| Owner | Filings | Most Recent |
|---|---|---|
| Consolidated Edison Company of New York | 36 | 09/13/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| McLaren Engineering Group | 2 | 08/27/2026 |
| LERA Consulting Structural Engineering | 4 | 07/14/2026 |
| Dyami Architecture | 1 | 10/03/2025 |
| Tectonic Engineering Consultants, G | 1 | 08/06/2025 |
| WB Engineers & Consultants | 5 | 07/14/2025 |
| Gensler | 1 | 07/14/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| Taccetta Consulting | 9 | 03/21/2026 |
| M G McLaren Engineering | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| On-Trac Construction Associates | General Contractor | 8 | 06/27/2026 |
| Sirina Fire Protection | Fire Protection | 2 | 07/08/2026 |
| Par Plumbing Co | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Tectonic Engineering Cons | 106 | 14 | 08/27/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Support of Excavation | Permit Issued | On-Trac Construction Associates | 03/10/2026 |
| DOB NOW | Support of Excavation | Permit Issued | On-Trac Construction Associates | 02/03/2026 |
| DOB NOW | Structural | Permit Issued | On-Trac Construction Associates | 01/28/2026 |
| DOB NOW | Foundation | Permit Issued | On-Trac Construction Associates | 01/28/2026 |
| DOB NOW | Plumbing | Permit Issued | Par Plumbing Co | 12/17/2025 |
| DOB NOW | Sprinklers | Permit Issued | Sirina Fire Protection | 12/16/2025 |
| DOB NOW | Sprinklers | Permit Issued | Sirina Fire Protection | 12/16/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | On-Trac Construction Associates | 11/19/2025 |
| DOB NOW | General Construction | Permit Issued | On-Trac Construction Associates | 11/18/2025 |
| DOB NOW | General Construction | Permit Issued | On-Trac Construction Associates | 10/20/2025 |
| DOB NOW | General Construction | Permit Issued | On-Trac Construction Associates | 10/16/2025 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 07/14/2026 | Permit Issued | On-Trac Construction Associates | Air Conditioning Systems, Heating Systems, Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/14/2026 | Permit Issued | Sirina Fire Protection | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/14/2026 | Permit Issued | Par Plumbing Co | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/14/2026 | Permit Issued | On-Trac Construction Associates | Steel, Concrete |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/27/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 05/29/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 05/12/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 05/12/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/20/2026 | Structural Cold-Formed Steel | — | special |
| 05/27/2026 | Final | GEORGE GHEBRYAL | progress |
| 05/27/2026 | Structural Steel - Welding | GEORGE GHEBRYAL | special |
| 05/27/2026 | Structural Steel - High Strength Bolting | GEORGE GHEBRYAL | special |
| 05/27/2026 | Structural Steel - Details | GEORGE GHEBRYAL | special |
| 05/27/2026 | Structural Stability – Alterations of existing buildings | GEORGE GHEBRYAL | special |
| 05/27/2026 | Post-installed Anchors | GEORGE GHEBRYAL | special |
| 05/27/2026 | Concrete - Cast-In-Place | GEORGE GHEBRYAL | special |
| 02/12/2026 | Concrete - Cast-In-Place | GEORGE GHEBRYAL | special |
| 02/12/2026 | Final | GEORGE GHEBRYAL | progress |
| 02/12/2026 | Masonry | GEORGE GHEBRYAL | special |
| 02/12/2026 | Structural Steel - Welding | GEORGE GHEBRYAL | special |
| 02/12/2026 | Structural Steel - High Strength Bolting | GEORGE GHEBRYAL | special |
| 02/12/2026 | Structural Steel - Details | GEORGE GHEBRYAL | special |
| 02/12/2026 | Structural Stability – Alterations of existing buildings | GEORGE GHEBRYAL | special |
| 02/12/2026 | Post-installed Anchors | GEORGE GHEBRYAL | special |
| 09/24/2025 | Subsurface Investigations (Borings/Test Pits) | MARK STIER | special |
| 08/15/2025 | Final | GEORGE GHEBRYAL | progress |
| 08/15/2025 | Structural Stability – Alterations of existing buildings | GEORGE GHEBRYAL | special |
| 08/15/2025 | Masonry | GEORGE GHEBRYAL | special |
| 08/15/2025 | Post-installed Anchors | GEORGE GHEBRYAL | special |
| 08/15/2025 | Structural Steel - Details | GEORGE GHEBRYAL | special |
| 08/15/2025 | Structural Steel - High Strength Bolting | GEORGE GHEBRYAL | special |
| 08/15/2025 | Structural Steel - Welding | GEORGE GHEBRYAL | special |
| 08/15/2025 | Concrete - Cast-In-Place | GEORGE GHEBRYAL | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Consolidated Edison | Office | Cellar, Floors 1, 2, Roof | Project Q01146588 |