← Back
Three families
1531 MCDONALD STREET
BRONX · Morris Park · BIN 2047101
💬 Discuss this project
1925Year Built
2.75Stories
C0Building Class
R4Zoning
3,035 sfGross Floor Area
3Units
Three families · Owner of record: 1531 MCD CORP. · 2,500 sf lot · 1.21 FAR built · Flood zone X
Locations of Work
ArchitectureElectrical
Roof1 filing · 7 docs
Floor 23p · 1 filing · 4 docs
Floor 11p · 1 filing · 4 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
1531 MCD CORP.103/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MOMENTUM SOLAR110/16/2024
BILLAH ENGINEERING PLLC110/25/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
INSHA BUILDING CONSULTANTS203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
RECORD 13 CONSTRUCTION COGeneral Contractor303/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MXV SIA LLC9281110/16/2024
BILLAH ENGINEERING5838110/25/2021
Building Lifecycle
All (11)Filed (2)Permit Issued (3)Signed Off (1)Special Inspection (5)
04/29/2026
Permit issued — Solar
X01122734-I1-SL
10/21/2024
Permit issued — Solar
X01122734-I1-SL
10/16/2024
Filed — Alteration
Installation of solar panels; Rooftop, Railed, Grid tied, 9 Panels, 3.69 kW
X01122734-I1
10/07/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
10/07/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mina Makar
10/07/2024
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
10/07/2024
Special inspection requirement — Final
Mina Makar
10/07/2024
Special inspection requirement — Air barrier - visual inspection
Mina Makar
07/01/2022
Signed off — Alteration
X00612148-I1
11/04/2021
Permit issued — General Construction
X00612148-I1-GC
10/25/2021
Filed — Alteration
X00612148-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarPermit IssuedMOMENTUM SOLAR04/29/2026
DOB NOWSolarPermit IssuedMOMENTUM SOLAR10/21/2024
DOB NOWGeneral ConstructionSigned-offRECORD 13 CONSTRUCTION CO11/04/2021
2 projects · most recent 10/07/2024
General Wiring
FiledStatusContractorScope
10/07/2024Permit IssuedISLAND ELECTRIC CORP—
10/31/2021Permit IssuedBLZ ELECTRIC INC.General Wiring
1 project · most recent 10/16/2024
FiledStatusContractorScope
10/16/2024Permit IssuedMOMENTUM SOLAR9 panels, 3.69 kw, 159 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
10/07/2024Fire-Resistant Penetrations and JointsMina Makarspecial
10/07/2024Structural Stability – Alterations of existing buildingsMina Makarspecial
10/07/2024Energy Code Compliance InspectionsMina Makarprogress
10/07/2024FinalMina Makarprogress
10/07/2024Air barrier - visual inspectionMina Makarenergy_progress
▾Documents — 11 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/25/2026X00612148-I1Request digital key ↗
08/20/2026X01122734-I1Request digital key ↗
▸Seals & Professional Certifications5
▸DOB NOWProgress Inspector Seal & Signature2
08/26/2026X01122734-I1Open ↗
08/26/2026X01122734-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/25/2026X00612148-I1Open ↗
08/13/2026X01122734-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/26/2026X01122734-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/25/2026X00612148-I1Open ↗
08/13/2026X01122734-I1Open ↗
▸Energy Compliance1
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026X00612148-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026X01122734-I1Open ↗