| Owner | Filings | Most Recent |
|---|---|---|
| DWIP | 25 | 07/08/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 10/20/2025 | $1.1M | — | — → — | $727/sf building |
| 04/29/2021 | $635K | — | — → — | $439/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| JON PAUL DESIGN & CONSULTING | 3 | 11/24/2025 |
| ROHAN ENGINEERING, PC | 5 | 11/06/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| JON PAUL DESIGN & CONSULTING | 14 | 03/21/2026 |
| VRD DEVELOPMENT | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| DWIP CORP | General Contractor | 6 | 07/08/2026 |
| ARCO PLBG AND HTG INC | Plumbing | 2 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| AM ENGINEERING SERVICES P | 7975 | 4 | 11/24/2025 |
| VIBRANALYSIS INC., DBA VT | 6864 | 3 | 11/06/2025 |
| ASE ENGINEERING PLLC | 5785 | 1 | 04/04/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | ARCO PLBG AND HTG INC | 06/18/2025 |
| DOB NOW | Structural | Signed-off | DWIP CORP | 12/27/2024 |
| DOB NOW | General Construction | Signed-off | DWIP CORP | 06/07/2024 |
| DOB NOW | General Construction | Signed-off | DWIP CORP | 10/20/2023 |
| DOB NOW | Plumbing | Signed-off | ARCO PLBG AND HTG INC | 11/18/2022 |
| DOB NOW | Structural | Signed-off | DWIP CORP | 05/04/2022 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 11/24/2025 | Signed-off | DWIP CORP | Heating and Air Conditioning Systems | Heat / Cool Mitsubishi Electric MXZ-3C24NA3 30,600 BTU · Heat Pump Outdoor ×1 MXZ-4C36NA3 36,000 BTU · Heat Pump Outdoor ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/06/2025 | Signed-off | ARCO PLBG AND HTG INC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/14/2024 | Complete | DB ELECTRIC LLC | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/16/2026 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 10/10/2025 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 05/31/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/23/2022 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 12/23/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/23/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/16/2026 | Interior lighting power | Albert Munoz | energy_progress |
| 03/16/2026 | HVAC-R and service water heating system controls | Albert Munoz | energy_progress |
| 03/16/2026 | Air barrier - visual inspection | Albert Munoz | energy_progress |
| 03/16/2026 | HVAC-R and service water piping design and insulation | Albert Munoz | energy_progress |
| 03/16/2026 | Insulation placement and R values | Albert Munoz | energy_progress |
| 03/16/2026 | Lighting in dwelling units | Albert Munoz | energy_progress |
| 03/16/2026 | Heating Systems | Albert Munoz | special |
| 03/16/2026 | Structural Stability – Alterations of existing buildings | Albert Munoz | special |
| 03/16/2026 | Mechanical Systems | Albert Munoz | special |
| 03/16/2026 | Fire-Resistant Penetrations and Joints | Albert Munoz | special |
| 03/16/2026 | Energy Code Compliance Inspections | Albert Munoz | progress |
| 03/16/2026 | Final | Albert Munoz | progress |
| 03/16/2026 | Fire-Resistance Rated Construction | Albert Munoz | progress |
| 03/16/2026 | Fenestration air leakage | Albert Munoz | energy_progress |
| 03/16/2026 | Fenestration areas | Albert Munoz | energy_progress |
| 03/16/2026 | Fenestration and door U-factor and product ratings | Albert Munoz | energy_progress |
| 03/16/2026 | HVAC-R and service water heating equipment | Albert Munoz | energy_progress |
| 03/16/2026 | Permanent certificate | Albert Munoz | energy_progress |
| 04/14/2022 | Structural Stability – Alterations of existing buildings | Albert Munoz | special |
| 04/14/2022 | Subgrade Inspections | Albert Munoz | special |
| 04/14/2022 | Structural Wood Frame | Albert Munoz | progress |
| 04/14/2022 | Concrete - Cast-In-Place | Albert Munoz | special |
| 02/28/2022 | Final | Albert Munoz | progress |