| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 04/08/2022 | $1.1M | — | Private party → Private party | $305/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| MEI ARCHITECT PLLC | 4 | 10/07/2024 |
| MEHDI GHAZI, P.E., P.C. | 3 | 07/15/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| ALPHA HOME DESIGN LLC | 4 | 03/21/2026 |
| IBUILD CONSULTING | 10 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| NEW HENGDA CONSTRUCTION | General Contractor | 9 | 07/08/2026 |
| PRIMROSE SERVICE INC | General Contractor | 6 | 03/21/2026 |
| ROCK E SMALL PLBG&HTG INC | Plumbing | 2 | 07/08/2026 |
| L&L CONSTRUCTION DEVELOP | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| MEHDI GHAZI, P.E. P.C. | 7129 | 5 | 10/07/2024 |
| SD TESTING & INSPECTION S | 7010 | 2 | 07/15/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | L&L CONSTRUCTION DEVELOP | 11/04/2024 |
| DOB NOW | General Construction | Permit Issued | PRIMROSE SERVICE INC | 03/08/2024 |
| DOB NOW | Construction Fence | Signed-off | PRIMROSE SERVICE INC | 03/07/2024 |
| DOB NOW | General Construction | Permit Issued | NEW HENGDA CONSTRUCTION | 09/08/2023 |
| DOB NOW | Plumbing | Signed-off | ROCK E SMALL PLBG&HTG INC | 08/17/2023 |
| DOB NOW | Construction Fence | Signed-off | NEW HENGDA CONSTRUCTION | 07/07/2023 |
| DOB NOW | Plumbing | Signed-off | ROCK E SMALL PLBG&HTG INC | 11/09/2022 |
| DOB NOW | General Construction | Permit Issued | NEW HENGDA CONSTRUCTION | 09/16/2022 |
| DOB NOW | Structural | Signed-off | NEW HENGDA CONSTRUCTION | 09/12/2022 |
| DOB NOW | Construction Fence | Signed-off | NEW HENGDA CONSTRUCTION | 07/13/2022 |
| BIS | — | ISSUED | NEW HENGDA CONSTRUCTION | 08/24/2022 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 10/07/2024 | Permit Issued | PRIMROSE SERVICE INC | Heating Systems | Heating Williamson GWA-233 233,000 BTU · Boiler ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/30/2024 | Complete | CL ELECTRICAL CORP | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/07/2024 | Permit Issued | PRIMROSE SERVICE INC | Steel, Masonry, Wood |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/07/2024 | Permit Issued | PRIMROSE SERVICE INC | Earthwork |
| Date | Type | Result | Report |
|---|---|---|---|
| 11/13/2024 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 11/04/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/25/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/07/2023 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 11/23/2022 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 11/23/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/23/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/25/2024 | Insulation placement and R values | MEHDI GHAZI | energy_progress |
| 10/25/2024 | Air barrier - visual inspection | MEHDI GHAZI | energy_progress |
| 10/25/2024 | HVAC-R and service water heating system controls | MEHDI GHAZI | energy_progress |
| 10/25/2024 | Metering | MEHDI GHAZI | energy_progress |
| 10/25/2024 | Interior lighting power | MEHDI GHAZI | energy_progress |
| 10/25/2024 | Energy Code Compliance Inspections | MEHDI GHAZI | progress |
| 10/25/2024 | HVAC-R and service water heating equipment | MEHDI GHAZI | energy_progress |
| 10/25/2024 | Air barrier — testing | MEHDI GHAZI | energy_progress |
| 10/25/2024 | Maintenance information | MEHDI GHAZI | energy_progress |
| 10/25/2024 | Protection of exposed foundation insulation | MEHDI GHAZI | energy_progress |
| 10/25/2024 | Fenestration air leakage | MEHDI GHAZI | energy_progress |
| 10/25/2024 | Electric vehicle service equipment requirements | MEHDI GHAZI | energy_progress |
| 10/25/2024 | Fenestration and door U-factor and product ratings | MEHDI GHAZI | energy_progress |
| 10/25/2024 | Final | MEHDI GHAZI | progress |
| 10/25/2024 | Fire-Resistance Rated Construction | MEHDI GHAZI | progress |
| 10/25/2024 | Ventilation and air distribution system | MEHDI GHAZI | energy_progress |
| 10/25/2024 | Fenestration areas | MEHDI GHAZI | energy_progress |
| 10/25/2024 | Permanent certificate | MEHDI GHAZI | energy_progress |
| 10/25/2024 | Duct leakage testing, insulation and design | MEHDI GHAZI | energy_progress |
| 10/25/2024 | HVAC-R and service water piping design and insulation | MEHDI GHAZI | energy_progress |
| 10/25/2024 | Fire-Resistant Penetrations and Joints | MEHDI GHAZI | special |
| 10/25/2024 | Heating Systems | MEHDI GHAZI | special |
| 10/25/2024 | Chimneys and vents | MEHDI GHAZI | special |
| 10/25/2024 | Subsurface Investigations (Borings/Test Pits) | XIUCHENG LI | special |
| 10/25/2024 | Mechanical Systems | MEHDI GHAZI | special |