| Owner | Filings | Most Recent |
|---|---|---|
| DAX REAL ESTATE | 8 | 07/08/2026 |
| 154 NORTH 9 ST | 2 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 12/10/2021 | $4.0M | — | THE NORTH NINTH STREET GROUP LLC → 154 NORTH 9TH OWNER LLC | $1,067/sf building |
| 08/25/2020 | $3.1M | — | 154 NORTH 9TH STREET LLC → THE NORTH NINTH STREET GROUP LLC | $827/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| KUSHNER STUDIOS | 3 | 07/25/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| KUSHNER STUDIOS | 3 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SENTER MANAGEMENT LLC | General Contractor | 7 | 07/08/2026 |
| AQUA PLUMBING & HTNG CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CROSSCHECK INSPECTION SER | 544 | 2 | 07/25/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | SENTER MANAGEMENT LLC | 09/14/2022 |
| DOB NOW | General Construction | Signed-off | SENTER MANAGEMENT LLC | 05/25/2022 |
| DOB NOW | Plumbing | Signed-off | AQUA PLUMBING & HTNG CORP | 04/27/2022 |
| DOB NOW | General Construction | Signed-off | SENTER MANAGEMENT LLC | 03/29/2022 |
| BIS | OT | ISSUED | MINNOW ASSOCIATES LLC | 08/01/2014 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/03/2022 | Complete | DENMAR ELECTRIC CORP | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/21/2022 | Energy Code Compliance Inspections | EUGENE BIFULCO | progress |
| 06/27/2022 | HVAC-R and service water heating system controls | EUGENE BIFULCO | energy_progress |
| 06/27/2022 | HVAC-R and service water piping design and insulation | EUGENE BIFULCO | energy_progress |
| 06/27/2022 | Fire-Resistant Penetrations and Joints | EUGENE BIFULCO | special |
| 06/27/2022 | HVAC-R and service water heating equipment | EUGENE BIFULCO | energy_progress |
| 06/27/2022 | Maintenance information | EUGENE BIFULCO | energy_progress |
| 06/09/2022 | Mechanical Systems | EUGENE BIFULCO | special |
| 06/09/2022 | Final | EUGENE BIFULCO | progress |
| 02/24/2022 | Fire-Resistant Penetrations and Joints | EUGENE BIFULCO | special |
| 02/01/2022 | Energy Code Compliance Inspections | EUGENE BIFULCO | progress |
| 02/01/2022 | Fire-Resistance Rated Construction | EUGENE BIFULCO | progress |
| 01/31/2022 | Lighting in dwelling units | EUGENE BIFULCO | energy_progress |
| 01/26/2022 | Final | EUGENE BIFULCO | progress |