0Year Built
—Stories
V0Building Class
M1-2DZoning
0 sfGross Floor Area
0Units
Rent Stabilized4 Open Violations ▸
Zoned residential, not Manhattan · 2,075 sf lot · 0 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionCivil
Floor 313p · 1 filing · 20 docs
Floor 214p · 1 filing · 20 docs
Floor 111p · 1 filing · 20 docs
Cellar33p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
GUINEA PIG HOLDINGS2307/08/2026
N TECH DESIGN OF AMERICA403/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
09/19/2018$975K—— → —— not available
▾Design Consultants (Architect / Engineer of Record)
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
UGB CONSTRUCTION INCGeneral Contractor707/08/2026
ALPHA SCAFFOLDING INCGeneral Contractor607/08/2026
USMAN G. BHUTTAGeneral Contractor403/21/2026
RISEUP BUILDERS LLCGeneral Contractor303/21/2026
SERGIO GIANNACHIElectrical103/21/2026
RICHARD NEUElectrical103/21/2026
NEU, RICHARDElectrical103/21/2026
LELIS, ARILSONElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HRF SERVICES CORP5616611/29/2023
Building Lifecycle
All (72)Filed (9)Permit Issued (12)Violation (9)Inspection (5)Objection (8)Special Inspection (29)
05/07/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
04/10/2026
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
03/23/2026
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
12/31/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
12/30/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
12/04/2025
Permit issued — Supported Scaffold
B01146901-I1-SF
11/24/2025
Violation issued (HPD, open)
I
11/17/2025
Permit issued — Sidewalk Shed
B01146681-I1-SH
09/17/2025
Permit issued — Foundation
B00782534-S6-FO
09/17/2025
Permit issued — Support of Excavation
B00782534-S5-SE
05/28/2025
Permit issued — Foundation
B00782534-S6-FO
05/22/2025
Permit issued — Support of Excavation
B00782534-S5-SE
05/22/2025
Permit issued — Earth Work
B00782534-S2-GC-CX
05/21/2025
Permit issued — General Construction
B00782534-I1-GC-CX
04/29/2025
Permit issued — Construction Fence
B00816725-I1-FN
12/30/2024
Violation issued (ECB, closed)
Unknown
12/30/2024
Violation issued (ECB, closed)
Unknown
12/30/2024
Violation issued (ECB, closed)
Unknown
12/30/2024
Violation issued (ECB, closed)
Construction
12/04/2024
Violation issued (HPD, open)
I
12/03/2024
Filed — Alteration
PROPOSED INSTALLATION OF TEMPORARY LIGHT DUTY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
B01146901-I1
12/03/2024
Permit issued — Supported Scaffold
B01146901-I1-SF
11/26/2024
Filed — Alteration
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. LIVE LOAD 300PSF.
B01146681-I1
11/26/2024
Permit issued — Sidewalk Shed
B01146681-I1-SH
10/31/2024
Permit issued — Construction Fence
B00816725-I1-FN
12/29/2023
Objection resolved — Addressed
12/22/2023
Filed — Alteration
Install temporary Wood Construction Fence . No Change to egress, occupancy or use.
B00816725-I1
12/04/2023
Objection resolved — Addressed
12/01/2023
Objection raised — Other
11/29/2023
Filed — New Building
New Three (3) Story three family residence.
B00782534-S6
11/28/2023
Violation issued (HPD, open)
I
11/27/2023
Objection resolved — Addressed
11/14/2023
Special inspection requirement — Footing and Foundation
FAHAD FATEH
11/14/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
FAHAD FATEH
11/14/2023
Special inspection requirement — Final
FAHAD FATEH
11/14/2023
Special inspection requirement — Subsurface Conditions – Fill Placement & In-Place Density
FAHAD FATEH
11/14/2023
Special inspection requirement — Underpinning
FAHAD FATEH
11/14/2023
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
FERAS AYOUB
11/09/2023
Objection raised — Other
10/31/2023
Filed — New Building
New Three (3) Story three family residence.
B00782534-S2
10/25/2023
Objection resolved — Addressed
10/19/2023
Objection raised — Energy
10/11/2023
Filed — New Building
New Three (3) Story three family residence.
B00782534-S1
10/09/2023
Special inspection requirement — Duct leakage testing, insulation and design
FAHAD FATEH
10/05/2023
Objection raised — Other
10/03/2023
Filed — New Building
New Three (3) Story three family residence.
B00782534-S4
10/03/2023
Filed — New Building
New Three (3) Story three family residence.
B00782534-S5
09/28/2023
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
FAHAD FATEH
06/21/2023
Special inspection requirement — Sprinkler Systems
FAHAD FATEH
06/21/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
09/23/2022
Filed — New Building
New Three (3) Story three family residence.
B00782534-I1
08/04/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
08/04/2022
Special inspection requirement — Interior lighting power
FAHAD FATEH
08/04/2022
Special inspection requirement — Ventilation and air distribution system
FAHAD FATEH
08/04/2022
Special inspection requirement — Metering
FAHAD FATEH
08/04/2022
Special inspection requirement — Energy Code Compliance Inspections
FAHAD FATEH
08/04/2022
Special inspection requirement — Fire-Resistance Rated Construction
FAHAD FATEH
08/04/2022
Special inspection requirement — HVAC-R and service water piping design and insulation
FAHAD FATEH
08/04/2022
Special inspection requirement — Air barrier - visual inspection
FAHAD FATEH
08/04/2022
Special inspection requirement — Fenestration areas
FAHAD FATEH
Latest 60 of 72 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSupported ScaffoldPermit IssuedALPHA SCAFFOLDING INC12/04/2025
DOB NOWSidewalk ShedPermit IssuedALPHA SCAFFOLDING INC11/17/2025
DOB NOWFoundationPermit IssuedUGB CONSTRUCTION INC09/17/2025
DOB NOWSupport of ExcavationPermit IssuedUGB CONSTRUCTION INC09/17/2025
DOB NOWFoundationPermit IssuedUGB CONSTRUCTION INC05/28/2025
DOB NOWSupport of ExcavationPermit IssuedUGB CONSTRUCTION INC05/22/2025
DOB NOWEarth WorkPermit IssuedUGB CONSTRUCTION INC05/22/2025
DOB NOWGeneral ConstructionPermit IssuedUGB CONSTRUCTION INC05/21/2025
DOB NOWConstruction FencePermit IssuedUGB CONSTRUCTION INC04/29/2025
DOB NOWSupported ScaffoldPermit IssuedALPHA SCAFFOLDING INC12/03/2024
DOB NOWSidewalk ShedPermit IssuedALPHA SCAFFOLDING INC11/26/2024
DOB NOWConstruction FencePermit IssuedRISEUP BUILDERS LLC10/31/2024
BIS—ISSUEDN TECH DESIGN OF AMERICA12/06/2024
1 project · most recent 11/29/2023
Air Conditioning Systems Associated Ducts and Piping Heating Systems
FiledStatusContractorScopeMake / Model / Capacity
11/29/2023Permit IssuedUGB CONSTRUCTION INCAir Conditioning Systems, Associated Ducts and Piping, Heating Systems
Cooling
Mitsubishi Electric MXZ-3C30NA2 28,400 BTU · Split System ×3
MXZ-8C48NA 48,000 BTU · Split System ×1
Heating
Mitsubishi Electric MXZ-3C30NA2 28,600 BTU · Heat Pump Outdoor ×3
MXZ-8C48NA 54,000 BTU · Heat Pump Outdoor ×1
Ducts & Piping
N/A n/a ×1
1 project · most recent 11/29/2023
Storm Water/Sanitary
FiledStatusContractorScope
11/29/2023——Storm, Water/Sanitary
1 project · most recent 11/27/2024
FiledStatusContractorScope
11/27/2024Permit IssuedRICHARD NEU—
1 project · most recent 11/29/2023
Steel Concrete
FiledStatusContractorScope
11/29/2023Permit IssuedUGB CONSTRUCTION INCSteel, Concrete
3 projects · most recent 12/03/2024
Scaffold Sidewalk Shed Fence
FiledStatusContractorScope
12/03/2024Permit IssuedALPHA SCAFFOLDING INCScaffold
11/26/2024Permit IssuedALPHA SCAFFOLDING INCSidewalk Shed
12/22/2023Permit IssuedUGB CONSTRUCTION INCFence
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
05/07/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/10/2026Fail-Final PL - Up to 3 Requested FloorsFailView ↗
03/23/2026Fail-Final PL - Up to 3 Requested FloorsFailView ↗
12/31/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
12/30/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 29
DateRequirementInspectorRole
11/14/2023Footing and FoundationFAHAD FATEHprogress
11/14/2023Structural Stability – Alterations of existing buildingsFAHAD FATEHspecial
11/14/2023FinalFAHAD FATEHprogress
11/14/2023Subsurface Conditions – Fill Placement & In-Place DensityFAHAD FATEHspecial
11/14/2023UnderpinningFAHAD FATEHspecial
11/14/2023Subsurface Investigations (Borings/Test Pits)FERAS AYOUBspecial
10/09/2023Duct leakage testing, insulation and designFAHAD FATEHenergy_progress
09/28/2023Exterior Insulation and Finish Systems (EIFS)FAHAD FATEHspecial
06/21/2023Sprinkler SystemsFAHAD FATEHspecial
06/21/2023Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
08/04/2022Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
08/04/2022Interior lighting powerFAHAD FATEHenergy_progress
08/04/2022Ventilation and air distribution systemFAHAD FATEHenergy_progress
08/04/2022MeteringFAHAD FATEHenergy_progress
08/04/2022Energy Code Compliance InspectionsFAHAD FATEHprogress
08/04/2022Fire-Resistance Rated ConstructionFAHAD FATEHprogress
08/04/2022HVAC-R and service water piping design and insulationFAHAD FATEHenergy_progress
08/04/2022Air barrier - visual inspectionFAHAD FATEHenergy_progress
08/04/2022Fenestration areasFAHAD FATEHenergy_progress
08/04/2022Maintenance informationFAHAD FATEHenergy_progress
08/04/2022Fenestration air leakageFAHAD FATEHenergy_progress
08/04/2022HVAC-R and service water heating equipmentFAHAD FATEHenergy_progress
08/04/2022Fenestration and door U-factor and product ratingsFAHAD FATEHenergy_progress
08/04/2022Insulation placement and R valuesFAHAD FATEHenergy_progress
08/04/2022HVAC-R and service water heating system controlsFAHAD FATEHenergy_progress
Latest 25 of 29.
▾Documents — 67 on file (BIS + DOB NOW)
▸Plans & Drawings9
▸DOB NOWPlans/Sketch9
08/26/2026B00782534-S4Request digital key ↗
08/26/2026B00782534-I1Request digital key ↗
08/26/2026B00816725-I1Request digital key ↗
Showing 3 of 9 on file for this type
▸Applications & Permits4
▸BISPLAN / WORK APPROVAL APPLICATION3
06/26/2024322106706Open ↗
12/08/2022322106706Open ↗
10/11/2022322106706Open ↗
▸BISWORK PERMIT APPLICATION1
12/12/2024322106706Open ↗
▸Zoning, Tax Lot & Property Records3
▸DOB NOWZD1: DOB Zoning Diagram1
08/13/2026B00782534-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026B00782534-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)1
08/13/2026B00782534-I1Open ↗
▸Seals & Professional Certifications19
▸DOB NOWDPL-1: Design Professional Seal & Signature9
08/26/2026B00782534-S5Open ↗
08/26/2026B00782534-S1Open ↗
08/26/2026B00782534-S2Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature6
08/25/2026B00782534-S6Open ↗
08/25/2026B00782534-S6Open ↗
08/25/2026B00782534-S6Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWProgress Inspector Seal & Signature3
08/25/2026B00782534-S6Open ↗
08/25/2026B00782534-I1Open ↗
08/25/2026B00782534-I1Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION1
10/11/2022322106706Open ↗
▸Trade Schedules & Equipment3
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)2
08/13/2026B00782534-S2Open ↗
08/13/2026B00782534-I1Open ↗
▸BISSEWER/HOUSE CON SIGNOFF: DEP HC 0211
12/12/2024322106706Open ↗
▸Safety & Tenant Protection5
▸DOB NOWStreet Tree Checklist2
08/26/2026B00782534-I1Open ↗
08/15/2026B00782534-S2Open ↗
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM1
10/11/2022322106706Open ↗
▸BISSRO MD ANTI-HARASSMENT CHECKLIST1
10/11/2022322106706Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026B00782534-S2Open ↗
▸Environmental & Asbestos1
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP20/21/5)1
12/12/2024322106706Open ↗
▸Inspections & Test Reports6
▸DOB NOWSOIL REPORT3
08/13/2026B00782534-S2Open ↗
08/13/2026B00782534-S5Open ↗
08/13/2026B00782534-S6Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram3
08/13/2026B00782534-S2Open ↗
08/13/2026B00782534-S5Open ↗
08/13/2026B00782534-S6Open ↗
▸Approvals, Objections & Sign-offs6
▸BISLETTERS - SUPPORTING DOCUMENTATION6
12/12/2024322106706Open ↗
12/12/2024322106706Open ↗
12/12/2024322106706Open ↗
Showing 3 of 6 on file for this type
▸Cost, Insurance & Ownership2
▸BISAcord 25 (Acord Certificate of Liability Insurance)1
12/12/2024322106706Open ↗
▸BISPROJECT-SPECIFIC GL INSURANCE1
12/12/2024322106706Open ↗
▸Filing & Intake Forms1
▸BISEFILING COVER SHEET1
10/11/2022322106706Open ↗
▸Other Documents8
▸DOB NOWSite Survey: Initial2
08/13/2026B00782534-S2Open ↗
08/13/2026B00782534-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/13/2026B00782534-S2Open ↗
08/13/2026B00782534-I1Open ↗
▸DOB NOWAdjoining Owners Notification2
08/13/2026B00782534-S2Open ↗
08/13/2026B00782534-S5Open ↗
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
12/12/2024322106706Open ↗
▸DOB NOWProperty Ownership Certification1
08/26/2026B00782534-I1Open ↗