most recent 09/11/2026
FiledStatusContractorScope
09/11/2026Permit IssuedACCORD POWER ELECTRIC LLC—
1 project · most recent 08/20/2026
FiledStatusContractorScope
08/20/2026Permit IssuedACCORD POWER INC56 panels, 24.64 kw, 2,650.99 roof_area_sqft
▾Field Inspections (DOB CAP) — 12
DateTypeResultReport
04/18/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
04/10/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/02/2026Pass-Final Boiler Equipment InspectionPassView ↗
03/30/2026Fail-Final PL - Up to 3 Requested FloorsFailView ↗
01/23/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
09/03/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
08/18/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
08/18/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
03/21/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/02/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/02/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
12/30/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 71
DateRequirementInspectorRole
04/09/2026HVAC-R and service water heating system controlsALEXIS SCHLESSINGERMANenergy_progress
04/09/2026HVAC-R and service water heating equipmentALEXIS SCHLESSINGERMANenergy_progress
04/09/2026HVAC-R and service water piping design and insulationALEXIS SCHLESSINGERMANenergy_progress
04/09/2026Heating SystemsALEXIS SCHLESSINGERMANspecial
04/09/2026Fire-Resistant Penetrations and JointsALEXIS SCHLESSINGERMANspecial
04/09/2026Tenant Protection Plan ComplianceALEXIS SCHLESSINGERMANspecial
04/08/2026Tenant Protection Plan ComplianceALEXIS SCHLESSINGERMANspecial
04/08/2026HVAC-R and service water heating equipmentALEXIS SCHLESSINGERMANenergy_progress
04/08/2026HVAC-R and service water piping design and insulationALEXIS SCHLESSINGERMANenergy_progress
04/08/2026HVAC-R and service water heating system controlsALEXIS SCHLESSINGERMANenergy_progress
04/08/2026Heating SystemsALEXIS SCHLESSINGERMANspecial
04/08/2026Fire-Resistant Penetrations and JointsALEXIS SCHLESSINGERMANspecial
04/07/2026Tenant Protection Plan ComplianceALEXIS SCHLESSINGERMANspecial
04/02/2026HVAC-R and service water piping design and insulationALEXIS SCHLESSINGERMANenergy_progress
04/02/2026HVAC-R and service water heating equipmentALEXIS SCHLESSINGERMANenergy_progress
04/02/2026HVAC-R and service water heating system controlsALEXIS SCHLESSINGERMANenergy_progress
04/02/2026HVAC-R and service water piping design and insulationALEXIS SCHLESSINGERMANenergy_progress
04/02/2026Heating SystemsALEXIS SCHLESSINGERMANspecial
04/02/2026Fire-Resistant Penetrations and JointsALEXIS SCHLESSINGERMANspecial
04/02/2026Tenant Protection Plan Compliance—special
04/02/2026HVAC-R and service water heating equipmentALEXIS SCHLESSINGERMANenergy_progress
04/02/2026HVAC-R and service water heating system controlsALEXIS SCHLESSINGERMANenergy_progress
04/02/2026Tenant Protection Plan ComplianceALEXIS SCHLESSINGERMANspecial
04/02/2026Heating SystemsALEXIS SCHLESSINGERMANspecial
04/02/2026Fire-Resistant Penetrations and JointsALEXIS SCHLESSINGERMANspecial
Latest 25 of 71.
▾Documents — 123 on file (BIS + DOB NOW)
▸Plans & Drawings20
▸DOB NOWPlans/Sketch20
08/27/2026M00829056-I1Request digital key ↗
08/27/2026M00829056-P1Request digital key ↗
08/27/2026M00826554-I1Request digital key ↗
Showing 3 of 20 on file for this type
▸Applications & Permits4
▸BISWORK PERMIT APPLICATION2
11/05/2010120513612Open ↗
08/05/2010120427911Open ↗
▸BISPLAN / WORK APPROVAL APPLICATION2
11/01/2010120513612Open ↗
08/02/2010120427911Open ↗
▸Seals & Professional Certifications60
▸DOB NOWDPL-1: Design Professional Seal & Signature20
08/27/2026M00829056-P1Open ↗
08/27/2026M00829056-I1Open ↗
08/27/2026M00826554-P1Open ↗
Showing 3 of 20 on file for this type
▸DOB NOWProgress Inspector Seal & Signature16
09/23/2026M01348459-I1Open ↗
09/23/2026M01348459-I1Open ↗
09/23/2026M01348459-I1Open ↗
Showing 3 of 16 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature16
09/23/2026M01348459-I1Open ↗
09/23/2026M01348459-I1Open ↗
09/23/2026M01046947-I1Open ↗
Showing 3 of 16 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION4
11/01/2010120513612Open ↗
08/05/2010120427911Open ↗
08/02/2010120427911Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM2
11/01/2010120513612Open ↗
08/02/2010120427911Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST2
11/01/2010120513612Open ↗
08/02/2010120427911Open ↗
▸Environmental & Asbestos20
▸DOB NOWDEP ACP-5: Asbestos Assessment Report17
08/27/2026M00829056-I1Open ↗
08/27/2026M00829056-P1Open ↗
08/27/2026M00826554-I1Open ↗
Showing 3 of 17 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER1
11/01/2010120513612Open ↗
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'1
08/02/2010120427911Open ↗
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form1
08/25/2026M01055570-I1Open ↗
▸Approvals, Objections & Sign-offs13
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter11
08/27/2026M00826554-I1Open ↗
08/27/2026M00826554-P1Open ↗
08/25/2026M01055570-I1Open ↗
Showing 3 of 11 on file for this type
▸BISADMINISTRATIVE OBJECTIONS2
11/01/2010120513612Open ↗
08/02/2010120427911Open ↗
▸Cost, Insurance & Ownership1
▸BISCOST AFFIDAVIT1
08/02/2010120427911Open ↗
▸Filing & Intake Forms2
▸BISEFILING COVER SHEET2
11/01/2010120513612Open ↗
08/02/2010120427911Open ↗
▸Other Documents3
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone3
08/27/2026M00826554-I1Open ↗
08/27/2026M00826554-P1Open ↗
08/13/2026M00826554-P2Open ↗