| Owner | Filings | Most Recent |
|---|---|---|
| UNITED DEVELOPERS | 16 | 07/08/2026 |
| ROCK DVLP CORP | 2 | 03/22/2026 |
| ARVERNE BEACH PROPERTIES | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 04/22/2024 | $824K | — | 69-49 DECOSTA AVE LLC → Private party | $421/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| PIROOZ ENGINEERING, P.C. | 4 | 04/22/2023 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| J&J DESIGNS INC | General Contractor | 7 | 07/08/2026 |
| SKY ELECTRIC LLC | Electrical | 1 | 03/22/2026 |
| INFINITI ESC PLUMBING COR | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| BUTTERFIELD & O'CONNOR | 4189 | 1 | 04/21/2023 |
| IP CONCRETE TESTING AND I | 6252 | 1 | 04/21/2023 |
| PIROOZ ENGINEERING P.C | 7177 | 1 | 08/26/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | J&J DESIGNS INC | 05/03/2023 |
| DOB NOW | Plumbing | Signed-off | INFINITI ESC PLUMBING COR | 04/27/2023 |
| DOB NOW | Earth Work | Permit Issued | J&J DESIGNS INC | 03/15/2023 |
| DOB NOW | Construction Fence | Signed-off | J&J DESIGNS INC | 03/08/2023 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/03/2023 | Complete | SKY ELECTRIC LLC | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 12/04/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 12/04/2023 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 10/20/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 10/13/2023 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 06/02/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/03/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 05/03/2023 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 05/03/2023 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 05/03/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/03/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/21/2023 | Fire-Resistant Penetrations and Joints | BRIAN T. O'CONNOR | special |
| 04/21/2023 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | BRIAN T. O'CONNOR | special |
| 04/21/2023 | Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities | INDARDEO PARBHUNATH | special |
| 04/21/2023 | Sprinkler Systems | BRIAN T. O'CONNOR | special |
| 09/29/2022 | Electric vehicle service equipment requirements | PIROOZ SOLTANIZADEH | energy_progress |
| 09/20/2022 | Interior lighting power | PIROOZ SOLTANIZADEH | energy_progress |
| 09/20/2022 | Ventilation and air distribution system | PIROOZ SOLTANIZADEH | energy_progress |
| 09/20/2022 | Duct leakage testing, insulation and design | PIROOZ SOLTANIZADEH | energy_progress |
| 08/25/2022 | Subsurface Investigations (Borings/Test Pits) | INDARDEO PARBHUNATH | special |
| 08/25/2022 | Fire-Resistant Penetrations and Joints | PIROOZ SOLTANIZADEH | special |
| 02/25/2022 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | PIROOZ SOLTANIZADEH | special |
| 02/25/2022 | Subgrade Inspections | PIROOZ SOLTANIZADEH | special |
| 02/25/2022 | Final | JAN PEREZ | progress |
| 02/25/2022 | Footing and Foundation | PIROOZ SOLTANIZADEH | progress |
| 02/25/2022 | Energy Code Compliance Inspections | PIROOZ SOLTANIZADEH | progress |
| 02/25/2022 | Fire-Resistance Rated Construction | PIROOZ SOLTANIZADEH | progress |
| 02/25/2022 | Lowest Floor Elevation | PIROOZ SOLTANIZADEH | progress |
| 02/25/2022 | Preliminary | PIROOZ SOLTANIZADEH | progress |
| 02/25/2022 | Structural Wood Frame | PIROOZ SOLTANIZADEH | progress |
| 02/25/2022 | Insulation placement and R values | PIROOZ SOLTANIZADEH | energy_progress |
| 02/25/2022 | Fenestration areas | PIROOZ SOLTANIZADEH | energy_progress |
| 02/25/2022 | Maintenance information | PIROOZ SOLTANIZADEH | energy_progress |
| 02/25/2022 | Air barrier — testing | PIROOZ SOLTANIZADEH | energy_progress |
| 02/25/2022 | HVAC-R and service water heating equipment | PIROOZ SOLTANIZADEH | energy_progress |
| 02/25/2022 | Metering | PIROOZ SOLTANIZADEH | energy_progress |