| Owner | Filings | Most Recent |
|---|---|---|
| BLDG MANAGEMENT CO., INC. | 98 | 07/08/2026 |
| 153-01 JAMAICA REALTY LLC IG S | 10 | 03/21/2026 |
| 153-01 JAMAICA AVENUE | 9 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| JEON CONSULTING | 1 | 03/10/2025 |
| YOUN DESIGN CORP. | 1 | 02/23/2025 |
| RAMIREZ ENGINEERING PLLC | 2 | 11/26/2024 |
| BAILEYS ENGINEERING PC | 1 | 10/17/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| HR EXPEDITING AND CONSULTING CORP | 4 | 03/21/2026 |
| AE DESIGN SOLUTION | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| NEPTUNE SIGNS AWNINGS | Scaffold | 2 | 07/08/2026 |
| FARELLA MICHAEL | Electrical | 1 | 03/21/2026 |
| HOWARD ZAMKOFF | Electrical | 1 | 03/21/2026 |
| DM ELECTRICAL CORPORATION | Electrical | 1 | 03/22/2026 |
| GLOBAL LUXURY SRVCS INC | General Contractor | 1 | 04/09/2026 |
| IPS PLUMBING CORP | Plumbing | 1 | 07/08/2026 |
| MICHAEL FARELLA | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| RAMIREZ ENGINEERING PLLC | 8679 | 1 | 11/26/2024 |
| BAILEYS ENGINEERING PC | 1970 | 1 | 10/17/2019 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sign | Signed-off | NEPTUNE SIGNS&AWNINGS INC | 04/29/2025 |
| DOB NOW | Sign | Signed-off | NEPTUNE SIGNS&AWNINGS INC | 02/26/2025 |
| DOB NOW | General Construction | Permit Issued | GLOBAL LUXURY SRVCS | 12/20/2024 |
| DOB NOW | Plumbing | Signed-off | IPS PLUMBING CORP | 12/02/2024 |
| BIS | OT | ISSUED | THE SCI CONSTRUCTION | 09/23/2020 |
| BIS | PL | ISSUED | WATER WORKS MECH LTD | 01/21/2016 |
| BIS | OT | ISSUED | HI TECH CONSTRUCTION & * | 01/19/2016 |
| BIS | OT | ISSUED | INTERIOR BUILDING SERVICE | 10/05/2009 |
| BIS | PL | ISSUED | JFR CONSTRUCTION CORP | 07/29/2009 |
| BIS | MH | ISSUED | INTERIOR BUILDING SERVICE | 06/16/2009 |
| BIS | OT | ISSUED | INTERIOR BUILDING SERVICE | 03/26/2009 |
| BIS | MH | ISSUED | INTERIOR BUILDING SERVICE | 03/26/2009 |
| BIS | OT | ISSUED | IBS INTERIORS LLC | 08/05/2008 |
| BIS | MH | ISSUED | IBS INTERIORS LLC | 08/05/2008 |
| BIS | PL | ISSUED | MARATHON MECHANICAL LLC | 03/19/2007 |
| BIS | OT | ISSUED | IBS INTERIORS, LLC | 03/12/2007 |
| BIS | — | ISSUED | NEW YORK SIGN CONTRACTOR | 02/21/2007 |
| BIS | SP | ISSUED | C.R.U. MECHAN & HEATIN IN | 02/12/2007 |
| BIS | PL | ISSUED | DPH PLUMBING & HTG CORP | 01/16/2007 |
| BIS | PL | ISSUED | C.R.U. MECHAN & HEAT INC | 01/08/2007 |
| BIS | OT | ISSUED | IBS INTERIORS,LLC | 12/07/2006 |
| BIS | OT | ISSUED | IBS INSTEIORS, LLC | 12/06/2006 |
| BIS | SP | ISSUED | ACCURATE MECHANICAL INC | 11/27/2006 |
| BIS | OT | ISSUED | PINNACLE CONTRACTORS OF NY INC | 11/14/2006 |
| BIS | OT | ISSUED | PINNACLE CONTRACTORS OF NY INC | 11/14/2006 |
| BIS | OT | ISSUED | IBS INSTEIORS, LLC | 08/14/2006 |
| BIS | PL | ISSUED | C2 PLUMBING LLC | 06/15/2006 |
| BIS | PL | ISSUED | C2 PLUMBING LLC | 06/07/2006 |
| BIS | OT | ISSUED | PINNACLE INTERIORS INC | 05/26/2006 |
| BIS | OT | ISSUED | PINNACLE INTERIORS INC | 05/26/2006 |
| BIS | BL | ISSUED | NEW YORK STANDARD MECH CORP | 11/10/2004 |
| BIS | SP | ISSUED | CAPITOL FIRE SPKL CO,INC | 10/21/2004 |
| BIS | PL | ISSUED | NEW YORK STANDARD MECH CORP | 07/23/2004 |
| BIS | EQ | ISSUED | SPRING SCAFFOLDING | 07/06/2004 |
| BIS | EQ | ISSUED | AMBROSINO CONST CORP | 06/30/2004 |
| BIS | EQ | ISSUED | SPRING SCAFFOLDING | 03/17/2004 |
| BIS | EQ | ISSUED | AMBROSINO CONST CORP | 01/08/2004 |
| BIS | EQ | ISSUED | SPRING SCAFFOLDING | 09/05/2003 |
| BIS | EQ | ISSUED | AMBROSINO CONST CORP | 07/31/2003 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 10/17/2019 | — | — | Air Conditioning Systems | Cooling Lg EM_S2 65,000 BTU · Condensing Unit ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/24/2025 | Complete | DM ELECTRICAL CORPORATION | General Wiring |
| 04/15/2025 | Complete | ASKO ELEC CONST & MAIN IN | — |
| 01/11/2025 | Complete | JONG HYUN KIM | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/25/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/18/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/04/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/13/2025 | Pass-Final Sign Permit Inspection | Pass | View ↗ |
| 02/20/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/05/2025 | Final | BENJAMIN JEON | progress |
| 11/09/2024 | Mechanical Systems | Amauris Ramirez | special |
| 11/09/2024 | Final | RONALD VILLANO | progress |