| Owner | Filings | Most Recent |
|---|---|---|
| Hubb NYC Properties | 69 | 07/08/2026 |
| 153 East 26th Street | 12 | 03/22/2026 |
| AD Realty Estate Investors | 8 | 03/21/2026 |
| Ldgllc | 6 | 03/21/2026 |
| 153 East 26th Hubb NYC | 4 | 03/22/2026 |
| Rod Aroy 153 | 2 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 10/07/2016 | $11.8M | — | 153 E. 26TH ST., LLC → 153 E 26TH ST HUBB NYC LLC | $747/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| Sullivan | 2 | 11/04/2024 |
| Bazini Engineering | 2 | 10/17/2023 |
| Altagracia Esther Martinez, R.A | 1 | 05/16/2023 |
| Azsk Architects | 11 | 10/21/2022 |
| Enthink Engineers | 1 | 06/29/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| Building Violation Solutions | 22 | 03/21/2026 |
| Municipal Building Consultants | 2 | 03/21/2026 |
| Rimkus New York | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Tri Contracting | General Contractor | 14 | 07/08/2026 |
| New Age Painting & Dec | specialty_contractor | 9 | 03/21/2026 |
| Andamio Scaffolding | Scaffold | 7 | 07/08/2026 |
| RVM Plumbing | Plumbing | 6 | 07/08/2026 |
| Canido Basonas Construction | Scaffold | 6 | 03/21/2026 |
| Dennison Electric | Electrical | 3 | 03/22/2026 |
| Canido Basonas Construction Service | General Contractor | 2 | 07/08/2026 |
| A Electrical Main Service | Electrical | 2 | 03/22/2026 |
| Highland Plumbing | Plumbing | 2 | 07/08/2026 |
| Orbit Plumbing & Heating | Plumbing | 2 | 07/08/2026 |
| Canido Basonas Construction Service | Scaffold | 1 | 07/08/2026 |
| Applied Electric | Electrical | 1 | 03/21/2026 |
| A Electrical Main Service | Electrical | 1 | 03/21/2026 |
| Approved Electric | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Outsource Special Inspection | 2827 | 2 | 11/04/2024 |
| Rimkus New York | 8123 | 2 | 11/04/2024 |
| Bazini Engineering | 1808 | 2 | 10/17/2023 |
| AK Engineering | 678 | 10 | 10/21/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Boiler Equipment | Signed-off | RVM Plumbing | 06/11/2025 |
| DOB NOW | Plumbing | Permit Issued | RVM Plumbing | 06/11/2025 |
| DOB NOW | Boiler Equipment | Signed-off | RVM Plumbing | 11/07/2024 |
| DOB NOW | Plumbing | Permit Issued | RVM Plumbing | 11/06/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | Andamio Scaffolding | 06/20/2024 |
| DOB NOW | Supported Scaffold | Permit Issued | Canido Basonas Construction Service | 05/24/2024 |
| DOB NOW | Supported Scaffold | Permit Issued | Canido Basonas Construction | 04/17/2024 |
| DOB NOW | Suspended Scaffold | Signed-off | Canido Basonas Construction | 12/21/2023 |
| DOB NOW | General Construction | Signed-off | Canido Basonas Construction Service | 11/30/2023 |
| DOB NOW | Boiler Equipment | Signed-off | RVM Plumbing | 10/25/2023 |
| DOB NOW | Plumbing | Permit Issued | RVM Plumbing | 10/25/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | Andamio Scaffolding | 06/21/2023 |
| DOB NOW | Supported Scaffold | Permit Issued | Canido Basonas Construction | 05/17/2023 |
| DOB NOW | General Construction | Signed-off | Canido Basonas Construction Service | 05/17/2023 |
| DOB NOW | Structural | Signed-off | Tri Contracting | 02/11/2023 |
| DOB NOW | Structural | Signed-off | Tri Contracting | 02/10/2023 |
| DOB NOW | Mechanical Systems | Signed-off | Tri Contracting | 02/10/2023 |
| DOB NOW | Mechanical Systems | Signed-off | Tri Contracting | 11/29/2022 |
| DOB NOW | Mechanical Systems | Signed-off | New Age Painting & Dec | 11/29/2022 |
| DOB NOW | Plumbing | Signed-off | Orbit Plumbing & Heating | 08/15/2022 |
| DOB NOW | Plumbing | Signed-off | Orbit Plumbing & Heating | 08/15/2022 |
| DOB NOW | General Construction | Signed-off | Tri Contracting | 07/18/2022 |
| DOB NOW | Mechanical Systems | Signed-off | Tri Contracting | 07/18/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | Andamio Scaffolding | 06/29/2022 |
| DOB NOW | Plumbing | Signed-off | Highland Plumbing | 04/13/2022 |
| DOB NOW | Plumbing | Signed-off | Highland Plumbing | 03/21/2022 |
| DOB NOW | Mechanical Systems | Signed-off | New Age Painting & Dec | 03/05/2022 |
| DOB NOW | Structural | Signed-off | New Age Painting & Dec | 03/04/2022 |
| BIS | MH | ISSUED | Trident Restoration | 06/06/2019 |
| BIS | OT | ISSUED | Trident Restoration | 06/05/2019 |
| BIS | PL | ISSUED | Orbit Plumbing & Heating | 05/08/2019 |
| BIS | OT | ISSUED | Trident Restoration | 05/02/2019 |
| BIS | OT | ISSUED | Trident Restoration | 12/19/2018 |
| BIS | MH | ISSUED | Trident Restoration | 12/19/2018 |
| BIS | MH | ISSUED | Trident Restoration | 12/19/2018 |
| BIS | PL | ISSUED | Orbit Plumbing & Heating | 09/19/2018 |
| BIS | OT | ISSUED | Trident Restoration | 09/13/2018 |
| BIS | PL | ISSUED | Orbit Plumbing & Heating | 06/21/2018 |
| BIS | OT | ISSUED | Trident Restoration | 05/29/2018 |
| BIS | PL | ISSUED | Orbit Plumbing & Heating | 04/19/2018 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/17/2023 | Signed-off | RVM Plumbing | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/09/2023 | Permit Issued | A Electrical Main Service | 12 meters, 1 new_meters |
| 09/21/2022 | Complete | Dennison Electric | General Wiring |
| 09/21/2022 | Complete | Dennison Electric | General Wiring |
| 08/17/2022 | Complete | Centennial Elevator Industries | General Wiring |
| 06/28/2022 | Complete | Borowide Elect'l Contractors | — |
| 03/27/2022 | Permit Issued | Supreme Electric | General Wiring |
| 11/15/2019 | Complete | Dennison Electric | General Wiring |
| 09/10/2019 | Complete | Dennison Electric | General Wiring |
| 09/24/2018 | Permit Issued | Dennison Electric | General Wiring |
| 07/16/2018 | Complete | RNW Electric | 16 meters, 1 new_meters |
| 06/18/2018 | Permit Issued | Dennison Electric | General Wiring |
| 05/01/2018 | Permit Issued | Dennison Electric | General Wiring |
| 01/22/2018 | Permit Issued | RNW Electric | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/16/2023 | Permit Issued | Canido Basonas Construction Service | Scaffold |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/07/2025 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |
| 09/30/2022 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 09/16/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/26/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/22/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/17/2023 | Fire-Resistant Penetrations and Joints | Joseph Bazini | special |
| 10/17/2023 | HVAC-R and service water heating equipment | Joseph Bazini | energy_progress |
| 10/05/2023 | Tenant Protection Plan Compliance | Joseph Bazini | special |
| 10/05/2023 | Tenant Protection Plan Compliance | Joseph Bazini | special |
| 09/26/2023 | Structural Stability – Alterations of existing buildings | WILLIAM DAVIS | special |
| 09/26/2023 | Tenant Protection Plan Compliance | JONAR MADRIAGA | special |
| 09/26/2023 | Post-installed Anchors | WILLIAM DAVIS | special |
| 09/26/2023 | Masonry | WILLIAM DAVIS | special |
| 09/26/2023 | Final | WILLIAM DAVIS | progress |
| 10/11/2022 | HVAC-R and service water heating system controls | Ari Kamo | energy_progress |
| 10/11/2022 | HVAC-R and service water heating equipment | Ari Kamo | energy_progress |
| 10/11/2022 | Final | Ari Kamo | progress |
| 10/11/2022 | Energy Code Compliance Inspections | Ari Kamo | progress |
| 10/11/2022 | Mechanical Systems | Ari Kamo | special |
| 10/11/2022 | HVAC-R and service water piping design and insulation | Ari Kamo | energy_progress |
| 08/19/2022 | Fire-Resistant Penetrations and Joints | Ari Kamo | special |
| 08/19/2022 | Structural Steel - Details | Ari Kamo | special |
| 08/19/2022 | Fire-Resistant Penetrations and Joints | Ari Kamo | special |
| 08/19/2022 | Structural Stability – Alterations of existing buildings | Ari Kamo | special |
| 08/19/2022 | Fire-Resistance Rated Construction | Ari Kamo | progress |
| 08/19/2022 | Final | Ari Kamo | progress |
| 08/19/2022 | Energy Code Compliance Inspections | Ari Kamo | progress |
| 08/18/2022 | Energy Code Compliance Inspections | Ari Kamo | progress |
| 08/18/2022 | Fire-Resistant Penetrations and Joints | Ari Kamo | special |
| 08/18/2022 | Fire-Resistance Rated Construction | Ari Kamo | progress |