| Owner | Filings | Most Recent |
|---|---|---|
| NGKF | 27 | 09/25/2026 |
| THOR EQUITIES | 4 | 07/08/2026 |
| RVART OWNER LLC | 3 | 03/22/2026 |
| JOYCE THEATER FOUNDATION, INC. | 7 | 03/22/2026 |
| RVART | 10 | 03/21/2026 |
| SIERRA REAL ESTATE | 13 | 03/21/2026 |
| PHOENIX BRIDGING INC DBA PHOENIX | 1 | 03/21/2026 |
| NEWMARK | 3 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 03/15/2023 | $60.0M | — | — → — | $3,892/sf building |
| 11/04/2016 | $93.0M | — | JENSEN 155 MERCER OWNER LLC → THOR ASB 155 MERCER LLC | $6,032/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| GILSANZ MURRAY STEFICEK LLP | 4 | 09/11/2026 |
| WELLWORTH CONSULTING LLC | 5 | 07/03/2024 |
| JG NEUKOMM ARCHITECTURE | 3 | 06/17/2024 |
| ABS ENGINEERING, PLLC | 8 | 06/12/2024 |
| SALVATOR A. CARADONNA JR. | 1 | 03/13/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| OUTSOURCE CONSULTANTS, INC. | 14 | 03/21/2026 |
| UNITED SAFETY CONSULTANTS | 5 | 03/21/2026 |
| ALL IN PERMIT CONSULTANTS | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SCHIMENTI CONSTRUCTION CO | General Contractor | 4 | 07/08/2026 |
| SPRING SCAFFOLDING LLC | General Contractor | 3 | 07/08/2026 |
| SETANTA INC | General Contractor | 3 | 03/21/2026 |
| SATO CONSTRUCTION CO.INC | General Contractor | 1 | 09/25/2026 |
| SEAN COAKLEY P & H INC | Plumbing | 1 | 07/08/2026 |
| JAVIER VALERA ACERO | Electrical | 1 | 03/21/2026 |
| NEPTUNE SIGNS AWNINGS | Scaffold | 1 | 07/08/2026 |
| MEGA PLBG CORP | Fire Protection | 1 | 07/08/2026 |
| SEAN COAKLEY P & H INC | Fire Protection | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| GILSANZ MURRAY STEFICEK | 240 | 3 | 07/26/2024 |
| ABS ENGINEERING, PLLC | 4835 | 8 | 06/12/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Permit Issued | SATO CONSTRUCTION CO.INC | 09/24/2026 |
| DOB NOW | Supported Scaffold | Signed-off | SPRING SCAFFOLDING LLC | 06/20/2024 |
| DOB NOW | Sprinklers | Signed-off | SEAN COAKLEY P & H INC | 05/02/2024 |
| DOB NOW | Plumbing | Signed-off | SEAN COAKLEY P & H INC | 04/22/2024 |
| DOB NOW | Construction Fence | Signed-off | SPRING SCAFFOLDING LLC | 04/18/2024 |
| DOB NOW | Mechanical Systems | Signed-off | SCHIMENTI CONSTRUCTION CO | 04/17/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | SPRING SCAFFOLDING LLC | 04/17/2024 |
| DOB NOW | Structural | Signed-off | SCHIMENTI CONSTRUCTION CO | 02/15/2024 |
| DOB NOW | General Construction | Signed-off | SCHIMENTI CONSTRUCTION CO | 02/09/2024 |
| DOB NOW | Sprinklers | Signed-off | REAL PLUMBING CORP | 10/23/2023 |
| DOB NOW | General Construction | Signed-off | SETANTA INC | 10/11/2023 |
| DOB NOW | Sign | Signed-off | NEPTUNE SIGNS&AWNINGS INC | 03/15/2018 |
| BIS | — | ISSUED | SCHIMENTI CONSTRUCTION CO | 05/06/2024 |
| BIS | MH | ISSUED | DANNA BROTHERS CONTRACTOR | 01/07/2019 |
| BIS | — | ISSUED | EXA USA,CORP | 02/12/2018 |
| BIS | EQ | ISSUED | EXA USA,CORP | 01/09/2018 |
| BIS | MH | ISSUED | EXA USA,CORP | 01/09/2018 |
| BIS | EQ | ISSUED | ARSENAL SCAFFOLD INC | 04/04/2017 |
| BIS | EQ | ISSUED | ARSENAL SCAFFOLD INC | 03/31/2017 |
| BIS | EQ | ISSUED | ARSENAL SCAFFOLD INC | 03/23/2017 |
| BIS | EQ | ISSUED | ARSENAL SCAFFOLD INC | 03/23/2017 |
| BIS | EQ | ISSUED | ARSENAL SCAFFOLD INC | 03/23/2017 |
| BIS | SP | ISSUED | A + SPRINKLER CORP | 02/23/2017 |
| BIS | PL | ISSUED | A PLUS PLUMBING CORP | 02/23/2017 |
| BIS | MH | ISSUED | EXA USA,CORP | 02/21/2017 |
| BIS | EQ | ISSUED | EXA USA,CORP | 01/13/2017 |
| BIS | — | ISSUED | EXA USA,CORP | 01/13/2017 |
| BIS | EQ | ISSUED | ARSENAL SCAFFOLD INC | 04/27/2016 |
| BIS | EQ | ISSUED | ARSENAL SCAFFOLD INC | 04/27/2016 |
| BIS | EQ | ISSUED | ARSENAL SCAFFOLD INC | 04/08/2016 |
| BIS | EQ | ISSUED | ARSENAL SCAFFOLD INC | 04/07/2016 |
| BIS | EQ | ISSUED | ARSENAL SCAFFOLD INC | 04/07/2016 |
| BIS | — | ISSUED | EXA USA,CORP | 01/11/2016 |
| BIS | EQ | ISSUED | EXA USA,CORP | 01/11/2016 |
| BIS | SP | ISSUED | A + SPRINKLER CORP | 08/27/2015 |
| BIS | — | ISSUED | EXA USA,CORP | 06/17/2015 |
| BIS | EQ | ISSUED | EXA USA,CORP | 06/17/2015 |
| BIS | EQ | ISSUED | ARSENAL SCAFFOLD INC | 04/23/2015 |
| BIS | EQ | ISSUED | ARSENAL SCAFFOLD INC | 04/21/2015 |
| BIS | EQ | ISSUED | ARSENAL SCAFFOLD INC | 04/15/2015 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/29/2026 | Permit Issued | LIVE WIRE ELECTRIC 1 LLC | General Wiring |
| 03/30/2026 | Cancelled | LIVE WIRE ELECTRIC 1 LLC | 2 meters, 2 new_meters |
| 01/14/2026 | Complete | LIVE WIRE ELECTRIC 1 LLC | — |
| 11/17/2025 | Complete | LIVE WIRE ELECTRIC 1 LLC | — |
| 11/17/2025 | Complete | LIVE WIRE ELECTRIC 1 LLC | — |
| 10/29/2025 | Cancelled | LIVE WIRE ELECTRIC 1 LLC | — |
| 10/29/2025 | Cancelled | LIVE WIRE ELECTRIC 1 LLC | — |
| 10/29/2025 | Cancelled | LIVE WIRE ELECTRIC 1 LLC | — |
| 04/28/2025 | Complete | LIVE WIRE ELECTRIC 1 LLC | General Wiring |
| 04/11/2024 | Complete | TOP SHELF ELECTRIC CORP | — |
| 02/27/2018 | Complete | ALEF ELEC'L CONTR'G INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/11/2026 | Permit Issued | SATO CONSTRUCTION CO.INC | Steel, Concrete, Masonry |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/15/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 07/30/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/25/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 07/23/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 06/06/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/06/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 04/19/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 04/16/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 04/16/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/16/2026 | Final | Max Lee | progress |
| 03/16/2026 | Post-installed Anchors | Max Lee | special |
| 03/16/2026 | Structural Stability – Alterations of existing buildings | Max Lee | special |
| 03/16/2026 | Structural Steel - Welding | Max Lee | special |
| 03/16/2026 | Structural Steel - High Strength Bolting | Max Lee | special |
| 03/16/2026 | Concrete - Cast-In-Place | Max Lee | special |
| 03/16/2026 | Structural Steel - Details | Max Lee | special |
| 03/16/2026 | Masonry | Max Lee | special |
| 03/16/2026 | Sprayed fire-resistant materials | Max Lee | special |
| 07/29/2024 | Concrete - Cast-In-Place | Philip Murray | special |
| 07/29/2024 | Post-installed Anchors | Philip Murray | special |
| 07/29/2024 | Structural Stability – Alterations of existing buildings | Philip Murray | special |
| 07/29/2024 | Structural Steel - Welding | Philip Murray | special |
| 07/29/2024 | Structural Cold-Formed Steel | Philip Murray | special |
| 07/29/2024 | Structural Steel - Details | Philip Murray | special |
| 07/29/2024 | Final | Philip Murray | progress |
| 07/25/2024 | Concrete - Cast-In-Place | Philip Murray | special |
| 07/25/2024 | Post-installed Anchors | Philip Murray | special |
| 07/25/2024 | Structural Cold-Formed Steel | Philip Murray | special |
| 07/25/2024 | Structural Stability – Alterations of existing buildings | Philip Murray | special |
| 07/25/2024 | Structural Steel - Details | Philip Murray | special |
| 07/25/2024 | Structural Steel - Welding | Philip Murray | special |
| 07/25/2024 | Final | Philip Murray | progress |
| 06/27/2024 | Post-installed Anchors | Alex Schwartz | special |
| 06/27/2024 | Sprinkler Systems | Alex Schwartz | special |