← Back
Two family frame
155-26 114 ROAD
QUEENS · Baisley Park · BIN 4264163
💬 Discuss this project
1925Year Built
2Stories
B2Building Class
R3-1Zoning
—Gross Floor Area
2Units
Two family frame · 0.5 FAR built · Flood zone X
Locations of Work
Electrical
Roof2p · 1 filing · 11 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
SILVERSPRING EQUITIES503/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MOMENTUM SOLAR101/08/2024
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SHAHRISH SHUVO ENGINEERIN8524101/08/2024
Building Lifecycle
All (9)Filed (1)Permit Issued (1)Objection (2)Special Inspection (5)
02/01/2024
Permit issued — Solar
Q00983330-I1-SL
01/23/2024
Objection resolved — Addressed
01/16/2024
Objection raised — Other
01/08/2024
Filed — Alteration
Installation of solar panels; Rooftop, Grid tied, Railed, 13 Panels, 5.2 KW
Q00983330-I1
12/28/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Shahrish Shuvo
12/28/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
Shahrish Shuvo
12/28/2023
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
12/28/2023
Special inspection requirement — Final
Mina Makar
12/28/2023
Special inspection requirement — Air barrier - visual inspection
Mina Makar
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarPermit IssuedMOMENTUM SOLAR02/01/2024
BISPLISSUEDTRI CITY WATER INC03/17/2006
BISEQISSUEDJULIO CONSTRUCTION01/19/2006
BIS—ISSUEDJULIO CONSTRUCTION01/19/2006
2 projects · most recent 03/05/2024
FiledStatusContractorScope
03/05/2024CompleteISLAND ELECTRIC CORP—
01/08/2024CompleteISLAND ELECTRIC CORP—
1 project · most recent 01/08/2024
FiledStatusContractorScope
01/08/2024Permit IssuedMOMENTUM SOLAR13 panels, 5.2 kw, 229 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
12/28/2023Fire-Resistant Penetrations and JointsShahrish Shuvospecial
12/28/2023Structural Stability – Alterations of existing buildingsShahrish Shuvospecial
12/28/2023Energy Code Compliance InspectionsMina Makarprogress
12/28/2023FinalMina Makarprogress
12/28/2023Air barrier - visual inspectionMina Makarenergy_progress
▾Documents — 13 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/23/2026Q00983330-P1Request digital key ↗
08/23/2026Q00983330-I1Request digital key ↗
▸Seals & Professional Certifications8
▸DOB NOWProgress Inspector Seal & Signature4
09/01/2026Q00983330-I1Open ↗
09/01/2026Q00983330-I1Open ↗
08/28/2026Q00983330-P1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/13/2026Q00983330-P1Open ↗
08/13/2026Q00983330-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
09/01/2026Q00983330-I1Open ↗
08/28/2026Q00983330-P1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/23/2026Q00983330-I1Open ↗
08/13/2026Q00983330-P1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q00983330-I1Open ↗