| Owner | Filings | Most Recent |
|---|---|---|
| ROOBY HOLDINGS | 12 | 09/01/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| CB ENGINEERING PC | 1 | 03/20/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| BIS | OT | ISSUED | JBJ CONCRETE RENOVATIONS | 03/04/2024 |
| BIS | PL | ISSUED | COASTLINE PLUMBING & HTG | 01/11/2023 |
| BIS | OT | ISSUED | JABUS BUILDING CORP | 01/17/2017 |
| BIS | OT | ISSUED | JABUS BUILDING CORP | 11/15/2016 |
| BIS | BL | ISSUED | COASTLINE PLUMBING & HTG | 10/21/2016 |
| BIS | PL | ISSUED | COASTLINE PLUMBING & HTG | 10/21/2016 |
| BIS | OT | ISSUED | JABUS BUILDING CORP | 08/24/2016 |
| BIS | EQ | ISSUED | JABUS BUILDING CORP | 03/23/2015 |
| BIS | OT | ISSUED | JABUS BUILDING CORP | 03/23/2015 |
| BIS | OT | ISSUED | JABUS BUILDING CORP | 12/05/2013 |
| BIS | OT | RE-ISSUED | JABUS BUILDING CORP | 11/08/2013 |
| BIS | EQ | ISSUED | JABUS BUILDING CORP | 11/08/2013 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/20/2026 | Energy Code Compliance Inspections | — | progress |
| 03/20/2026 | Fire-Resistance Rated Construction | — | progress |
| 03/20/2026 | Fenestration air leakage | — | energy_progress |
| 03/20/2026 | Air barrier — testing | — | energy_progress |
| 03/20/2026 | Insulation placement and R values | — | energy_progress |
| 03/20/2026 | Air barrier - visual inspection | — | energy_progress |
| 03/20/2026 | Exterior lighting power | — | energy_progress |
| 03/20/2026 | Interior lighting power | — | energy_progress |
| 03/20/2026 | Fenestration and door U-factor and product ratings | — | energy_progress |
| 03/20/2026 | Maintenance information | — | energy_progress |
| 03/20/2026 | Fenestration areas | — | energy_progress |
| 03/20/2026 | Lighting controls | — | energy_progress |
| 03/20/2026 | Metering | — | energy_progress |
| 03/20/2026 | Lighting in dwelling units | — | energy_progress |