← Back
Three families
153-07 76 ROAD
QUEENS · BIN 4538888
💬 Discuss this project
2009Year Built
3Stories
C0Building Class
R4Zoning
2,520 sfGross Floor Area
3Units
Three families · 3,923 sf lot · 0.64 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbing
Floor 33p · 1 filing · 5 docs
Floor 23p · 1 filing · 5 docs
Floor 15p · 2 filings · 16 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
YUVAL GOLAN DEVELOPERS1003/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
OLA CONSULTING ENGINEERS, PC303/11/2024
LANDOW AND LANDOW ARCHITECTS106/27/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
MUNICIPAL BUILDING CONSULTANTS403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
JGM CONSTRUCTION DEVELOPMENTGeneral Contractor907/08/2026
DEMAR PLUMBING CORPFire Protection207/08/2026
DEMAR MECHANICAL INCPlumbing207/08/2026
E.D. MECHANICAL INCPlumbing103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
METRIC CONSULTING AND INS1803403/11/2024
Building Lifecycle
All (40)Filed (4)Permit Issued (8)Inspection (6)Objection (18)Special Inspection (4)
09/04/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
05/23/2024
Inspection — Pass-Final PL - Underground
Pass
View inspection ↗
05/07/2024
Inspection — Pass-Final SP - Up to 3 Requested Floors
Pass
View inspection ↗
03/19/2024
Special inspection requirement — Sprinkler Systems
SAMI HAJJAR P.E
03/11/2024
Filed — Alteration
FILING FOR THE FOLLOWING: PLUMBING - INSTALLATION OF NEW DOMESTIC WATERPIPING, VALVES AND BACKFLOW PREVENTIONDEVICE. SPRINKLER - INSTALLATION OF NEW SPRINKLER PIPING,SPRINKLERS AND COORDINATION WITH ASSOCIATED FIRE ALARM WIRING, CONTROLS,ETC.
Q00536205-P2
02/26/2024
Special inspection requirement — Sprinkler Systems
SAMI HAJJAR P.E
10/11/2023
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
09/01/2023
Filed — Alteration
FILING FOR THE FOLLOWING: PLUMBING - INSTALLATION OF NEW DOMESTIC WATERPIPING, VALVES AND BACKFLOW PREVENTIONDEVICE. SPRINKLER - INSTALLATION OF NEW SPRINKLER PIPING,SPRINKLERS AND COORDINATION WITH ASSOCIATED FIRE ALARM WIRING, CONTROLS,ETC.
Q00536205-P1
08/02/2023
Inspection — Pass-Final SP - Up to 3 Requested Floors
Pass
View inspection ↗
06/20/2023
Permit issued — Sprinklers
Q00536205-I1-EW-SP
08/03/2022
Inspection — Pass-Final PL - Underground
Pass
View inspection ↗
07/01/2022
Permit issued — General Construction
Q00533525-I1-GC
07/01/2022
Permit issued — General Construction
Q00533525-I1-GC
07/01/2022
Permit issued — General Construction
Q00533525-I1-GC
07/01/2022
Permit issued — General Construction
Q00533525-I1-GC
06/30/2022
Permit issued — General Construction
Q00533525-I1-GC
06/22/2022
Permit issued — Sprinklers
Q00536205-I1-EW-SP
06/21/2022
Permit issued — Plumbing
Q00536205-I1-PL
08/11/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
SAMI HAJJAR P.E
07/27/2021
Objection raised — Scope
07/27/2021
Objection resolved — Addressed
07/16/2021
Objection raised — Mechanical
07/16/2021
Objection resolved — Addressed
07/15/2021
Objection raised — Mechanical
07/15/2021
Objection resolved — Addressed
07/15/2021
Objection raised — Structural
07/15/2021
Objection resolved — Addressed
07/15/2021
Objection raised — Admin
07/15/2021
Objection resolved — Addressed
07/15/2021
Objection raised — Structural
07/15/2021
Objection resolved — Addressed
07/15/2021
Objection raised — Structural
07/15/2021
Objection resolved — Addressed
07/15/2021
Objection raised — Scope
07/15/2021
Objection resolved — Addressed
07/15/2021
Objection raised — Structural
07/15/2021
Objection resolved — Addressed
07/01/2021
Filed — Alteration
FILING FOR THE FOLLOWING: PLUMBING - INSTALLATION OF NEW DOMESTIC WATERPIPING, VALVES AND BACKFLOW PREVENTIONDEVICE. SPRINKLER - INSTALLATION OF NEW SPRINKLER PIPING,SPRINKLERS AND COORDINATION WITH ASSOCIATED FIRE ALARM WIRING, CONTROLS,ETC.
Q00536205-I1
06/27/2021
Filed — Alteration
Construction of new sprinkler soffit. Converting 3 family building into dormitory.
Q00533525-I1
06/03/2021
Special inspection requirement — Final
SAMI HAJJAR P.E
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSprinklersSigned-offDEMAR PLUMBING CORP06/20/2023
DOB NOWGeneral ConstructionPermit IssuedJGM CONSTRUCTION DEVELOPM07/01/2022
DOB NOWGeneral ConstructionPermit IssuedJGM CONSTRUCTION DEVELOPM07/01/2022
DOB NOWGeneral ConstructionPermit IssuedJGM CONSTRUCTION DEVELOPM07/01/2022
DOB NOWGeneral ConstructionPermit IssuedJGM CONSTRUCTION DEVELOPM07/01/2022
DOB NOWGeneral ConstructionPermit IssuedJGM CONSTRUCTION DEVELOPM06/30/2022
DOB NOWSprinklersSigned-offDEMAR PLUMBING CORP06/22/2022
DOB NOWPlumbingSigned-offDEMAR MECHANICAL INC06/21/2022
BISMHISSUEDA & E QUALITY CONSTRUCTION08/27/2009
BISEQISSUEDA & E QUALITY CONSTRUCTION04/30/2009
BIS—ISSUEDA & E QUALITY CONSTRUCTION10/31/2008
BISPLISSUED24 SEVEN PLUMBING INC07/22/2008
BIS—ISSUEDA & E QUALITY CONSTRUCTION06/19/2008
BISEQISSUEDA & E QUALITY CONSTRUCTION06/19/2008
BISEQISSUEDA & E QUALITY CONSTRUCTION06/05/2008
1 project · most recent 03/11/2024
FiledStatusContractorScope
03/11/2024Signed-offDEMAR PLUMBING CORP29 heads
1 project · most recent 03/11/2024
Plumbing-Sprinkler
FiledStatusContractorScope
03/11/2024Signed-offDEMAR MECHANICAL INCPlumbing-Sprinkler
▾Field Inspections (DOB CAP) — 6
DateTypeResultReport
09/04/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
05/23/2024Pass-Final PL - UndergroundPassView ↗
05/07/2024Pass-Final SP - Up to 3 Requested FloorsPassView ↗
10/11/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
08/02/2023Pass-Final SP - Up to 3 Requested FloorsPassView ↗
08/03/2022Pass-Final PL - UndergroundPassView ↗
▾Special Inspection Requirements (DOB NOW) — 4
DateRequirementInspectorRole
03/19/2024Sprinkler SystemsSAMI HAJJAR P.Especial
02/26/2024Sprinkler SystemsSAMI HAJJAR P.Especial
08/11/2021Fire-Resistant Penetrations and JointsSAMI HAJJAR P.Especial
06/03/2021FinalSAMI HAJJAR P.Eprogress
▾Documents — 68 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/23/2026Q00536205-P2Request digital key ↗
08/23/2026Q00536205-P1Request digital key ↗
08/23/2026Q00536205-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸Applications & Permits8
▸BISPLAN / WORK APPROVAL APPLICATION5
08/09/2018421653856Open ↗
07/10/2018421653856Open ↗
08/19/2009420067340Open ↗
Showing 3 of 5 on file for this type
▸BISWORK PERMIT APPLICATION2
08/27/2009420067340Open ↗
06/05/2008410117467Open ↗
▸BISNon-Directive 14 Construction Sign Off Including Sign Applications1
12/16/2009420067340Open ↗
▸Seals & Professional Certifications15
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/27/2026Q00533525-I1Open ↗
08/23/2026Q00536205-P1Open ↗
08/23/2026Q00536205-I1Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION3
12/16/2009420067340Open ↗
08/27/2009420067340Open ↗
04/18/2008410101170Open ↗
▸DOB NOWSpecial Inspector Seal & Signature3
09/18/2026Q00536205-P2Open ↗
08/28/2026Q00533525-I1Open ↗
08/26/2026Q00536205-I1Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST2
08/19/2009420067340Open ↗
05/30/2008410117467Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM2
08/19/2009420067340Open ↗
05/30/2008410117467Open ↗
▸DOB NOWProgress Inspector Seal & Signature1
08/28/2026Q00533525-I1Open ↗
▸Trade Schedules & Equipment18
▸BISEQUIPMENT USE PERMITS16
12/16/2009420067340Open ↗
12/16/2009420067340Open ↗
12/16/2009420067340Open ↗
Showing 3 of 16 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT2
12/16/2009420067340Open ↗
12/16/2009420067340Open ↗
▸Safety & Tenant Protection2
▸BISSTREET TREE CHECKLIST2
08/19/2009420067340Open ↗
05/30/2008410117467Open ↗
▸Environmental & Asbestos3
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER3
08/19/2009420067340Open ↗
05/30/2008410117467Open ↗
04/18/2008410101170Open ↗
▸Approvals, Objections & Sign-offs9
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter4
08/13/2026Q00536205-P2Open ↗
08/13/2026Q00536205-P1Open ↗
08/13/2026Q00533525-I1Open ↗
Showing 3 of 4 on file for this type
▸BISADMINISTRATIVE OBJECTIONS3
08/19/2009420067340Open ↗
05/30/2008410117467Open ↗
04/18/2008410101170Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST2
12/16/2009420067340Open ↗
11/16/2009410117467Open ↗
▸Cost, Insurance & Ownership4
▸BISCOST AFFIDAVIT4
07/10/2018421653856Open ↗
12/16/2009420067340Open ↗
08/19/2009420067340Open ↗
Showing 3 of 4 on file for this type
▸Filing & Intake Forms5
▸BISEFILING COVER SHEET4
07/10/2018421653856Open ↗
08/19/2009420067340Open ↗
05/30/2008410117467Open ↗
Showing 3 of 4 on file for this type
▸BISADDITIONAL INFORMATION1
04/18/2008410101170Open ↗