| Owner | Filings | Most Recent |
|---|---|---|
| BRUKLYN BUILDERS | 55 | 07/08/2026 |
| OWNERS REP | 10 | 07/08/2026 |
| 155 SMITH STREET LLC | 2 | 03/22/2026 |
| BK DEVELOPERS | 1 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 03/30/2023 | $3.0M | — | 155 SMITH LLC → 155 SMITH STREET LLC | $321/sf building |
| 03/09/2021 | $2.0M | — | — → — | $217/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| LEANDRO NILS DICKSON ARCHITECT, LLC | 11 | 11/25/2024 |
| ADVANCED ENGINEERING & INSPECT. PLL | 5 | 01/15/2024 |
| PAUL PERDEK, PROF. ENG. PLLC | 4 | 06/15/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| EXPEDITING 4 U | 11 | 03/21/2026 |
| BRUKLYN BUILDERS | 6 | 03/21/2026 |
| AE DESIGN SOLUTION | 2 | 03/21/2026 |
| BMG GROUP USA | 5 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| BRUKLYN BUILDERS INC | General Contractor | 17 | 07/08/2026 |
| CORE SCAFFOLD SYSTEMS INC. | General Contractor | 5 | 07/08/2026 |
| PRIME PIPING & HEATING IN | Fire Protection | 1 | 07/08/2026 |
| MPI PLUMBING CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HRF SERVICES CORP | 5616 | 15 | 11/25/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Supported Scaffold | Signed-off | BRUKLYN BUILDERS INC | 11/26/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | BRUKLYN BUILDERS INC | 11/26/2024 |
| DOB NOW | Sprinklers | Signed-off | A M B MECHANICAL INC | 02/20/2024 |
| DOB NOW | Plumbing | Signed-off | YG SERVICES INC | 08/02/2023 |
| DOB NOW | Mechanical Systems | Signed-off | BRUKLYN BUILDERS INC | 07/05/2023 |
| DOB NOW | Structural | Signed-off | BRUKLYN BUILDERS INC | 06/22/2023 |
| DOB NOW | Foundation | Signed-off | BRUKLYN BUILDERS INC | 06/22/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | CORE SCAFFOLD SYSTEMS INC | 06/15/2023 |
| DOB NOW | General Construction | Permit Issued | BRUKLYN BUILDERS INC | 06/07/2023 |
| DOB NOW | Foundation | Signed-off | BRUKLYN BUILDERS INC | 06/05/2023 |
| DOB NOW | Support of Excavation | Signed-off | BRUKLYN BUILDERS INC | 06/05/2023 |
| DOB NOW | Supported Scaffold | Signed-off | CORE SCAFFOLD SYSTEMS INC | 05/09/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | CORE SCAFFOLD SYSTEMS INC | 05/09/2023 |
| DOB NOW | Construction Fence | Signed-off | BRUKLYN BUILDERS INC | 05/05/2023 |
| BIS | PL | ISSUED | DELPHI PLBG. & HTG., INC | 05/16/2011 |
| BIS | PL | ISSUED | BEST PLUMBING & HVAC INC | 05/26/2010 |
| BIS | MH | ISSUED | NJ PAPPAS CONSTRUCTION CO | 04/16/2004 |
| BIS | MH | ISSUED | N J PAPPAS CONSTRUCTION CO | 08/07/2003 |
| BIS | PL | ISSUED | ACE CONTRACTING INC. | 06/19/2003 |
| BIS | — | ISSUED | N J PAPPAS CONST CO | 05/23/2003 |
| BIS | EQ | ISSUED | N J PAPPAS CONST CO | 05/23/2003 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/25/2024 | Signed-off | YG SERVICES INC | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/11/2023 | Complete | POWER DIRECT ELECTRIC INC | General Wiring |
| 08/24/2023 | Complete | POWER DIRECT ELECTRIC INC | — |
| 05/05/2023 | Complete | SOLAS ELECTRICAL CORP | — |
| 10/05/2019 | Complete | MACK ELECTRICAL INC | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/25/2024 | Signed-off | A M B MECHANICAL INC | 3 scope_items |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/29/2024 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 07/02/2024 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 04/10/2024 | Pass-Final SP - Up to 9 Requested Floors | Pass | View ↗ |
| 03/06/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 02/26/2024 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 02/23/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 11/29/2023 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 11/20/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/13/2023 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 11/09/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/30/2023 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 09/05/2023 | Pass-Final PL - Underground | Pass | View ↗ |
| 08/09/2023 | Pass-Final PL - Underground | Pass | View ↗ |
| 06/22/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 06/22/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/22/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/09/2025 | Metering | FAHAD FATEH | energy_progress |
| 04/09/2025 | Protection of exposed foundation insulation | FAHAD FATEH | energy_progress |
| 04/09/2025 | Fenestration areas | FAHAD FATEH | energy_progress |
| 04/09/2025 | Lighting controls | FAHAD FATEH | energy_progress |
| 04/09/2025 | Lighting in dwelling units | FAHAD FATEH | energy_progress |
| 04/09/2025 | Fenestration air leakage | FAHAD FATEH | energy_progress |
| 04/09/2025 | Air barrier - visual inspection | FAHAD FATEH | energy_progress |
| 04/09/2025 | Insulation placement and R values | FAHAD FATEH | energy_progress |
| 04/09/2025 | Exterior lighting power | FAHAD FATEH | energy_progress |
| 04/09/2025 | Maintenance information | FAHAD FATEH | energy_progress |
| 04/09/2025 | Fenestration and door U-factor and product ratings | FAHAD FATEH | energy_progress |
| 04/09/2025 | Structural Stability – Alterations of existing buildings | FAHAD FATEH | special |
| 04/09/2025 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 04/09/2025 | Exterior Insulation and Finish Systems (EIFS) | FAHAD FATEH | special |
| 04/09/2025 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 04/09/2025 | Fire-Resistance Rated Construction | FAHAD FATEH | progress |
| 04/09/2025 | Interior lighting power | FAHAD FATEH | energy_progress |
| 11/21/2024 | Fenestration and door U-factor and product ratings | FAHAD FATEH | energy_progress |
| 11/21/2024 | Metering | FAHAD FATEH | energy_progress |
| 11/21/2024 | Insulation placement and R values | FAHAD FATEH | energy_progress |
| 11/21/2024 | Maintenance information | FAHAD FATEH | energy_progress |
| 11/21/2024 | Protection of exposed foundation insulation | FAHAD FATEH | energy_progress |
| 11/21/2024 | Air barrier - visual inspection | FAHAD FATEH | energy_progress |
| 11/21/2024 | Fenestration areas | FAHAD FATEH | energy_progress |
| 11/21/2024 | Exterior lighting power | FAHAD FATEH | energy_progress |